Silvercorp reports that the GC Project has a net present value of US$160M pre-tax or US$120M post-tax at 8% discount rate

Economic Studies

1

NEWS RELEASE

Trading Symbol: TSX: SVM

NYSE American: SVM

Silvercorp reports that the GC Project has a net present value of US$160M pre-tax or

US$120M post-tax at 8% discount rate

VANCOUVER, British Columbia –July 25, 2018 – Silvercorp Metals Inc. (“Silvercorp” or the “Company”)

(TSX / NYSE American: SVM) is pleased to report the results of an updated National Instrument (“NI”) 43 -

101 Technical Report with an effective date of June 30, 2018 (Mineral Resources and Mineral Reserves

effective December 31, 2017), prepared by AMC Mining Consultants (Canada) Ltd. (“AMC”) on the

Gaocheng silver-zinc-lead property in Guangdong Province, People’s Republic of China (the “Gaocheng NI

43-101 Technical Report”).

The four authors of the Gaocheng NI 43 -101 Technical Report all qualify as independent Qualified

Persons. Two of the authors visited the Gaocheng Property in January 2018. AMC examined all aspects of

the project, including drill core, underground workings, processing plant and surface infrastructure. The

Gaocheng NI 43-101 Technical Report, with an effective date of 30 June 2018, will be made available for

review on the SEDAR system and on the Company’s website at www.silvercorp.ca in due course.

The Mineral Resource estimates for the Gaocheng property were prepare d by Mr. Shiping Yin, Resource

Geologist of Silvercorp using Micromine TM, and were verified by Ms. Dinara Nussipakynova, P.Geo . of

AMC using DatamineTM software, who takes responsibility for those estimates.

The Mineral Reserve estimates for the Gaocheng property were prepared by the Silvercorp Gaocheng

mining engineering team and were verified by Mr. H. A. Smith, P.Eng. of AMC, who takes responsibility for

those estimates.

Highlights of the Gaocheng NI 43-101 Technical Report

Mineral Reserves of 3.56 million tonnes in the Proven and Probable categories grading 96 grams per

tonne (g/t) silver (Ag), 1.4% lead (Pb), and 3.1% zinc (Zn), containing 11 million ounces silver, 112 million

pounds lead, and 240 million pounds zinc.

From the start of operations at Gaocheng in 2014 through to December 31 , 2017, 987,000 tonnes have

been mined at average head grades of 98 g/t silver, 1.5% lead and 2.7% zinc.

Based on Proven and Probable Reserves only, the GC mine is a viable operation with a projected Life of

Mine (LOM) of 12 years through to 2030, with an average annual production rate of approximately

300,000 tonnes, and with average silver equivalent grades of the order of 335 g/t for the first eight years

and then 240 g/t for the remainder of the mine life. GC also has the potential to extend the LOM beyond

2030, via conversion of existing Mineral Resources to Mineral Reserves, and further exploration and

development.

2

Based on the LOM production forecast and the metal pric e and other assumptions shown under

‘Economic Analysis’ below, a base case pre -tax NPV at 8% discount rate of $160M is projected ($120M

post-tax). Over the LOM, 45% of the net revenue is projected to come from zinc, 35% from silver and 20%

from lead.

As part of an economic sensitivity assessment, metal prices more in line with those current at the time of

writing of this Technical Report (silver – $16.75/troy ounce, lead – $1.14/lb, zinc – $1.45/lb) indicate a

pre-tax NPV at 8% discount rate of $176M ($13 2M post-tax). For this scenario, 49% of the net revenue is

projected to come from zinc, 29% from silver and 22% from lead.

In comparison with the Mineral Reserve estimate in the previous Te chnical Report (effective date January

23, 2012 and pre -operations), there is a 264% increase in Proven Mineral Reserve tonnes and a 56%

decrease in Probable Mineral Reserve tonnes, with a decrease in Mineral Reserve total tonnes of 25%

(1,186,000 t).

