Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

TAU.V ·

AISC† costs consist of mining costs, processing costs, mine-level G&A, offsite charges, royalties, sustaining capital, expansion capital, and closure costs.

Royalties & Streams

*AuEq reported for the mined materials/mill feed in mineral resource estimate and mineral reserve estimates assumes a conversion of 80:1 for Ag

to AuEq based on expected average expected recoveries of 93% Au and 86.1% Ag at US$2,000/oz Au and $24.50/oz Ag.

**AuEq production values are based on payable ounces as calculated by the financial model and have varying gold and silver recoveries by

deposit at a US$2,900/oz Au and US$35/oz Ag.

AISC† costs consist of mining costs, processing costs, mine-level G&A, offsite charges, royalties, sustaining capital, expansion capital, and

closure costs.

THESIS GOLD INC.

1050-1075 West Georgia Street

Vancouver, BC

Canada, V6E 3C9

Thesis Gold Announces Positive Prefeasibility Study for Lawyers-

Ranch Project: After-Tax NPV5% of $2.37 Billion and 54.4% IRR

All dollar amounts are in Canadian dollars (“$”) unless otherwise indicated.

Vancouver, British Columbia -- (December 1, 2025) – Thesis Gold Inc. (“Thesis” or the “Company”)

(TSXV: TAU | WKN: A3EP87 | OTCQX: THSGF) is pleased to announce positive results from an

independent Prefeasibility Study (“PFS”) for its 100% owned Lawyers -Ranch Project (“Lawyers-Ranch”

or the “Project”) in the prolific Toodoggone Mining District of British Columbia.

The PFS was prepared by Ausenco Engineering Canada ULC . (“ Ausenco”), Mining Plus Canada Ltd.

(“Mining Plus”), Knight Piésold Ltd. (“Knight Piésold”), Equilibrium Mining Inc. (“Equilibrium”), P&E

Mining Consultants Inc . (“P&E”), pHase Geochemistry Inc., Frank Wright Consulting, and SLR

Consulting Ltd. (“SLR”) in accordance with National Instrument 43 -101 – Standards of Disclosure for

Mineral Projects (“NI 43 -101”). The NI 43-101 PFS Technical Report will be filed on SEDAR + at

www.sedarplus.ca and Thesis Gold’s website www.thesisgold.com within 45 days of this announcement.

The PFS outlines a plan for developing the combined Lawyers -Ranch Project using both open pit and

underground mining methods, with ore processed at a single facility.

PFS highlights are summarized below:

• Strong Economics at US$2,900 per ounce of gold (oz Au) and US$35 per ounce of silver (oz Ag):

o Pre-tax: 73.5%, internal rate of return (“IRR”) and $3.73 billion net present value at a 5%

discount rate (“NPV5%”)

o After-tax: IRR of 54.4% and an NPV5% of $2.37 billion

o At US$4,100/oz Au and US$51/oz Ag:

 Pre-tax: 117.4% IRR and $6.86 billion NPV5%

 After-tax: 87.8% IRR and $4.36 billion NPV5%

• Strong Early Production: Strong gold-equivalent (“AuEq”)* annual production rates for the first

three years averaging 266,000 ounces**, and 187,000 ounces** over the Life of Mine (“LOM”).

• Increased Tonnes Processed, Increased Throughput Rates and Extended Mine Life: Despite the

removal of Inferred Resources from the mine plan, total tonnes processed rose by 18% (relative to the

2024 Preliminary Economic Assessment). Process plant throughput increased by 9% to 13,700 tonnes

per day (t /d) and the mine life increased to 15- years, based solely on Measured and Indicated

Resources.

• Mineral Reserve: Maiden Mineral Reserve statement with 76.16 million tonnes of ore grading 0.97

g/t Au and 28 g/t Ag for a total AuEq* grade of 1.33 g/t.

• Low All-in Sustaining Costs (“AISC†”): Average AISC† of US$1,185 per AuEq** ounce.

• Silver: Silver production accounts for approximately 23% of revenue.

*AuEq reported for the mined materials/mill feed in mineral resource estimate and mineral reserve estimates assumes a conversion of 80:1 for Ag

to AuEq based on expected average expected recoveries of 93% Au and 86.1% Ag at US$2,000/oz Au and $24.50/oz Ag.

