Thor Explorations Announces Third Quarter 2024 Financial and Operating Results, for the
Thor Explorations Announces Third Quarter
2024 Financial and Operating Results, for the
Three Months Ending September 30, 2024
Vancouver, British Columbia--(Newsfile Corp. - November 11, 2024) - Thor Explorations Ltd. (TSXV:
THX) (AIM: THX) ("Thor Explorations", "Thor" or the "Company") is pleased to provide an operational
and financial review for its Segilola Gold mine, located in Nigeria ("Segilola"), and for the Company's
mineral exploration properties located in Nigeria, Senegal and Cote D'Ivoire for the three months to
September 30, 2024 (the "Quarter", the "Period" or "Q3").
The Company's Unaudited Condensed Consolidated Financial Statements together with the notes
related thereto, as well as the Management's Discussion and Analysis for the three months ended
September 30, 2024 are available on Thor Explorations' website at:
https://thorexpl.com/investors/financials/
.
All figures are in US dollars ("US$") unless otherwise stated.
Q3 2024 Financial Highlights
18,167 ounces ("oz") of gold sold with an average gold price of US$2,328 per oz.
Cash operating cost of US$585 per oz sold and all-in sustaining cost ("AISC") of US$766 per oz
sold.
Revenue of US$40.2 million (Q3 2023: US$36.6 million).
EBITDA of US$27.4 million (Q3 2023: US$10.5 million).
Net profit of US$17.5 million (Q3 2023: US$0.9 million).
Senior debt facility reduced to US$3.9 million as at September 30, 2024.
This debt is scheduled to be fully repaid by the end of Q4 2024
Transitioned from a net debt position of US$2.7 million as at June 30, 2024 to a net cash position
of US$2.7 million as at September 30, 2024.
Operational Highlights
Segilola Production
Gold ("Au") Poured for the Period totalled 20,110oz
Mill feed grade was 3.22 grammes per tonne ("g/t") gold with recovery at 88.5%. The lower
recovery was due to a delayed change in mill liner during the period.
201,958 tonnes ("t") of ore were processed, an increase in productivity levels by 16%
compared to Q2, equivalent to a throughput rate of 2,195t per day, with no significant
downtime periods.
The process plant achieved a further reduction of the gold in circuit by 1,614oz of Au.
The stockpile balance increased by 13% to 1,329,007t of ore at an average grade of 0.94g/t as
this was mined during shortfalls resulting from events that occurred during the Quarter.
The significant stockpile available (more than one year of process plant supply) offers
flexibility and low risk for future process plant production.
Mining rates were lower than Q2 2024 due to the previously reported fly-rock incident. Improved
controlled blasting practices are now in place to avoid a recurrence.
Severe September weather period brought over 415 millimetres of rain in 12 days, surpassing in-
pit pumping capacity and contingency plans which delayed high-grade ore access to Q4 2024.
The Company has since increased pit pumping capacity.
Segilola Exploration
The priority of the Company's exploration strategy is extending the Segilola mine life through
delineation of potential additional underground resources at Segilola.
An initial 12 hole drilling program continued during the period with initial positive drill results
received from the first two holes of 3.0 m grading 11.24g/t Au from 294m and 1.5m grading 3.22g/t
Au from 269m.
In addition to the Segilola Underground Drilling Program, additional geochemical sampling
continued at near mine open pit targets.
Douta
RC drilling activities were completed during the period. The program was focussed on increasing
the percentage of oxide resources at the Makosa East Prospect, which runs parallel to the main
Makosa mineralised trend and is additional to the current mineral resource. Additional infill drilling
was completed at the Makosa North, Mansa and Maka prospects.
Remaining Pre-Feasibility Study ("PFS") and Mineral Resource Estimate update workstreams are
being completed, with a target completion in Q4 2024.
Cote D'Ivoire
During the Quarter Thor expanded its operations into Cote d'Ivoire following the signing of a
binding agreement with Endeavour Mining Corporation to acquire a 100% interest in the Guitry
Gold Project for US$100,000 in cash and a 2% Net Smelter Royalty.
Earlier in 2024 the Company entered into an option agreement with Goldridge Resources SARL to
acquire an 80% interest in the Boundiali Exploration permit, an early stage gold exploration project
located in north west Cote d'Ivoire.
