Silvercorp Updates El Domo Development Plans and Staffing
1
NEWS RELEASE
Trading Symbols: SVM (TSX/NYSE American)
SRL (TSXV), SRLZF (OTCQB)
Silvercorp Updates El Domo Development Plans and Staffing
VANCOUVER, British Columbia –August 21, 2024 – With the success ful acquisition of Adv entus Mining
Corporation on July 31, 2024 and the receipt of the Change of Phase for the El Domo copper-gold project
(the “Project”) (see August 6, 2024 news release) , Silvercorp Metals Inc. (“Silvercorp” or the “Company”)
(TSX/NYSE American: SVM), its Ecuadorian subsidiary , Curimining S.A. (“Curimining”) , and Salazar
Resources Limited (TSX-V: SRL, OTCQB: SRLZF) (“Salazar”, collectively with Silvercorp, and Curimining, the
“Companies”), are pleased to report that the Companies have initiated the process for construction with a
goal to bring the Project into production some time in 2026, as previously planned.
Senior Mining Executives Added to the Team
Silvercorp has recently hired Jaymes Dircks to be the General Manager of Curimining, to lead the
construction of the Project. Jaymes specializes in mine construction and project management. Previously,
he worked at B2Gold Corp. where he was the General Manager of B2Gold Nunavut. Prior to that, he was
with Sabina Gold & Silver Corp. where he was the construction director of the Backriver Project in Nunavut,
and Aldridge Minerals Inc. where he was the EPC director for the Yenipazar mine in Turkey. Jaymes has over
30 years of experience in all aspects of mining development, with a focus on on-site construction leadership.
Jaymes will spend the preponderance of his time in Ecuador at the Project site.
In addition to Jaymes, the Company has also hired a senior mining engineer with experience in building and
operating large scale open pittable copper mines.
Construction Preparation and Flowsheet Improvement
The Company has also identified several priority and parallel projects, such as 1) further metallurgical test
work to improve metal recoveries , 2) advancing the power supply for mine operation, as well as
optimization and improvement of access infrastructure, 3) completing D etailed Engineering Design,
including the improved operational efficiency of the process plant, mining pit optimization and construction
planning based on the 2021 Feasibility Study 1, and 4) reviewing and selecting suitable vendors, such as
experienced mine, process plant and tailing s storage facility builders, and processing equipment
manufacturers for the mills.
The metallurgical test work may have the most impact on the improvement of the economics of the Project.
The current flow sheet, as defined in the 2021 Feasibility Study, floats all sulphide minerals (“bulk float”) in
the rougher circuit, including copper (“Cu”), zinc (“Zn”), lead (“Pb”) and pyrite first, and then separate s
copper, zinc, and lead into three different concentrates, with approximately 36% of the gold (“Au”) and
33% of the silver (“Ag”) reporting to the copper concentrate, and approximately 15% of the Au and 24% of
the Ag reporting to the zinc concentrate.
1 NI 43-101 Technical Report Feasibility Study Curipamba El Domo Project Central Ecuador, Effective Date October 26, 2021,
available on www.sedarplus.ca
2
After reviewing the 2019 metallurgical study by Base Met Labs, located in Kamloops, British Columbia and
Curimining, the Company has found that the tests that sequentially floating copper first yielded much higher
Au and Ag recoveries (see table below) at the lower concentrate mass pull than the current bulk flotation
flowsheet, especially the Test #26, which yielded a rougher copper concentrate with 87% Cu, 74% Au, and
53% Ag recoveries. For unknown reasons, these sequential selective flotation of copper upfront tests were
not continued after 2019.
Based on this analysis, the Company plans to drill for metallurgical samples for further testing. Any potential
process optimization arising from this test work will still result in the Project producing the same three
different concentrates via a flotation process . In parallel to the metallurgical drilling, a five -hole
geotechnical drilling campaign has also been planned to optimize open pit slope design and mine planning.
Qualified Person
Jinxing Ji, P. Eng., an independent consultant engaged by Silvercorp is a qualified person under N ational
Instrument 43-101 Standards of Disclosure for Mineral Projects (“NI 43-101”), and has reviewed and given
consent to the scientific and technical information contained in this news release.
About Silvercorp
Silvercorp is a Canadian mining company producing silver, gold, lead, and zinc with a long history of
profitability and growth potential. The Company’s strategy is to create shareholder value by 1) focusing on
generating free cashflow from long-life mines; 2) organic growth through extensive drilling for discovery; 3)
ongoing merger and acquisition efforts to unlock value; and 4) a long -term commitment to responsible
mining and ESG. For more information, please visit our website at www.silvercorpmetals.com.
About Salazar
Salazar Resources Limited is focused on creating value and positive change through discovery, exploration,
and development in Ecuador. The team has an unrivalled understanding of the geology in -country and has
played an integral role in the discovery of many of the major projects in Ecuador, including the two newest
operating gold and copper mines. Salazar Resources has a wholly owned pipeline of copper-gold exploration
projects across Ecuador with a strategy to make another commercial discovery and farm -out non -core
assets. The Company actively engages with Ecuadorian communities and together with the Salazar family
it co -founded The Salazar Foundation, an independent non -profit organization dedicated to sustainable
progress through economic development. Th e Company already has carried interests in three projects. At
its maiden discovery, Curipamba, Salazar Resources has a 25% stake fully carried through to production. At
3
two copper-gold porphyry projects, Pijili and Santiago, the Company has a 20% stake fully carried through
to a construction decision.
