Slam Acquisition Expands Zinc Copper Silver Footprint IN Bmc Core Intervals to 14.51% Zinc, 5.86% Lead, 0.67% Copper and 139.9 G/T Silver

Drill Results

N bmh AQ

TSXV: SXL

SLAM ACQUISITION EXPANDS ZINC COPPER

SILVER FOOTPRINT IN BMC

CORE INTERVALS TO 14.51% ZINC, 5.86% LEAD, 0.67% COPPER AND

139.9 G/T SILVER

For Immediate Release, September 6, 2023

Miramichi, New Brunswick ‐ SLAM Exploration Ltd. (TSXV-SXL) (“SLAM” or the

“Company”) is pleased to announce it has entered into an arm’s length option agreement dated

September 01, 2023, to acquire a 100% interest in and to the Mine Road project, which is located

adjacent to the former producing Heath Steele mine in the Bathurst Mining Camp (“BMC”) of

northern New Brunswick.

Project Highlights:

• Railroad Zone: 14.51% zinc, 5.86% lead, 0.67% copper and 139.9 g/t silver over a 9.0

metre interval in diamond drill hole IL2014-003.

• Roche Trend: Diamond drill hole IL2018-01 intersected 7.0 meters of 0.9% copper on

the Roche Trend, 5 kilometres southwest of the Railroad Zone,

• Infrastructure: Paved road and high voltage powerline transect the property.

• Drill-ready project : Untested conductors, magnetic and soil anomalies as well as

priority targets on the Railroad and Roche Zones.

Previously drilled holes include IL2014-003 that cored 14.51% zinc, 5.86% lead , 0.67% copper

and 139.9 g/t silver over a 9.0 metre interval (7.8 metre true width ). This hole also intersected

6.57% zinc, 2.78% lead, 0.46% copper , and 68.1 g/t silver over a 3 m core interval (2.6 metre

true width). This was one of 5 holes drilled on the Railroad Zone in 2014.

On the Roche Trend, 5 kilometres southwest of the Railroad Zone, diamond drill hole IL2018-01

intersected 7.0 meters of 0.9% copper . This is the deepest intercept on the Roche T rend and

according to accepted models for VMS deposits, the increasing copper content may signify that

the core of the deposit lies below this hole.

SLAM President Mike Taylor states, “This is a drill ready project with a massive previous work

database that is available to design drilling programs to test for potential extensions and new

2

discoveries. The BMC was a prolific producer of zinc, lead, copper and silver and is long

overdue for such a discovery.”

Mine Road Project: The 7,500 hectare Mine Road project comprises 347 units in 2 mineral

claims adjacent to the former producing Heath Steele mine property . From 1957 and 1996, the

operator mined 21 million tonnes at Heath Steele with an average grade of 4.98% zinc, 0.36%

lead, 0.54% copper and 69.66 g/t silver. A total of 2,330 million pounds of zinc, 833 million

pounds of lead, 446 million pounds of copper and 45 million ounces of silver were processed.

(For reference, these numbers are derived from: McCutcheon, S.R. (compiler) 1997; Geology

and massive sulphides of the Bathurst Camp, New Brunswick; Geological Association of Canada

- Mineralogical Association of Canada, Joint Annual Meeting, Ottawa ’97, Field Trip B7,

Guidebook, 85 p.)

Volcanogenic Massive Sulphide Occurrences: The Mine Road project contains 7 volcanogenic

massive sulphide occurrences including the R ailroad Zone described above. The Company

expects to generate additional targets once the Mine Road project database is integrated with

SLAM’s extensive Bathurst Joint Venture database. A total of $1,448,000 in exploration

expenditures have been applied to the Mine Road project during the past 10 years and

assessment work credits of $428,776 are available for future claim renewals.

Infrastructure: The Mine Road project is located on the Mine Road (Route 430) which

connects the former Heath Steele mine to the city of Miramichi which is 60 kilometres to the

southeast. The claims are accessed from this paved road and a series of logging roads. Electric

power is available from lines that connect Heath Steele to the New Brunswick power grid.