**AuEq production values are based on payable ounces as calculated by the financial model and have varying gold and silver recoveries by

deposit at a US$2,900/oz Au and US$35/oz Ag.

AISC† costs consist of mining costs, processing costs, mine-level G&A, offsite charges, royalties, sustaining capital, expansion capital, and

closure costs.

- 2 -

• Quick Payback: The Project offers an after-tax payback period of 1.1 years at US$2,900 Au and

US$35 Ag.

• Capex: Initial capital expenditure is estimated at $ 736.2 million, with a compelling after-tax

NPV5%:initial capital ratio of 3.2:1. The initial capital estimate does not consider a potential revenue

of $91.1 million in pre -production revenue from processing stockpiles as part of the initial

commissioning and ramp-up plan.

• Project Upside: Significant project upside exists both in the potential to further optimize engineering

design through a Feasibility Study, and in the project-wide exploration potential that remains untapped.

The section entitled “Project Upside” further details the opportunities present at Lawyers-Ranch.

Dr. Ewan Webster, President and CEO, commented , “With the prefeasibility results announced today,

Thesis Gold is positioned as one of the strongest value-creation stories in the sector. An after-tax NPV

of $2.37 billion, a 54.4% IRR, and a 1.1-year payback places Lawyers-Ranch firmly among the top tier of

development-stage gold projects globally. The study strengthens the technical rigor of the project, increases

total tonnes processed, and delivers a substantially improved payback period while preserving an

exceptionally strong early-year production profile. I’m extremely proud of our team, Aus enco, and our

technical partners, whose work provides the foundation for advancing Lawyers -Ranch through permitting

and toward construction. Importantly, this is not the end of the growth story. With significant resource

expansion and discovery potential still ahead of us, we view this PFS as both a validation of what we’ve

discovered to date and as the foundation for the next phase of value creation.”

Bill Lytle, Non -Executive Chairman, added, “ I am looking forward to advancing the project through

Feasibility Study and permitting, as we look to create significant value for all our stakeholders by

responsibly developing the Ranch-Lawyers project.”

The Company will host a webcast call to discuss the results of the PFS on Monday, December 1st at 10:00

am Eastern time. To join the call: visit https://app.webinar.net/G0lQbExeaRm, or dial 1-289-815-

3444 (Toronto), or 1 (800) 715 -9871 (toll free North America ). For more details , visit

https://thesisgold.com/investors/.

PFS Project Enhancements

A comprehensive review of the 2024 PEA was undertaken to identify and incorporate optimizations that

would strengthen overall project economics as the study advanced to PFS -level engineering, cost

estimating, and confidence.

The review identified mine sequencing as the primary opportunity to strengthen Project economics.

Optimization work brought high-margin ore forward, increased mill throughput, and reshaped the

production schedule to improve the IRR and shorten the payback period. This work highlighted the

economic importance of Ranch ore, from the Ranch portion of the Project (the “Ranch Area”), the value of

prioritizing higher -grade underground feed, and the benefits of a stockpiling approach. As a result, the

Ranch Area was advanced to the first three years of production, and the underground cut -off grade was

increased to 2.2 g/t AuEq* to maximize margins.

In addition to optimized mine -sequencing of the four pits in the Lawyers portion of the Project (the

“Lawyers Area”) as well as the eight Ranch Area pits, the larger pit shells at the Lawyers Area were

*AuEq reported for the mined materials/mill feed in mineral resource estimate and mineral reserve estimates assumes a conversion of 80:1 for Ag

to AuEq based on expected average expected recoveries of 93% Au and 86.1% Ag at US$2,000/oz Au and $24.50/oz Ag.

**AuEq production values are based on payable ounces as calculated by the financial model and have varying gold and silver recoveries by

deposit at a US$2,900/oz Au and US$35/oz Ag.

AISC† costs consist of mining costs, processing costs, mine-level G&A, offsite charges, royalties, sustaining capital, expansion capital, and

closure costs.

- 3 -

subdivided into staged pushbacks to improve operational flexibility, bring additional ounces forward, and

reduce strip ratio s in the early years of the LOM . In parallel, the pro ject incorporated a 9% increase to

process plant throughput and a slight reduction in the open-pit cut-off grade over the LOM.