Mineral Resources at December 31 , 2017 total 6.4 million tonnes (inclu sive of Mineral Reserves) in the

Measured and Indicated categories grading 96 g/t Ag, 1.3% Pb, and 2.9% Zn, containing approximately 20

million ounces silver, 181 million pounds lead, and 412 million pounds zinc.

Measured and Indicated tonnes have decreased by 16%, which is due to a combination of mining

depletion and change in classification method. Inferred Mineral tonnes have decreased by 6%. In the

Measured plus Indicated category, grades have decreased for silver by 21% and for zinc by 6%. The lead

grade remains unchanged. In the Inferred category, grades have decreased for silver, lead, and zinc by

13%, 16% and 2% respectively.

The results of the underground drilling program at GC show that vein structures are still open at depth.

2018 Mineral Resource and Mineral Reserve Summary

The previous independent Mineral Resource and Mineral Reserve estimates on the property were at

December 31, 2011 (T echnical Report effective date January 23, 2012). Silvercorp completed its first

phase of diamond drilling on the Gaocheng property in 2008. Systematic drilling commenced on the

property in 2011 and continued through to 2017. All Silvercorp drilling was completed as NQ -sized core.

Drillhole collars were surveyed using a total station and down h ole surveys were completed every 50 m

downhole. Core recoveries varied between 41.7% and 100% averaging 96.9%.

Mineral Resources:

The Mineral Resource estimates for the Gaocheng property were prepared by Mr Shiping Yin, Resource

Geologist of Silvercorp , and were reviewed by independent Qualified Person, Ms. Dinara Nussipakynova,

P.Geo of AMC who takes responsibility for the estimates. As a result of a recommendation in the 2012

Technical Report, the December 2017 Resources were estimated using a block m odelling approach, with

MicromineTM software. Interpolation was carried out using inverse distance cubed (ID 3) for all the veins.

Estimates were made for a total of 89 mineralized vein structures for the Gaocheng property.

The Mineral Resources are reporte d above a cut-off of 100 g/t silver equivalent (AgEq). Cut -off grades are

based on in situ values in AgEq terms in grams per tonne (after application of mining recovery and

payable values) and incorporate all mining and processing costs provided by Silverc orp and reviewed by

AMC.

The estimated Mineral Resources and metal content for the property as of December 31, 2017 are

detailed in Table 1 below.

3

Table 1 Gaocheng Property - Measured & Indicated, and Inferred Mineral Resources

(Inclusive of Mineral Reserves)

Resource classification Tonnes (Mt) Ag (g/t) Pb (%) Zn (%)

Contained metal

Ag (koz) Pb (Mlbs) Zn (Mlbs)

Measured 2.735 101 1.4 3.2 8,840 84 195

Indicated 3.638 92 1.2 2.7 10,818 98 217

Measured and Indicated 6.374 96 1.3 2.9 19,658 181 412

Inferred 7.481 107 1.2 2.6 25,662 196 429

Notes: CIM Definition standards (2014) were used for reporting the Mineral Resources

Mineral Resource are reported at a cut-off grade of 100 g/t AgEq.

The equivalency formula is Ag g/t+44.6*Pb%+43.5*Zn% using prices of $19/oz Ag, $1.00/lb Pb and $1.25/lb Zn and estimated

recoveries of 77% Ag, 86% Pb, and 83% Zn.

Drilling results up to December 31, 2017.

Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

The numbers may not compute exactly due to rounding.

Source: Silvercorp, reproduced as a check by AMC Mining Consultants (Canada) Ltd.

Mineral Reserves

The Mineral Reserve estimates for the Gaocheng property were prepared by Silvercorp under the

guidance of independent Qualified Person, Mr. H. A. Smith, P.Eng, who takes QP responsibility for those

estimates. The assumption has been made that current stopi ng practices will continue to be employed at

the Gaocheng property, namely predominantly shrinkage stoping but also with a relatively small amount

of cut and fill resuing, using hand -held drills and hand -mucking within stopes, and loading to mine cars by

rocker-shovel or by hand. Minimum mining widths of 1.0 m for shrinkage and 0.5 m for resuing are

assumed.