About the El Domo Project
El-Domo is a high grade copper -gold project located in Central Ecuador, approximately 150 km northeast
of the major port city of Guayaquil – about a 3-hour drive. The project concessions span low-lying hills and
plains between 300 to 900 masl. El Domo is a flat-lying tabular shaped VMS deposit, with mineralization
beginning at 30 metres from surface and dimensions of approximately 800 x 400 metres. Three well -
maintained gravel roads provide direct site access to El Domo.
For further information:
Silvercorp Metals Inc.
Lon Shaver
President
Phone: (604) 669-9397
Toll Free 1(888) 224-1881
Email: [email protected]
Website: www.silvercorpmetals.com
CAUTIONARY DISCLAIMER - FORWARD-LOOKING STATEMENTS
This news release includes “forward -looking statements” within the meaning of the United States Private
Securities Litigation Reform Act of 1995 and “forward-looking information” within the meaning of applicable
securities laws relating to, among other thi ngs the discussions regarding strategies for the development of
the Project; the start of construction at the Project and the timing of bringing it into production; the timing
and results of further metallurgical tests, geotechnical drilling, advancing power supply, optimizing access
infrastructure, completing detailed engineering design, improving process plant efficiency, mining pit
optimization, and selecting vendors for mine, process plant, tailings storage, and mill equipment. By their
very nature, forward-looking statements involve known and unknown risks, uncertainties and other factors
that may cause our actual results, performance or achievements to be materially different from any future
results, performance or achievements expressed or implied by the forward -looking statements. These
forward-looking statements and information reflect the Company’s current views with respect to future
events and are necessarily based upon a number of assumptions that, while considered reasonable by the
Company, are inherently subject to significant operational, business, economic and regulatory uncertainties
and contingencies. Such factors and assumptions include, amongst others, risks related to the exploration,
development, production, recoveries and other anticipated or possible future developments at the Project,
including, without limitation, that exploration, development and production activities will not occur or be as
anticipated; business integration risks; the outcome of the appeal (the “Appeal”) to the provincial court of
the ruling made by the local court in Las Naves Canton, Bolívar Province, Ecuador in respect of litigation
brought by a group of plaintiffs concerning the environmental co nsultation process for the Project; change
in national and local governments, legislation, taxation, controls, regulations and political or economic
developments; all necessary permits, licenses and regulatory approvals for our operations are received in a
timely manner; interpretations of s cientific and technical information; fluctuations in spot and forward
prices of copper or certain other commodities; risks and hazards associated with the business of mineral
exploration, development and mining (includin g environmental hazards, industrial accidents, unusual or
unexpected formations pressures, cave -ins and flooding); discrepancies between actual and estimated
metallurgical recoveries; the presence of laws and regulations that may impose restrictions on min ing;
employee relations; relationships with and claims by local communities and indigenous populations;
availability of increasing costs associated with mining inputs and labour; the speculative nature of mineral
4
exploration and development (including the risks of obtaining necessary licenses, permits and approvals
from government authorities); title to properties; joint venture partners; our ability to comply with
environmental, health and safety laws; environment al risks; foreign exchange rate fluctuations; key
personnel; dependence on management; and the economic, business and political conditions in China,
Ecuador and Canada. The foregoing list of assumptions is not exhaustive. Forward-looking information may
in some cases be identified by words such as “will”, “anticipates”, “expects”, “intends” and similar
expressions suggesting future events or future performance.
We caution that all forward -looking information is inherently subject to change and uncertainty and that
actual results may differ materially from those expressed or implied by the forward -looking information. A
number of risks, uncertainties and other fac tors, including the Appeal or subsequent developments in the
litigation and potential impacts of the Appeal or such subsequent litigation developments on the Project,
could cause actual results and events to differ materially from those expressed or impli ed in the forward -
looking information or could cause our current objectives, strategies and intentions to change. Accordingly,
we warn investors to exercise caution when considering statements containing forward-looking information
and that it would be unr easonable to rely on such statements as creating legal rights regarding our future
results or plans. We cannot guarantee that any forward -looking information will materialize and you are
cautioned not to place undue reliance on this forward-looking information. Any forward-looking information
contained in this news release represent expectations as of the date of this news release and are subject to
change after such date. However, we are under no obligation (and we expressly disclaim any such
obligation) t o update or alter any statements containing forward -looking information, the factors or
assumptions underlying them, whether as a result of new information, future events or otherwise, except as
required by law. All of the forward -looking information in th is news release is qualified by the cautionary
statements herein.
A comprehensive discussion of other risks that impact Silvercorp can also be found in their public reports
and filings which are available under its profile at www.sedarplus.ca.
CAUTIONARY NOTE TO US INVESTORS
The technical and scientific information contained herein has been prepared in accordance with NI 43‐101
and the Canadian Institute of Mining, Metallurgy and Petroleum classification system, which differs
significantly from the standards adopted by the U.S. Securities and Exchange Com mission (the “SEC”).
Accordingly, the technical and scientific information contained herein, including any estimates of mineral
reserves and mineral resources, may not be comparable to similar information disclosed by U.S. companies
subject to the disclosure requirements of the SEC.
Additional information relating to the Company, including Silvercorp’s Annual Information Form, can be
obtained under the Company’s profile on SEDAR+ at www.sedarplus.ca, on EDGAR at www.sec.gov, and on
the Company’s website at www.silvercorpmetals.com.