The PFS outlines a 15-year LOM processing 76 million tonnes, with average annual production of 266,000

AuEq** ounces in the first three years to support a rapid payback. Total life -of-mine production is 2.84

million AuEq** ounces.

The results of the PFS were compared to the 2024 PEA and are detailed in Table 1 below:

Table 1: Comparison of 2025 PFS to 2024 PEA Results

General Unit 2025 PFS 2024 PEA Change

After-Tax NPV (5%) $M 2,370 1,277 +86%

After-Tax IRR % 54.4 35.2 +55%

Payback Period yrs 1.1 2.0 -45%

Payable AuEq** koz 2,837 3,025 -6%

LOM yrs 15.2 14 +7%

After-Tax NPV:Initial Capital ratio 3.2:1 2.1:1 +52%

AISC†/AuEq** oz US$oz 1,185 1,013 +17%

Open Pit Stripping Ratio W:O 4.6 5.0 -8%

Project Upside

Opportunities to potentially further improve the project in the planned future Feasibility Study, include

the following:

• Pre-Concentration: Pre-concentration of Ranch Area ore to increase average grade and reduce

haulage costs from Ranch Area to the process plant located at the Lawyers Area site. An initial

assessment, conducted by ABH Engineering Inc. with test work performed by Tomra Mining in

Germany, shows promising results for Ranch Ore Sorting.

• Crown Pillar Recovery: The PFS did not include recovery of the crown pillar between the open

pit and underground workings. With further study there is an opportunity to increase the mineable

ore from underground without impacting the open pits.

• Pit Geotechnical Optimization: Opportunities exist to steepen portions of the Ranch pits in key

locations where ground conditions permit; additional drilling and improved rock- mass granularity

will help refine and optimize these zones.

• Construction and Commissioning Optimization: Additional opportunity exists to optimize the

construction and commissioning phase , specifically evaluating alternative sources to borrow

materials to reduce initial capital costs.

• Mine Life Extension:

o Inferred Mineral Resources from both Ranch and Lawyers are not captured within

the PFS mine plan. Upgrading the classification of these Inferred ounces through

additional drilling presents an opportunity to potentially expand the mineable materials.

o Numerous early-stage and undrilled targets exist across the entirety of the Lawyers-Ranch

tenure, and Thesis is focused on a comprehensive, systems-based approach to unlocking

additional exploration potential in an emerging porphyry district.

*AuEq reported for the mined materials/mill feed in mineral resource estimate and mineral reserve estimates assumes a conversion of 80:1 for Ag

to AuEq based on expected average expected recoveries of 93% Au and 86.1% Ag at US$2,000/oz Au and $24.50/oz Ag.

**AuEq production values are based on payable ounces as calculated by the financial model and have varying gold and silver recoveries by

deposit at a US$2,900/oz Au and US$35/oz Ag.

AISC† costs consist of mining costs, processing costs, mine-level G&A, offsite charges, royalties, sustaining capital, expansion capital, and

closure costs.

- 4 -

PFS Overview

The PFS considers a conventional truck and shovel open pit mining (“OP”) operation at the Lawyers Area,

with common equipment sizing feeding a 13 ,700 (t/d), industry standard processing plant that includes

crushing, grinding, flotation, leaching and a Merrill Crowe recovery circuit, to produce both precious metals

concentrate and gold-silver doré bullion on site.

The PFS considers a crossover to underground mining (“U/G”) using longhole stoping to feed up to 1,640

t/d from the Dukes Ridge and Cliff Creek deposits during operational years one to seven. The PFS includes

contract mining at the Ranch Area, during the first three years of operations.

The PFS is based on an update of the Mineral Resource Estimate with an effective date of October 16, 2025,

and the first Mineral Reserve Statement for the Project, with an effective date of October 27, 2025.

Ausenco was appointed as lead consultant in January 202 5 to prepare the PFS in accordance with NI 43-

101 standards. Ausenco was assisted by Mining Plus Canada Ltd. (“Mining Plus”) for mining and Mineral

Reserve, Knight Piésold Ltd. (“KP”) for tailings management facility (“TMF”), waste rock storage facility

(“WRSF”) design, and site -wide water management , Equilibrium for open pit and underground

geotechnical assessment, Frank Wright Consulting Inc. (“Frank Wright”) for metallurgy , P&E Mining

Consultants Inc. for Mineral Resource estimation, pHase Geochemistry Inc. for material characterization,

and SLR Consulting Ltd. for environmental and permitting.

