SILVER STORM COMMENCES REHABILITATION ACTIVITIES AT LA PARRILLA

Toronto, Ontario, October 21, 2025: Silver Storm Mining Ltd. (“ Silver Storm” or the " Company")

(TSX.V: SVRS | OTCQB: SVRS | FSE: SVR) is pleased to announce the Company has commenced

rehabilitation activities at its 100% -owned La Parrilla Silver Mine Complex (“La Parrilla ”) in

Durango State, Mexico.

Highlights:

• Processing Plant Rehabilitation Program has Commenced

o Engineering contractor engaged and mobilized: Dynamic Engineering was awarded

the contract for rehabilitation of the La Parrilla processing plant. Estimated completion

time is 7 to 9 months.

o Sulphide circuit will be expanded to 1,250 tonnes per day, representing a 25%

increase

o Long lead items ordered for processing plant, including flotation cells

• Underground Rehabilitation Work Underway: Initial activities include drift cleaning, scaling,

ventilation upgrades, and recommissioning of underground services

• Strategic Restart Plan: SRK Consulting (Canada) has been engaged to review the Company’s

restart plan for La Parrilla

“The commencement of rehabilitation activities and the ordering of long -lead items at La

Parrilla marks an important milestone for Silver Storm, ” stated Greg McKenzie, President &

CEO. “With the existing infrastructure in place and recent financings completed, we are taking decisive

steps in respect of the Company’s objective of bringing the historic La Parrilla Silver Mine Complex

back into production and creating value for our shareholders and the communities of Durango.

Rehabilitation and preparation activities will take seven to nine months, and subject to further technical

evaluations, we could target the potential restart of operations as early as the second quarter of 2026.”

Plant Rehabilitation to be Completed by Dynamic Engineering, Expansion of Sulphide Circuit

The Company is pleased to announce that Dynamic Engineering Services Ltd. (“Dynamic”) has been

engaged to complete the rehabilitation of the La Parrilla processing plant (the “Processing Plant”).

As part of the rehabilitation activities, the nameplate capacity of the sulphide circuit of the Processing

Plant will be expanded to 1,250 tonnes per day. A larger capacity sulphide circuit will better align with

the mineralization profile of La Parrilla, which is characterized by a large growth in sulphide material

as disclosed in the most recent Technical Report for La Parilla filed by the Company in March 2025.

Figure 1 - Roof Replacement on Kitchen and Mess Hall

Dynamic mobilized its team to site at La Parrilla on September 3, 2025 to commence its work has

made significant progress . Activities include rehabilitating the kitchen/mess hall (Figure 1), living

quarters and office areas (Figure 2), replacing the roofs on several buildings, as well as purchasing

tools and equipment for the rehabilitation efforts.

Figure 2 - Medical Services and Living Quarters Refurbishment

Rehabilitation of the Processing Plant is expected to take approximately seven to nine months to

complete. Activities will comprise the maintenance, rehabilitation, and installation of the new

equipment required for any potential resumption of mineral processing activities at La Parrilla.

In July 2025, the Company placed an order for eight new 1,000 ft3 rougher and scavenger cells for the

flotation circuit, which meet the requirements for the expanded feed rate. A new cyclone has also been

ordered to increase the capacity of the grinding circuit. Manufacturing of these systems are well

underway (Figure 3). Delivery of the flotation cells and cyclone is expected by December 2025.

Figure 3 - Manufacturing of Components of Flotation Cells Well Underway

The crushing and milling circuit will have the primary jaw crusher replaced, the ball mills relined, motor

systems serviced, and all feed lines, conveyors, screens and cyclones serviced and repaired . The

building housing for the secondary crushing system will be reinforced. As part of the expansion of the

sulphide circuit, one of the site’s three ball mills will be redirected from the oxide circuit to process feed

exclusively to the sulphide circuit.

The oxide leach and tailings plant will also be partially rehabilitated, including the repair of five leach

tanks in order, and all related mechanical parts serviced and repaired. All pumps and valves will be

removed, serviced, cleaned reinstalled, and repaired if required. The tailings systems will be inspected,

cleaned, and serviced.

Following the mechanical completion of rehabilitation activities of the processing plant , Dynamic will

lead, manage and supervise all commissioning activities through the completion of wet

commissioning.

