Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

TALA.V ·

Fuerte Announces a Positive Preliminary Economic Assessment for the Coffee Gold Project; Positioning the Company as one of Canada's Next Gold Producers After-Tax NPV(5%) of US$2.3 Billion and IRR of 47.8% at Consensus Gold Prices

Drill Results Economic Studies

Fuerte Announces a Positive Preliminary

Economic Assessment for the Coffee Gold

Project; Positioning the Company as one of

Canada's Next Gold Producers

After-Tax NPV(5%) of US$2.3 Billion and IRR of 47.8% at Consensus Gold Prices

After-Tax NPV(5%) of US$4.0 Billion and IRR of 67.2% at Spot Gold Price

Vancouver, British Columbia--(Newsfile Corp. - February 22, 2026) -

Fuerte Metals Corporation

(TSXV: FMT) (OTCQB: FUEMF) ("Fuerte" or the "Company")

is pleased to announce the results of

its Preliminary Economic Assessment ("PEA") for the 100% owned Coffee Gold Project ("Coffee") in

Yukon, Canada.

Highlights:

Very robust economics:

After-Tax NPV(5%) of US$2.3 Billion, IRR of 47.8%, and payback

achieved in 1.7 years at analyst consensus gold prices

(1)

. After-Tax NPV(5%) of US$4.0 Billion,

IRR of 69.7%, and payback achieved in 1.2 years at spot gold prices

(2)

.

High-quality open-pit heap-leach mine with significant production:

249,000 oz per year on

average in the first full five years of production and 217,000 oz on average over the 13-year Life of

Mine.

Attractive cost profile:

Cash operating costs of US$1,136/oz and All-In Sustaining Costs

("AISC") of US$1,274/oz position the project in 2

nd

quartile of global producers.

Stable, supportive jurisdiction:

Strong support from the Yukon Government and agreements in

place with key First Nations provide momentum in a politically secure, established mining

jurisdiction.

Clear pathway to production:

PEA is the catalyst for significant early works in 2026, expected

receipt of mine permits by end of year, and a construction decision in early 2027.

1

Analyst consensus prices as at February 18, 2026: US$4,100/oz in 2029 and US$3,620 in 2030 and beyond.

2

Spot price scenario is based on US$5,000/oz, which is the LBMA gold price as of the close of business on February 18, 2026, of US$5,003/oz

rounded to the nearest $100/oz.

Fuerte's CEO, Tim Warman, commented:

"The positive results of the PEA strongly validate our

decision to acquire the Coffee project in 2025. We will be moving ahead with an aggressive timeline

and early works program in 2026, including construction of the remaining portions of the access road

from Dawson to the Coffee Project, which we anticipate beginning on receipt of road-related permits

later this spring. We expect to obtain the key remaining mine licenses by year-end, which would pave

the way for a construction decision for the project in early 2027. We are excited to drive forward with

Coffee and to deliver significant economic benefits to our shareholders, residents of the Yukon, and

our First Nations partners."

We respectfully acknowledge that protection of the water and lands around the Coffee Creek and mine

project area is of high importance to First Nations. Through cooperation, transparency, and respect, we

pledge to continue to build on relationships with Tr'ondëk Hwëch'in, White River First Nation, Selkirk

First Nation, and the First Nation of Na-Cho Nyäk Dun, whose Traditional Territories overlap or partially

overlap with the project access road, and areas where exploration and mining activities may occur.

PEA Summary

The PEA contemplates a high-grade open-pit heap-leach mine with an initial planned mine life of

approximately 13 years. Coffee is expected to produce 249,000 saleable gold ounces per year on

average for the first full five years of production and an average of 217,000 saleable gold ounces per

year over the life of mine ("LOM") at an attractive AISC of US$1,274/oz.

Consistent with PEA studies, the production profile includes Inferred resources and is provided in the

chart below. Approximately 16% of the ounces mined in the PEA profile are in the Inferred category,

which cannot be included in the Feasibility Study scheduled for Q4/26. In order to upgrade a portion of

these Inferred ounces to the Indicated category, the Company will commence an infill drilling program in

Q1/26. The mineralization at Coffee is such that it hosts a number of high grade near surface zones that

enable the mining of good grade material early in the mine plan allowing for higher average production in

the initial five years.