The Agreement: The Company can earn a 100% interest in and to the Mine Road project by

making the following cash payments and common share issuances:

Due Date Cash Payments Common Share Issuances

Within 5 days receipt of approval from the

TSX-V

- 100,000

On or b efore the 1 st anniversary of the option

agreement

$10,000 100,000

On or before the 2nd anniversary of the option

agreement

$10,000 100,000

On or before the 3rd anniversary of the option

agreement

$10,000 100,000

On or before the 4th anniversary of the option

agreement

$20,000 100,000

Total $50,000.00 500,000

The Mine Road project is subject to a 2% NSR royalty. SLAM retains the right to buy back half

the royalty equal to 1.0% NSR for $1,000,000 and the further right to buy back the remaining

royalty equal to 1.0% NSR for $1,000,000 at any time. The option agreement and proposed share

issuances remain subject to approval by the TSX Venture Exchange. All security issuances will

3

be subject to a statutory hold period of 4 months and one day from issuance in accordance with

Canadian securities laws. No finders’ fees were paid on this arm’s length agreement.

About SLAM Exploration Ltd:

The Mine Road project is a significant addition to SLAM’s portfolio of wholly -owned BMC

projects that include the A’Hearn, Strachens and Portage volcanogenic massive sulphide

projects. The Company has extensive experience in the BMC and owns a huge database covering

the entire mining camp dating back to its participation in the Bathurst Joint Venture. The

Company holds NSR royalties and expects additional cash and share payments on the Wedge,

Goodwin, Ramsay and Ferguson projects in this mineral rich area.

Elsewhere in the mineral -rich province of New Brunswick, e xploration for gold along regional

fault structures has resulted in significant gold discoveries. These include the Maisie gold vein

system at SLAMs wholly owned Menneval project. With gold and copper trends up to 20 km

long, SLAM has identified an area with high potential for additional gold discoveries and

acquired the Shadow Lake, Jake Lee, Rogers Lake and Highway projects . Gold assays are

pending on 250 soil samples. These projects are associated with the Fundy fault zone and located

in southwestern New Brunswick where Galway Metals recently announced a 2.3- million-ounce

gold deposit at Clarence stream. Targeting critical elements as well as gold, the Company

aggressively pursues new exploration opportunities such as the recent Highway and Mine Road

acquisitions.

To view SLAM’s corporate presentation, click SXL-Presentation. Additional information is

available on SLAMs website SLAM and SEDAR+ filings at www.sedarplus.ca. Follow us on

twitter @SLAMGold.

QA-QC Procedures: The drilling results described above are from assessment reports by well

established mining firms with assays from commercial laboratories. The assessment reports

included a summary of QA-QC procedures and the Company deems these results to be reliable.

Qualifying Statements: Mike Taylor P.Geo, President and CEO of SLAM Exploration Ltd., is a

qualified person as defined by National Instrument 43- 101, and has approved the contents of this

news release.

Certain information in this press release may constitute forward -looking information, including statements

regarding mineral resources and the Company’s plans with respect to the exploration and development of its

properties. This information is based on current expectations that are subject to significant risks and uncertainties

that are difficult to predict. Actual results might differ materially from results suggested in any forward -looking

statements. The Company assumes no obligation to update the forward-looking statements, or to update the reasons

why actual results could differ from those reflected in the forward looking -statements unless and until required by

securities laws applicable to the Company. There are a number of risk factors that could cause future results to

differ materially from those described herein. Information identifying risks and uncertainties is contained in the

Company's filings with the Canadian securities regulators, which filings are available at www.sedarplus.ca. Neither

the TSXV nor its Regulation Services Provider (as that term is defined in the policies of the TSXV) accepts

responsibility for the adequacy or accuracy of this release.

4

CONTACT INFORMATION:

Mike Taylor, President & CEO

Contact: 506-623-8960 [email protected]

Eugene Beukman, CFO

Contact: 604-687-2038 [email protected] SEDAR+: 00012459