Thor Announces Construction Update at Segilola GOLD MINE

Mine Development & Operations

NEWS RELEASE

NOT FOR DISSEMINATION IN THE UNITED STATES OR FOR

DISTRIBUTION TO U.S. WIRE SERVICES

FOR IMMEDIATE RELEASE TSXV: THX

August 10, 2020 Shares Outstanding: 621,195,975

Vancouver, British Columbia

THOR ANNOUNCES CONSTRUCTION UPDATE AT SEGILOLA GOLD MINE

Thor Explorations Ltd. (TSX VENTURE: THX) (“ Thor” or the “Company”) is pleased to announce that

concrete has been poured on the Segilola process plant site, construction and procurement are

progressing on schedule and on budget with first gold pour expected in Q2 2021.

Highlights:

 First concrete has been poured at the process plant

 Water Storage Facility is at final height and is starting to fill

 Detailed design 80% complete

 Main Camp buildings are at roof level

 Procurement 60% complete, with SAG and Ball mills scheduled for delivery in early in 2021

 Over 200 members of the local communities have been employed by the project

 No Lost Time Injuries to date

 COVID -19 monitoring and mitigation measures continue at site

Segun Lawson, President & CEO, stated:” Our construction team and EPC contractor, Norinco

International Cooperation Limited, are continuing to deliver on our targets in a challenging operating

environment due to the COVID-19 pandemic. I cannot speak highly enough of the professionalism being

displayed day in and day out by our workforce and contractors.”

Figure 1: Segilola Gold Project, Osun, Nigeria

Construction Update

The first concrete has been poured by Norinco International Ltd (“Norinco”), the LSTK EPC Contractor,

for the foundations for the plant at Segilola and the CIP tank foundation pouring is in process.

Figure 2: Leach tank construction progress

The Water Storage Facility has been constructed to final height and the spillway construction is

progressing. The facility is filling well and is expected to reach full capacity before the end of the year.

Figure 3: Water Storage Dam and Water Storage Facility

Construction at the main camp is continuing with the main buildings at roof level. Handover of the

administration, technical services, dining facilities, clinic and recreational facilities is expected in Q4

2020.

Figure4: Camp and main buildings

Procurement is 60% complete, with vendors re-confirming delivery times. The first shipment of materials

recently arriving at Lagos port. Long lead items are scheduled to arrive on site in Q4 2020 and Q1 2021.

Local employment is a key aspect of the Company’s development approach and during this initial period

over 360 jobs have been created, with 92% being Nigerian nationals and approximately 56% being from

the local communities.

The Company has a strong and proactive approach to health and safety and to date the Project

completed over 220,000 man hours with no lost time injuries.

COVID-19

As the COVID-19 (Coronavirus) pandemic continues to have a global effect, the health and safety of

our employees, communities and contractors are our utmost priority. The Company is taking steps and

precautions to address the effects of the pandemic responsibly and to limit potential exposure to the

rapidly changing situation. Measures have been put in place to monitor and mitigate against the spread

of COVID -19 which includes testing, monitoring, and all-round practices of cleanliness and washing to

ensure any instances of COVID-19 are instantly monitored and identified. A handbook has been

provided for all personnel and both HSE teams from Thor and Norinco continue to report on this on a

daily basis following constant monitoring. All government and regulatory rules are also adhered to.

Exploration

Both the contracted RC and diamond rigs have arrived on site and exploration drilling has commenced

in parallel with construction. Both rigs will be running concurrently and will be targeting the down dip

extension of the Segilola Deposit and satellite targets identified within the licence. The first drilling

results are expected in mid-September.

Qualified Person

The above information has been prepared under the supervision of Alfred Gillman (Fellow AusIMM,

CP), who is designated as a “qualified person” under National Instrument 43-101 and has reviewed

and approves the content of this news release. He has also reviewed QA/QC, sampling, analytical

and test data underlying the information.

Further details can be found on the Company’s website: www.thorexpl.com

About Thor

Thor Explorations Ltd. is a Canadian mineral exploration company engaged in the acquisition,

exploration and development of mineral properties located in Nigeria, Senegal and Burkina Faso. Thor

holds a 100% interest in the Segilola Gold Project located in Osun State of Nigeria and a 70% interest

in the Douta Gold Project located in south-eastern Senegal. Thor also holds a 49% interest in the Bongui

and Legue gold permits located in Houndé greenstone belt, south west Burkina Faso. Thor trades on

the TSX Venture Exchange under the symbol “THX”.

THOR EXPLORATIONS LTD.

Segun Lawson

President & CEO

For further information please contact:

Thor Explorations Ltd

Email: [email protected]

Fig House Communications (Investor Relations)

Tel: +1 416 822 6483

Email: [email protected]

Blytheweigh

Camilla Horsfall / Megan Ray / Rachael Brooks

Tel: +44 207 138 3203

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in

the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy

of this release.

This press release does not constitute an offer to purchase securities. The securities to be offered in

the offering have not been and will not be registered under the United States Securities Act of 1933, as

amended, or any state securities laws and may not be offered or sold in the United States or to, or for

the benefit or account of, a U.S. person, except pursuant to an available exemption from such

registration requirements.

Cautionary Note Regarding Forward-Looking Statements

Except for the statements of historical fact contained herein, the information presented constitutes

“forward looking statements” within the meaning of certain securities laws, and is subject to important

risks, uncertainties and assumptions that could cause the actual results of the Company to differ

materially from the forward-looking statements. Such forward-looking statements, including but not

limited to, the Company’s ability to fully finance the Project, to bring the Project into operation or to

produce gold from the Project, and the use of the proceeds. The words “may”, “could”, “should”,

“would”, “suspect”, “outlook”, “believe”, “anticipate”, “estimate”, “expect”, “intend”, “plan”, “target” and

similar words and expressions are used to identify forward-looking information. The forward-looking

information in this news release describes the Company’s expectations as of the date of this news

release and accordingly, is subject to change after such date. Readers should not place undue

importance on forward-looking information and should not rely upon this information as of any other

date. While the Company may elect to, it does not undertake to update this information at any particular

time.