LOM annual gold production with Inferred contribution

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/7505/284732_fuerte1.jpg

The PEA mine plan estimates a robust internal rate of return (IRR) of 47.8% and after-tax net present

value (NPV5%) of US$2.3 billion at analyst consensus gold prices (US$3,620/oz long-term) and a

foreign exchange rate of 1.39 CAD per 1.00 USD. The mineral resources included in the mine design

are from pit shells developed using a gold price of US$2,500/oz.

PEA Study Highlights

PEA Study Highlights

LOM Production

Material Mined

Mt

90.5

Gold Grade

(g/t)

1.25

Contained Gold

kozs

3,644

Processed Material Stacking Rate

Mtpa

7.4

Average Recovery

Rec

%

77.5%

Recovered Gold

kozs

2,824

Strip Ratio

waste: material

processed

7.6

Mine Life

years

13

Annual Production (Saleable Gold)

Annual Production - First Full 5 Years

oz/yr

249,000

Annual Production - Life of Mine

oz/yr

217,000

Operating Costs

Avg. LOM Operating Costs

C$/t processed

44.24

Total Cash Costs

1

US$/oz

1,136

All-in Sustaining Cost - First Full 5 Years

1

US$/oz

1,166

All-in Sustaining Cost

1

US$/oz

1,274

Capital Costs

Total Direct Capital Costs

C$M

638.5

Indirect Costs

C$M

165.3

Contingency

C$M

179.4

Total Initial Capital

C$M

983.1

Sustaining Capital

C$M

558.8

Economic Attributes

Gold Price

US$/oz

Consensus

2

Spot

3

After Tax NPV(5%)

US$B

2.3

4.0

After Tax IRR

%

47.8

67.2

Payback Period

years

1.7

1.2

1

Total Cash Costs are a non-GAAP financial measure and include mining, processing, refining & transport, G&A and royalty costs. All-in Sustaining

Costs (AISC) is a non-GAAP financial measure and is comprised of total cash costs, sustaining capital expenditures to support the on-going

operations, and closure costs.

2

Analyst consensus prices as at February 18, 2026: US$4,100/oz in 2029 and US$3,620 in 2030 and beyond.

3

Spot price scenario is based on US$5,000/oz, which is the LBMA gold price as of the close of business on February 18, 2026, of US$5,003/oz

rounded to the nearest $100/oz.

Economic Sensitivities

The following table provides a sensitivity analysis of key project economic parameters at various gold

prices.

Project Economics - Gold Price Sensitivity

Gold Price (US$/oz)

$2,500

Consensus

1

$4,500

Spot

2

$5,500

Pre-tax NPV(5%) (US$M)

1,678

3,770

5,414

6,234

7,282

After-tax NPV(5%) (US$M)

983

2,326

3,380

3,963

4,578

Pre-tax NPV(5%) (C$M)

2,332

5,241

7,526

8,665

10,122

After-tax NPV(5%) (C$M)

1,366

3,233

4,698

5,508

6,363

After-tax IRR (%)

26.4

47.8

62.1

67.2

76.9

Payback (years)

2.9

1.7

1.4

1.2

1.1

1

Analyst consensus prices as at February 18, 2026: US$4,100/oz in 2029 and US$3,620 in 2030 and beyond.

2

Spot price scenario is based on US$5,000/oz, which is the LBMA gold price as of the close of business on February 18, 2026, of US$5,003/oz

rounded to the nearest $100/oz.

The following chart provides the rolling after-tax NPV(5%) at both analyst consensus and spot prices.

The chart demonstrates the go-forward value of the project once the capital for the project has been

incurred.

Rolling After-Tax NPV(5%)

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/7505/284732_fuertegraph2.jpg

Resource Estimate

The Mineral Resource Estimate ("MRE") used in the PEA is unchanged from that presented in the

technical report prepared for Fuerte Metals Corporation and entitled "NI 43-101 Technical Report for the

2025 Mineral Resource Estimate Update on the Coffee Gold Project, Yukon, Canada" prepared by

Micon International Ltd. ("Micon"). The MRE has an effective date of August 21, 2025.

Resource Category

Tonnage

(kt)

Gold Grade

(g/t)

Contained Gold

(gold koz)

Measured

1,200

1.80

69

Indicated

78,846

1.14

2,888

Measured + Indicated

80,046

1.15

2,957

Inferred

21,200

1.17

800

Notes to Table

1

.

Economic parameters used in the resource are a gold price of US$2,500/oz; heap leach average recoveries for the individual metallurgical

domains of 86.3% for Oxide, 76.0% for Upper Transition, 54.5% for Middle Transition and 31.4% for Lower Transition; a mining cost of

C$3.27-$3.50/t, processing costs of C$6.64/t, and general and administrative costs of C$6.0/t. A CAD:USD exchange rate of 1.35 was also

assumed.