SRK Canada Review

The Company's plans to restart La Parilla is largely based on internal data and reports in conjunction

with management's knowledge of the property and the existing estimate of mineral resources on the

property. There is no preliminary economic assessment, pre -feasibility study or feasibility study of

mineral reserves demonstrating economic and technical viability for the project, resulting in increased

uncertainty and higher risks of economic and technical failure than would be the case if such studies

were completed.

SRK Consulting (Canada) Inc. (“SRK”) has been engaged to review all components of the Company’s

plans to restart La Parrilla , including geomechanical, ventilation, water management, underground

mine design, development schedules, and mineral processing considerations.

Qualified Person

The scientific and technical information in this document has been reviewed and approved by Shane

Ghouralal, P.Eng., a Qualified Person as defined by National Instrument 43-101.

About Silver Storm Mining Ltd.

Silver Storm Mining Ltd. holds advanced-stage silver projects located in Durango, Mexico. Silver Storm

is committed to advancing toward a potential near-term restart of its 100% owned La Parrilla Silver

Mine Complex, a prolific operation comprised of a 2,000 tpd mill and three underground mines. The

Company also holds a 100% interest in the San Diego Project, which is among the largest

undeveloped silver assets in Mexico. For more information regarding the Company and its projects,

please visit our website at www.silverstorm.ca.

For additional information, please contact:

Greg McKenzie, President & CEO

Ph: +1 (416) 504-2024

[email protected]

Neither the TSXV nor its Regulation Services Provider (as that term is defined in the policies of the

TSXV) accepts responsibility for the adequacy or accuracy of this news release.

Cautionary Note Regarding Forward Looking Statements:

Certain statements in this news release are forward -looking and involve a number of risks and

uncertainties. Such forward-looking statements are within the meaning of the phrase ‘forward-looking

information’ in the Canadian Securities Administrators’ National Instrument 51 -102 – Continuous

Disclosure Obligations. Forward -looking statements are not comprised of historical facts. Forward -

looking statements include estimates and statements that describe the Company’s future plans,

objectives or goals, including words to the effect that the Company or management expects a stated

condition or result to occur. Forward-looking statements may be identified by such terms as “believes”,

“anticipates”, “expects”, “estimates”, “may”, “could” , “would”, “will”, or “plan”. Since forward -looking

statements are based on assumptions and address future events and conditions, by their very nature

they involve inherent risks and uncertainties. Although these statements are based on information

currently available to the Company, the Company provides no assurance that actual results will meet

management’s expectations. Risks, uncertainties and other factors involved with forward -looking

information could cause actual events, results, performance, prospe cts and opportunities to differ

materially from those expressed or implied by such forward -looking information. Forward -looking

information in this news release includes but is not limited to: the Company's plans and expectations

for La Parrilla; the timeline for the completion of the rehabilitation work and sulphide circuit expansion

activities at La Parrilla; the timeline for the delivery new equipment; and the timeline and ability to place

the La Parrilla Complex back into operation.

In making the forward -looking statements included in this news release, the Company has applied

several material assumptions, including but not limited to the following: the Company´s financial

condition and development plans do not change because of unforeseen events, and management’s

ability to execute its business strategy; no unexpected or adverse regulatory changes with respect to

La Parrilla; the ability of contractors hired by the Company to complete their work on-time, on-budget,

and within the technical specifications required in their contracts; and the decision to potentially place

La Parrilla into production, and any related production decisions are largely bas ed on internal

Company data and reports from previous operations and not based on NI 43 -101 compliant reserve

estimates, preliminary economic assessments, pre -feasibility or feasibility studies, resulting in

increased uncertainty and higher risks of economic and technical failure than would be the case if

such studies were completed and relied upon to support a production decision. No mineral reserves

have been established for La Parilla, and mineral resources that are not reserves do not have

demonstrated economic viability.

Forward-looking statements and information are subject to various known and unknown risks and

uncertainties, many of which are beyond the ability of the Company to control or predict, that may

cause the Company’s actual results, performance or achievements to be materially different from

those expressed or implied thereby, and are developed based on assumptions about such risks,

uncertainties and other factors set out herein.

Such forward -looking information represents managements best judgment based on information

currently available. No forward -looking statement can be guaranteed, and actual future results may

vary materially. Accordingly, readers are advised not to place und ue reliance on forward -looking

statements or information.