Lithium
Exploration activities during the quarter comprised of geological mapping that focused on
generating targets within Newstar-owned exploration permits.
Environment, Social and Governance
Q3 projects under the Community Development Agreements included awarding 26 school
scholarships, quarterly elderly palliative deliveries, and initiating tenders for road and school
improvements.
ESG data, aligned with Global Reporting Initiative standards, is being compiled for 2023-2024 and
uploaded to the Onyen ESG system. This will improve annual comparisons for energy, water, and
waste intensity per oz Au.
One Lost Time Injury (LTI) occurred due to a workshop incident, leading to targeted training on
hand injuries.
In Senegal, information is being compiled for the baseline of an EIA for the Douta project and
included consultations with local village elders and government bodies to align with regional
economic development plans.
Outlook
Production guidance of 85,000oz for 2024 with an AISC guidance of US$$800 - US$900 per oz.
Advance exploration programmes across the portfolio, including near mine, underground and
regional projects at Segilola, extension and infill programmes at Douta, assessment of regional
potential targets in Nigeria and joint venture options on potential targets.
Continue to advance the Douta project towards an updated Mineral Resource Estimate and PFS.
Segun Lawson, President & CEO, stated:
"Firstly, it is important to provide an update on the ongoing Osun State tax dispute. The Minister of
Mines in Nigeria commissioned a fact-finding committee (the "Committee") to investigate the claims
made by the Osun State Government, with the findings to be reported within 7 days. The Committee
provided Osun State with an extension to submit evidence of its claims by 8
th
November and the
Company expects the Minister to disclose its findings in the near future. We look forward to the
findings of the Committee and remain confident regarding our position on all the allegations made by
Osun State.
"We are pleased to have profitably navigated through a challenging quarter, during which a fly-rock
incident and severe weather disruptions at Segilola impeded operations. We produced just over
20,000 ounces and sold 18,167 ounces of gold achieving an average gold price of US$2,328 per
ounce at a cash operating cost of US$585 per ounce sold, and an AISC of US$766 per ounce sold.
We have reduced our senior debt facility to US$3.9 million, which is on track for full repayment in Q4
and notably, we have transitioned from a net debt position to a net cash position.
"On the exploration front, we have had a positive start to our Segilola Underground Exploration
programme, which is ongoing with a planned 12-hole drilling programme. We look forward to receiving
the remaining results.
"At Douta, we have now completed our fieldwork and received all the required drilling results for an
updated resource and PFS. We are at the final stages of completing the remaining workstreams for
the PFS with completion targeted for Q4 2024.
"The Quarter also marked our strategic entry into Cote d'Ivoire, with the acquisition of the Guitry and
Boundiali projects, which will further diversify and strengthen our portfolio in West Africa as we look to
unlock value at these projects.
"We look forward to completing the year with another profitable quarter whilst delivering further value
through exploration upside in Nigeria and through advancing the Douta Project to its next milestone."
About Thor Explorations
Thor Explorations Ltd. is a mineral exploration company engaged in the acquisition, exploration,
development, and production of mineral properties located in Nigeria, Senegal, and Burkina Faso. Thor
Explorations holds a 100% interest in the Segilola Gold Project located in Osun State, Nigeria and has a
70% economic interest in the Douta Gold Project located in south-eastern Senegal. Thor Explorations
trades on AIM and the TSX Venture Exchange under the symbol "THX".
THOR EXPLORATIONS LTD.
Segun Lawson
President & CEO
For further information please contact:
Thor Explorations Ltd
Email:
Canaccord Genuity (Nominated Adviser & Broker)
Henry Fitzgerald-O'Connor / James Asensio / Harry Rees
Tel: +44 (0) 20 7523 8000
Hannam & Partners (Broker)
Andrew Chubb / Matt Hasson / Jay Ashfield / Franck Nganou
Tel: +44 (0) 20 7907 8500
BlytheRay (Financial PR)
Tim Blythe / Megan Ray / Said Izagaren
Tel: +44 207 138 3203
Yellow Jersey PR (Financial PR)
Charles Goodwin / Shivantha Thambirajah / Soraya Jackson
Tel:
+44 (0) 20 3004 9512
NOT FOR DISSEMINATION IN THE UNITED STATES OR FOR
DISTRIBUTION TO U.S. WIRE SERVICES
To view the source version of this press release, please visit
https://www.newsfilecorp.com/release/229440