2

.

The calculated cut-off grades vary between 0.13 g/t Au and 0.48 g/t Au, depending on the metallurgical domain. The global weighted

average cut-off grade is 0.18 g/t Au, with domain tonnage contributions comprising 64% Oxide, 18% Upper Transition, 5% Middle Transition,

and 13% Lower Transition.

3

.

Design inter-ramp angles vary between 46.3 and 48.3 degrees in pit walls governed by bedding and foliation stability. Pit walls not expected

to be impacted by southerly dipping bedding and foliation are designed at inter-ramp angles between 51.7 and 55.3 degrees.

4

.

Pit optimization was done on 12x12x10 m re-block model with a minimum of 4x4x5 m regularized SMU.

5

.

Numbers have been rounded to the nearest for thousand tonnes and ounces. Differences may occur in totals due to rounding.

6

.

The mineral resources described above have been prepared in accordance with the Canadian Institute of Mining, Metallurgy and Petroleum

Standards and Practices.

7

.

Messrs. Alan J. San Martin, P.Eng. and Charley Murahwi, P.Geo. from Micon International Limited are the Qualified Person (QP) for this

Mineral Resource Estimate.

8

.

Mineral resources are not mineral reserves as they have not demonstrated economic viability. The quantity and grade of reported Measured,

Indicated and Inferred mineral resources in this news release are uncertain in nature; however, it is reasonably expected that a significant

portion of Inferred Mineral Resources could be upgraded into Measured and Indicated Mineral Resources with further exploration.

9

.

Micon's QPs have not identified any legal, political, environmental, or other factors that could materially affect the potential development of

the mineral resource estimate.

Mining

The Coffee Gold Project will be mined by conventional truck / loader open pit operations with an average

annual production rate of 7.4 Mt of material processed, and a LOM strip ratio of 7.6:1. Material to be

leached will be mined principally from four pits, with minor production from smaller pits, over an expected

13-year mine life. Mining will take place year-round, with material to be leached delivered by truck from

the pits to the crusher except in the coldest period of the year (approximately three months) when this

material will be stockpiled.

Processing

Run-of-mine ("ROM") process material will be delivered from the pits via trucks and dumped into the

primary gyratory crusher at an average daily rate of about 26,900 t. A ROM stockpile area with a

capacity of ~1.5 Mt will allow the stockpiling of material to be processed when the crusher is not running,

particularly during the winter months. There will be two-stage crushing with a final target product size of

P80 of 50 mm. Material to be processed will be stacked on the Heap Leach Facility ("HLF") by

conveyors.

The HLF will consist of a conventional, multi-lift, free-draining ridge-top leach pad, ponds, access roads,

and leachate solution distribution and collection piping. Barren solution will be irrigated onto the heap

using drip irrigation. Pregnant (gold-bearing) solution will be collected at the base of the heap leach pad

by impermeable membranes and piping. The pregnant solution will flow to the process plant by gravity

for gold recovery.

The leach pad will be constructed in stages, with each stage large enough to provide capacity for one

and a half to three years of operation. The pad will be lined with two liners: a geosynthetic clay liner at the

base directly overlain by an impermeable collection geomembrane. A network of drainage pipes within a

layer of permeable gravel at the base of the pad will collect and direct the pregnant solution into trunk

lines on each flank of the pad and transport it by gravity to the process plant. A series of horizontal

trenches or wick drains will be installed beneath the liner system to detect leakage.

Process solution (barren, pregnant and heap rinse water) will be stored in tanks located at the plant. The

barren solution will be heated when necessary to ensure that the thermal integrity of the system and the

leach pad is maintained. Ponds adjacent to the heap leach pad will be used to store contact and clean

water generated from seasonal and storm events, heap upset conditions (e.g., power loss), and normal

precipitation runoff.

Leached gold will be recovered from solution using an activated carbon adsorption circuit. The gold will

then be stripped from carbon using a desorption process followed by electrowinning to produce a

precipitate sludge, which is refined on site in a furnace to produce doré bars as final products.

Heap Leach Facility Engineering and Safety

The safety of the HLF is of paramount importance to our team, who have taken a proactive approach to

carry out a robust technical review of the HLF design and operating procedures, including:

A

third-party expert review

of all existing HLF documentation, including but not limited to;

foundation investigations, design plans, stability assessments, HLF water balance, and operating

and closure plans. That work was completed and recommendations from that review were made to

HLF design and operating procedures planning and documentation.

