TDG GOLD Corp. Announces Opening of Baker MINE CAMP and Outlines Phase One Drill Program FOR Shasta Project, Toodoggone District, British Columbia
1
TDG Gold Corp.
Unit 1 - 15782 Marine Drive
White Rock, B.C. V4B 1E6
www.tdggold.com
TDG GOLD CORP. ANNOUNCES OPENING OF BAKER MINE CAMP AND OUTLINES PHASE ONE DRILL
PROGRAM FOR SHASTA PROJECT, TOODOGGONE DISTRICT, BRITISH COLUMBIA
White Rock, British Columbia, June 15, 2021. TDG Gold Corp (TSXV: TDG) (the “Company” or “TDG”) is
pleased to announce the opening of its Baker Mine Camp located within the road connected “Toodoggone
Production Corridor” of north-central British Columbia. With the assistance of Chu Cho Industries and in
cooperation with TDG’s neig hbour Benchmark Metals Inc., the final stretch of the Finlay-Nation forest
service road which runs from Highway 97 was cleared up to the Baker Camp during the final week of May.
TDG’s camp management team has mobilized and the 20-person camp at Baker Mine is scheduled to be
fully operational by June 28, 2021. TDG’s geological team led by VP Exploration, Andy Randell, P.Geo. , is
expected to arrive in camp by the June 24, 2021.
SHASTA EXPLORATION PROGRAM
The primary focus of TDG’s 2021 exploration is a diamond drill program at its former producing high-grade
gold-silver Shasta mine. Figure 1 below shows a map of the proposed drill locations for 2021.
Figure 1 showing the Permitted Mine Area and proposed drill hole locations for Phase 1 (green) of the
Shasta 2021 drill program.
2
TDG Gold Corp.
Unit 1 - 15782 Marine Drive
White Rock, B.C. V4B 1E6
www.tdggold.com
Of TDG’s proposed 68 drill holes in the 2021 Shasta drill program, 29 (3,855m total) are included in the
Phase 1 drill program, all of which are within the existing Permitted Mine Area (“PMA”). Phase 2 drill holes
are also largely within the PMA and are dependent on results of Phase 1 activities.
In TDG’s news release of March 03, 2021, TDG published an exploration target range for Shasta of 0.90 -
1.47 million ounces of gold -equivalent based on recompilation of historical drilling information. The
purpose of the proposed drilling is threefold: (1) to confirm the validity of historical drill assays; (2) to drill
test known extensions to the existing mineralization around the historical mine workings; and, (3) to drill
test for continuity of mineralization betwee n historically identified zones. Drilling is expected to
commence around mid-July after mapping and surface studies are complete along with relogging of the
historical core which is stacked at Shasta.
Less than 50% of the historical drill core at Shasta was assayed. TDG will attempt to reassay sections of
the historical core wherever possible. Historical drilling at Shasta was BQ diameter, whereas TDG intends
to drill NQ2 and HQ diameter core with the aim of providing larger and more representative sampling of
quartz carbonate stockwork and brecciation that exists as a mineralized halo surrounding the fault
controlled, higher grade hanging wall that was the target of the historical mine operations.
TDG aims to publish a n inaugural resource estimate for Shasta in H1 2022. All drill locations have been
selected in collaboration with Moose Mountain Technical Services in order to facilitate the calculation of
a NI 43-101 compliant resource estimate for Shasta.
BAKER EXPLORATION PROGRAM
The exploration plan for Baker will initially focus on detailed mapping, sampling and trenching within the
Baker footprint and the satellite zones , with the Baker “B Vein” being prioritized. The B Vein is situated
300 metres northeast of the historical workings and appears to have high -grade ore material remaining
in situ according to records and observations made during a site visit in October 2020 . A hand sample
collected at the B Vein site was recently assayed and returned grades of 135 grams per tonne (“g/t”) gold
(“Au”) and 5.36 percent copper. Although this is a single sample and cannot be taken as representative of
the entire B Vein, it is an encouraging result given that the sample was collected from outcrop.
The first stage of work at Baker will be led by Dr Thomas Bissig, former senior Research Associate with the
Mineral Deposit Research Unit (“MDRU”). Thomas is a co -author of a MDRU 2019 report for Geoscience
BC which considers an exploration framework for porphyry to epithermal transitions in the Toodoggone
Mineral District. Information gathered from the initial work will be used to define a drilling campaign later
in the season should it be warranted. The Permitted Mine Area includes the historical Baker Pit, and any
work outside of this will be completed under new exploration permits for the Baker- Shasta and Oxide
Peak properties.
METS EXPLORATION PROGRAM
Exploration at the Mets mining lease will focus on confirmation of grades and extent of development that
has occurred historically on site. Core from previous drill campaigns is stored at the Baker mill and will be
relogged and assayed where appropriate. New maps and surface / trench samples will be collected on site
to augment the historical data, and a new environmental baseline testing project will start in June 2021.
The Mets m ining lease covers 200 hectares and is road accessible from the Baker Mine. Between 1980
and 1992, 8,784m of diamond drilling, 2,622m of trenching and 350m of underground development were
3
TDG Gold Corp.
Unit 1 - 15782 Marine Drive
White Rock, B.C. V4B 1E6
www.tdggold.com
completed at Mets. Historical drill highlights include 9.52 g/t Au and 1.9 g/t Ag over 25.90 m and 3.57 g/t
Au and 2.36 g/t Ag over 46.40 m, including 13.93 g/t Au and 2.00 g/t Ag over 11.80 m (see TDG news
release of May 19, 2021).
Qualified Person
The technical content of this news release has been reviewed and approved by Andy Randell, PGeo., a
qualified person as defined by National Instrument 43-101.
About TDG Gold Corp.
TDG is a major mineral claim holder in the historical Toodoggone Production Corridor of north-central
British Columbia, Canada, with over 23,000 hectares of brownfield and greenfield exploration
opportunities under direct ownership or earn -in agreement. TDG’s flagship projects are the former
producing, high-grade gold-silver Shasta, Baker and Mets mines which are all road accessible, produced
intermittently between 1981 -2012, and have over 65,000 metres of historical drilling. In 2021, TDG
proposes to advance the projects through compilation of historical data, new geolo gical mapping,
geochemical and geophysical surveys, and drill testing of the known mineralization occurrences and their
extensions. TDG currently has 64,423,459 common shares issued and outstanding.
ON BEHALF OF THE BOARD
Fletcher Morgan
Chief Executive Officer
For further information:
TDG Gold Corp.,
Telephone: +1.604.536.2711
Email: [email protected]
Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies
of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.
This news release may contain certain “forward looking statements”. Forward-looking statements involve
known and unknown risks, uncertainties, assumptions and other factors that may cause the actual results,
performance or achievements of the Company to be materially different from any future results,
performance or achievements expressed or implied by the forward- looking statements. Any forward -
looking statement speaks o nly as of the date of this news release and, except as may be required by
applicable securities laws, the Company disclaims any intent or obligation to update any forward-looking
statement, whether as a result of new information, future events or results or otherwise.