PFS Parameters and Assumptions

The financial modeling for the PFS was completed by Ausenco and included the following parameters and

assumptions:

Table 2: Summary of PFS Production

Production Unit First 5-year Avg LOM Total / Avg.

Mine Life yrs n/a 15

Total Processed Feed Tonnes kt 25,168 76,156

Waste Mined kt 119,746 341,960

OP Stripping Ratio W:O 6.5 4.6

Head Grade - Au g/t 1.25 0.97

Head Grade - Ag g/t 35.76 28.1

Head Grade - AuEq* g/t 1.68 1.31

Recovery Rate - Au % 92.9 92.8

Recovery Rate - Ag % 79.4 81.6

Total Payable Au koz 924 2,198

Total Payable Ag koz 21,460 52,940

Total Payable AuEq** koz 1,183 2,837

Average Annual Production - Au koz/yr 185 145

Average Annual Production - Ag koz/yr 4,292 3,482

Average Annual Production - AuEq** koz/yr 237 187

*AuEq reported for the mined materials/mill feed in mineral resource estimate and mineral reserve estimates assumes a conversion of 80:1 for Ag

to AuEq based on expected average expected recoveries of 93% Au and 86.1% Ag at US$2,000/oz Au and $24.50/oz Ag.

**AuEq production values are based on payable ounces as calculated by the financial model and have varying gold and silver recoveries by

deposit at a US$2,900/oz Au and US$35/oz Ag.

AISC† costs consist of mining costs, processing costs, mine-level G&A, offsite charges, royalties, sustaining capital, expansion capital, and

closure costs.

- 5 -

Table 3: Summary of PFS Economic Results

General Unit LOM

Au Price US$/oz 2,900

Ag Price US$/oz 35.00

Exchange Rate USD:CAD 1.35

Operating Costs Unit LOM Avg.

Mining $/t Processed1 25.53

Processing $/t Processed1 15.36

G&A $/t Processed1 5.64

Total $/t Processed1 46.53

AISC† US$/AuEq** oz 1,185

Capital Cost Unit LOM Total

Initial Capital $M 736.2

Sustaining Capital $M 789.4

including U/G Sustaining Capital of: $M 227.3

Closure Capital $M 71.8

Salvage Credit $M (56.3)

Total Capital $M 1,541.1

Pre-Tax Financials Unit LOM

NPV (5%) $M 3,730

IRR % 73.5

Payback Period Yrs 0.8

After-Tax Financials Unit LOM.

NPV (5%) $M 2,370

IRR % 54.4

Payback Period Yrs 1.1

After-Tax NPV:Initial Capital Ratio 3.2:1

1Excluding pre-production operating costs and tonnes.

The annual production of total payable gold and silver is presented in Figure 1.

*AuEq reported for the mined materials/mill feed in mineral resource estimate and mineral reserve estimates assumes a conversion of 80:1 for Ag

to AuEq based on expected average expected recoveries of 93% Au and 86.1% Ag at US$2,000/oz Au and $24.50/oz Ag.

**AuEq production values are based on payable ounces as calculated by the financial model and have varying gold and silver recoveries by

deposit at a US$2,900/oz Au and US$35/oz Ag.

AISC† costs consist of mining costs, processing costs, mine-level G&A, offsite charges, royalties, sustaining capital, expansion capital, and

closure costs.

- 6 -

Figure 1: Annual Payable Precious Metals

Sensitivity Analysis

A sensitivity analysis to metal prices was performed and the impacts on the Project’s key economic

indicators are summarized below:

Table 4: Metal Price Sensitivity Analysis

Base Case Spot1

Gold Price ($US)/oz 2,000 2,500 2,900 3,500 4,100

Silver Price ($US)/oz 24.00 28.00 35.00 43.00 51.00

Pre-Tax

NPV5% ($M) 1,429 2,608 3,730 5,295 6,861

IRR 34.9% 55.8% 73.5% 96.3% 117.4%

After Tax

NPV5% ($M) 909 1,658 2,370 3,364 4,357

IRR 25.9% 41.2% 54.4% 71.2% 86.9%

NPV5%: Initial Capex 1.2 2.3 3.2 4.6 5.9

Payback Years 2.5 1.7 1.1 0.8 0.6

1 Assumed spot price as of November 24, 2025.

*AuEq reported for the mined materials/mill feed in mineral resource estimate and mineral reserve estimates assumes a conversion of 80:1 for Ag

to AuEq based on expected average expected recoveries of 93% Au and 86.1% Ag at US$2,000/oz Au and $24.50/oz Ag.