A failure modes and effects analysis

was completed in 2025 for the HLF which included the

third-party technical experts, as well as the project team and HLF engineers and informed by

findings from

the Independent Review Board

investigation into the Eagle Gold Mine Heap

Leach Failure. Recommendations from that investigation have been evaluated and integrated into

the Project HLF design, operation, maintenance and closure plans where appropriate. The design

and operation of the Coffee HLF will be monitored by an Independent Technical Review Board,

one of the key recommendations arising from the Eagle Mine investigation.

The HLF design has had 10 years of progressively detailed design and substantial engineering review,

and the design incorporates conventional stacking of well-drained material and a conservative

water/solution management design that allows for unplanned events and contingencies.

Capital Costs

The direct construction capital for Coffee is estimated at C$638.5 million, including off-site costs of

C$71.3 million for the Northern Access Route, which will provide road access to site from Dawson City.

Mobile mining equipment costs are included in the direct construction capital at C$89.2 million for the

primary equipment and $39.2 million for the auxiliary equipment, reflecting the purchase of an owner-

operated mining fleet. Indirect costs are estimated at C$165.3 million and contingency is C$179.4

million. Sustaining capital over the life of mine (including contingency) is estimated at C$558.8 million

and closure costs are estimated at C$182.6 million.

Capital Cost Summary

C$ millions

Direct Construction Capital

567.2

Northern Access Route

71.3

Total Direct Capital Costs

638.5

Indirect Costs

165.3

Contingency

179.4

Total Initial Capital

983.1

Sustaining Capital - LOM

558.8

Reclamation Costs

182.6

Total LOM Capital Incl. Sustaining & Reclamation

1,724.5

Operating Costs

Operating costs average C$44.24/tonne stacked and are based on estimates provided by WSP for

labour and consumables. Total cash costs are forecast to average US$1,136/oz of gold produced over

the life of mine and All-in Sustaining Costs (AISC) are expected to average US$1,274/oz. Costs in the

first full five years of the mine plan will benefit from the processing of higher-grade material and AISC will

average US$1,166/oz over the period.

Operating Cost Summary

(C$)

(US$)

Mining Costs ($/t material stacked)

30.32

21.81

Site Services Costs ($/t material stacked)

1.84

1.32

Processing Costs ($/t material stacked)

6.48

4.67

G&A Costs ($/t material stacked)

5.60

4.03

Total Operating Costs ($/t material stacked)

44.24

31.83

Total Operating Costs ($/oz gold sold)

1,412

1,016

Royalties ($/oz)

1

140

101

Refining & Transport ($/oz)

28

20

Total Cash

Cost ($/oz gold sold)

1,579

1,136

Sustaining Capital & Other ($/oz)

192

138

All-in Sustaining Cost ($/oz sold)

1,771

1,274

1

Royalty costs include payments to third party royalty holders and assume that a buyback of half of a 2% NSR is exercised prior to commercial

production and that the 3% NSR to Newmont is re-purchased at the end of the first year of commercial production.

Environmental, Social, and Permitting

The Coffee Gold Mine Project is nearing the completion of mine permitting; the environmental and

socioeconomic assessment process was completed in 2022, and major mine license applications were

filed in 2023.

The Quartz Mining Licence (QML) and Water Use Licence (WUL) are required to advance

major mine construction and operations activities, and the company anticipates receipt of these permits

by year-end 2026.

The Coffee Gold Mine Project licensing documents do not fully reflect the scope of the project outlined in

the PEA and amended permits will be required to fully realize the value of the Coffee Project.

The first

several years of mine construction and operation will not require material divergence from the mine

permit approvals, and the Company intends to pursue additional permitting, as required, in parallel with

mine development and production.

Next Steps

The Company is planning a 40,000-metre drill program in 2026, for the purposes of both upgrading the

confidence level of existing mineral resources and testing new targets.

The infill drill program will focus on upgrading the mineral resource confidence in the Supremo Extension

deposit and parts of Latte deposit to the Measured and Indicated category to improve confidence and

bring additional resources into the Feasibility Study. The Feasibility Study will also evaluate potential

opportunities to improve productivity and overall project performance.

While the majority of drilling will focus on infill, a portion of the 2026 drill program will be allocated to test

new targets at the project. The Coffee project is situated on a 70,000 hectare claim package with the

potential for resource expansion as well as new discoveries.