**AuEq production values are based on payable ounces as calculated by the financial model and have varying gold and silver recoveries by

deposit at a US$2,900/oz Au and US$35/oz Ag.

AISC† costs consist of mining costs, processing costs, mine-level G&A, offsite charges, royalties, sustaining capital, expansion capital, and

closure costs.

- 7 -

Mineral Resource Estimate

The PFS is based on the Mineral Resource Estimate prepared by P&E Mining Consultants Inc., and APEX

Geoscience Ltd., with an effective date of October 16, 2025. It is summarized below (Table 5). Mineral

Resources that are not Mineral Reserves do not have demonstrated economic viability.

Table 5: Summary of October 16, 2025 Mineral Resource Estimate

Mineral

Resource

Area

Cut-off

AuEq

(g/t)

Classification Tonnes

(k)

Au

(g/t)

Ag

(g/t)

Cu

(%)

AuEq

(g/t)

Au

(koz)

Ag

(koz)

Cu

(kt)

AuEq

(koz)

Pit-Constrained Mineral Resource Estimate

Lawyers Area 0.25

Measured 50,674 0.91 31.9 0.00 1.31 1,482 51,920 0 2,131

Indicated 61,778 0.77 21.0 0.00 1.03 1,527 41,737 0 2,049

M&I 112,452 0.83 25.9 0.00 1.16 3,009 93,657 0 4,179

Inferred 8,583 0.59 16.3 0.00 0.80 164 4,509 0 220

Ranch Area 0.25

Measured 376 3.91 1.3 0.02 3.93 47 16 0 47

Indicated 3,502 1.77 10.1 0.06 1.90 200 1,137 2 214

M&I 3,878 1.98 9.3 0.06 2.10 247 1,153 2 261

Inferred 5,785 1.50 4.7 0.10 1.56 279 876 6 290

Total 0.25

Measured 51,049 0.93 31.6 0.00 1.33 1,529 51,936 0 2,178

Indicated 65,281 0.82 20.4 0.00 1.08 1,727 42,874 2 2,263

M&I 116,330 0.87 25.3 0.00 1.19 3,256 94,810 2 4,441

Inferred 14,369 0.96 11.7 0.04 1.10 443 5,385 6 510

Out-of-Pit Mineral Resource Estimate

Lawyers Area 1.20

Indicated 1,173 2.20 81.5 0.00 3.21 83 3,073 0 121

Inferred 1,334 1.72 51.7 0.00 2.36 74 2,216 0 101

Ranch Area 1.20

Indicated 26 1.89 6.6 0.09 1.98 2 5 0 2

Inferred 530 1.80 4.2 0.16 1.85 31 71 1 32

Total 1.20

Indicated 1,199 2.19 79.8 0.00 3.19 84 3,078 0 123

Inferred 1,863 1.74 38.2 0.05 2.22 104 2,286 1 133

Total Mineral Resource Estimate

All Combined

Measured 51,049 0.93 31.6 0.00 1.33 1,529 51,936 0 2,178

Indicated 66,480 0.85 21.5 0.00 1.12 1,811 45,952 2 2,386

M&I 117,529 0.88 25.9 0.00 1.21 3,340 97,888 2 4,564

Inferred 16,232 1.05 14.7 0.04 1.23 547 7,671 7 643

Source: APEX (2025)

Notes:

*AuEq reported for the mined materials/mill feed in mineral resource estimate and mineral reserve estimates assumes a conversion of 80:1 for Ag

to AuEq based on expected average expected recoveries of 93% Au and 86.1% Ag at US$2,000/oz Au and $24.50/oz Ag.

**AuEq production values are based on payable ounces as calculated by the financial model and have varying gold and silver recoveries by

deposit at a US$2,900/oz Au and US$35/oz Ag.

AISC† costs consist of mining costs, processing costs, mine-level G&A, offsite charges, royalties, sustaining capital, expansion capital, and

closure costs.