With the positive results of the PEA, the Company is planning an Early Works program to complete

several strategic initiatives that will help accelerate the construction timeline once a construction

decision is made. The initiatives permissible under our existing permits include:

New airstrip that allows larger aircraft and night flights

Installation of a construction camp

Development of laydown areas

Other minor projects (Ex., aggregate stockpiling, powder magazine, etc.)

Upon receipt of the remaining permits for the Northern Access Route ("NAR"), the company is also

planning to begin work on the site access road from Dawson City to the project. The NAR is a ~214 km

road, much of which currently exists in the form of public roads to access nearby placer gold operations.

Approximately 40 km of new road will be built with the remainder requiring upgrades for more permanent

use.

The Company is also advancing the previously announced Feasibility Study with G Mining Services, who

will also manage construction of the project. Once the permits are received, our ambition is to be in a

position to make a construction decision in early 2027.

About Fuerte Metals Corporation

Fuerte is a Canadian exploration and development company focused on advancing high-potential

precious metals and base metals projects across the Americas. Our flagship asset is the 100%-owned

Coffee Project in the Yukon, Canada - a high-quality gold project advancing through the final stages of

permitting, engineering, and resource expansion drilling in preparation for a construction decision.

Coffee hosts 3.0 million ounces of open-pit heap-leach Measured and Indicated Resource and an

Inferred Resource of 0.8 million ounces. We respectfully acknowledge that protection of the water and

lands around the Coffee Creek and mine project area is of high importance to First Nations. Through

cooperation, transparency, and respect, we pledge to continue to build on relationships with Tr'ondëk

Hwëch'in, White River First Nation, Selkirk First Nation, and the First Nation of Na-Cho Nyäk Dun, whose

Traditional Territories overlap or partially overlap with the project access road, and areas where

exploration and mining activities may occur. In addition to Coffee, Fuerte holds a portfolio of copper and

gold assets, including the Placeton-Caballo Muerto Project in Chile and the Cristina and Yecora Projects

in Mexico, offering additional growth and exploration upside. At Fuerte, we are committed to building

value through disciplined project development, responsible stewardship of the land, a safety-focused

culture, and creating long-term returns for shareholders.

Qualified Persons

The Preliminary Economic Assessment was prepared by independent Qualified Persons in accordance

with National Instrument 43-101 - Standards of Disclosure for Mineral Projects. A technical report on the

Coffee Gold Project will be prepared in accordance with National Instrument 43-101 and filed under the

Company's profile on SEDAR+ and on the Company website within 45 days.

The report will cover all key aspects of the Project, including property description and location, geology,

mineral resource estimates, mining methods, metallurgical testing and recovery processes, project

infrastructure, permitting, capital and operating cost estimates, and economic analysis.

The Qualified Persons ("QPs") responsible for the Study include:

Charley Murahwi., (Micon) - Mineral Resource Estimates

William Richard McBride and David Jin., (WSP) - Process Plant Design, Process Infrastructure,

Metallurgy, Recovery Methods, and Operating (plant and G&A) Cost Estimates, Financial Analysis

Lasha Young and Kim Ferguson., (WSP) - Environmental Studies, Permitting and Social or

Community Impacts

Marc Rougier., (WSP) - Waste Rock Storage Design, Project Infrastructure

John Kurylo., (SRK) - Mine Waste and Water Management Infrastructure (geotechnical)

Samantha Barnes., (SRK) - Mine Waste and Water Management Infrastructure (hydrotechnical)

Hannah Chiew., (Ensero) - Water Treatment

Russ Downer., (Open Contour) - Responsible for Mine Optimization, Mine Design, and Mine

Schedule

Barry Calson., (Forte Dynamics) - Heap Leach

Full detail of areas of responsibility of the QPs can be found in the Technical Report.

The content of this news release from the Study has been reviewed and approved by the QPs who

authored the Study. In addition, Mr. Denis Flood, P.Eng., Chief Operating Officer of Fuerte Metals and a

QP as defined in NI 43-101, has reviewed the PEA on behalf of the Company and has approved the

technical disclosure contained in this news release.

The PEA is preliminary in nature and includes inferred mineral resources that are considered too

speculative geologically to have economic considerations applied that would enable them to be

categorized as mineral reserves. There is no certainty that the PEA will be realized. Mineral resources

that are not mineral reserves do not have demonstrated economic viability.

Additional Information