- 8 -

1. Mr. Eugene Puritch, P.Eng., FEC, CET, and Mr. Yungang Wu, M.Sc., P.Geo., of P&E Mining Consultants Inc., are independent

Qualified Persons as defined by NI 43-101 and are responsible for the Mineral Resource Estimate, with an effective date of October

16, 2025.

2. Mineral Resources are inclusive of Mineral Reserves. Mineral Resources that are not Mineral Reserves do not have demonstrated

economic viability.

3. The estimate of Mineral Resources may be materially affected by environmental, permitting, legal, title, taxation, socio-political,

marketing, or other relevant issues.

4. The Inferred Mineral Resource in this estimate has a lower level of confidence than that applied to an Indicated Mineral Resource and

must not be converted to a Mineral Reserve. It is reasonably expected that the majority of the Inferred Mineral Resource could

potentially be upgraded to an Indicated Mineral Resource with continued exploration.

5. The Mineral Resources were estimated in accordance with the Canadian Institute of Mining, Metallurgy and Petroleum (CIM), CIM

Standards on Mineral Resources and Reserves, Definitions (2014) and Best Practices Guidelines (2019) prepared by the CIM Stan ding

Committee on Reserve Definitions and adopted by the CIM Council.

6. Historical mined areas were removed from the block-modelled Mineral Resources.

7. The Lawyers Area includes the Cliff Creek (CC), Dukes Ridge (DR), Phoenix (PX), and Amethyst Gold Breccia (AGB) zones. The

2025 MRE includes updates to the CC, DR, and PX zones since the 2024 MRE. The AGB block model remains unchanged from the

2022 MRE but is restated with updated RPEEE constraints.

8. The Ranch Area includes the Thesis II, Thesis III, Bingo, Barite Vein (BV), Bonanza-South, JK, Bonanza, and Ridge zones. The 2025

MRE updates all Ranch Area zones from the 2024 MRE.

9. Economic assumptions include metal prices of US$2,500/oz Au, US$30/oz Ag, and US$8,800/tonne Cu; an exchange rate of 0.73

US$:CAD$; process recoveries of 93% Au for both Areas, 86% and 88% Ag for the Lawyers and Ranch areas, respectively, and 85%

Cu for the Ranch Area; and processing and G&A costs of CAD$17/t and CAD$6/t, respectively. AuEq values are calculated using an

Au-to-Ag ratio of 1:80. Cu is not included in the AuEq calculation.

10. Pit-constrained Mineral Resources include blocks within an optimized pit shell derived using the economic assumptions described

above, together with a mining cost of CAD$4.0/t for mineralized and waste material, and pit slopes of 52° and 48° for the Lawyer s

and the Ranch Areas, respectively.

11. Out-of-pit Mineral Resource Estimates include blocks below the constraining pit shell that form continuous and potentially mineable

shapes, derived using the economic assumptions described above together with a mining cost of CAD$90/t. These parameters result in

an out-of-pit cut-off grade of 1.20 g/t AuEq. Mining shapes encapsulate material within domains with a minimum horizontal width of

2.0 m (perpendicular to strike) and target vertical and horizontal dimensions of approximately 10 m (H) by 20 m (L).

Mineral Reserve

The PFS is based on the Mineral Reserve E stimate prepared by Mining Plus and reported by Thesis Gold

with an effective date of October 27, 2025. The Mineral Reserve Estimate is summarized in Table 6 below:

Table 6: Summary of October 27, 2025, Mineral Reserve Estimate

Category Tonnes

(kt)

Au

(g/t)

Ag

(g/t)

AuEq

(g/t)7 Au (koz) Ag (koz) AuEq

(koz)

Open Pit

Proven

Lawyers Area 31,582 0.97 33.45 1.39 990 33,965 1,414

Ranch Area 365 3.66 1.11 3.67 43 13 43

Open Pit Subtotal: Proven 31,948 1.01 33.08 1.42 1,033 33,978 1,457

Probable

Lawyers Area 39,661 0.79 20.16 1.04 1,007 25,709 1,329

Ranch Area 2,134 1.65 11.69 1.80 113 802 123

Open Pit Subtotal: Probable 41,795 0.83 19.73 1.08 1,120 26,511 1,452

Underground

Proven

Lawyers Area 1,301 2.96 115.68 4.41 124 4,839 184