Average dilution beyond planned mining widths has been estimated at 13%, while assumed mining

recovery factors are 92% for shrinkage stopes and 95% for resuing stopes.

The Gaocheng NI 43 -101 Technical Report defines Mineral Reserves of 3.56 million tonnes in the Proven

and Probable categories grading 96 g/t Ag, 1.4% Pb, and 3.1% Zn, containing 11 million ounces silver, 112

million pounds lead, and 240 million pounds zinc. Mineral Reserve tonnes are noted to be 56% of Mineral

Resource (Measured plus Indicate d) tonnes. Silver, lead and zinc Mineral Reserve grades are 100%, 110%

and 104% respectively of the corresponding Measured plus Indicated Mineral Resource grades. Metal

content conversions for silver, lead and zinc from Measured plus Indicated Mineral Resources to Proven

plus Probable Mineral Reserves are 56%, 62% and 58% respectively.

Table 2 Gaocheng Property - Mineral Reserves

Reserve classification Tonnes (Mt) Ag (g/t) Pb (%) Zn (%)

Contained metal

Ag (koz) Pb (Mlbs) Zn (Mlbs)

Proven 1.691 96 1.4 3.2 5,219 53 120

Probable 1.873 97 1.4 2.9 5,841 58 121

Proven and Probable 3.564 96 1.4 3.1 11,000 112 240

Notes to Mineral Reserve Statement:

Full breakeven cut-off grades: Shrinkage = 180 g/t AgEq: Resuing = 245 g/t AgEq.

Marginal material cut-off grade: 145 g/t AgEq.

Dilution (zero grade) assumed as 0.1 m on each wall of a shrinkage stope and 0.05 m on each wall of a resuing stope.

Mining recovery factors assumed as 95% for resuing and 92% for shrinkage.

Metal prices: Silver US$19/troy oz, lead US$1.00/lb, zinc US$1.25/lb.

Processing recovery factors: Ag – 77%, Pb - 86%, Zn – 83%.

Effective date December 31, 2017.

Exchange rate assumed is RMB 6.50: US$1.00.

Rounding of some figures may lead to minor discrepancies in totals.

4

Table 3 Mineral Reserve Cut-off Grades and Key Estimation Parameters

Item Gaocheng Mine

Foreign exchange rate (RMB:US$) 6.5 6.5

Shrinkage Resuing

Operating costs

Mining cost (includes development & exploration) ($/t) 37.37 63.56

Milling cost ($/t) 15.69 15.69

G&A and product selling cost ($/t) 7.41 7.41

Sustaining capital ($/t) 3.63 3.63

Mineral Resources tax ($/t) 3.21 3.21

Total operating costs (US$/t) 67.31 93.50

Mining recovery (%) 92 95

Mill recoveries

Ag (%) 77 77

Pb (%) 86 86

Zn (%) 83 83

Breakeven COG (AgEq g/t) 180 245

Metal price assumptions: Ag $19/oz; Pb $1.00/lb; Zn $1.25/lb.

Economic analysis

Although Silvercorp is a producing issuer and, therefore, does not require an economic analysis for the

purposes of th e Gaocheng NI 43 -101 Technical R eport, AMC considered it reasonable to include a

summary-level analysis to illustrate the potential economic impact relative to the latest Mineral Reserve

estimation and to the associated production schedule.

The Gaocheng mine has been in commercial production for four years. From FY 2019 onwards, a 12 -year

LOM is envisaged for the resource as currently understood, with average silver equivalent grades

projected to be of the order of 335 g/t for the first eight years an d then to fall to an average of 240 g/t for

the remainder of the mine life. Operating and capital costs are anticipated to be reasonable. For the

summary economic assessment, AMC has largely used FY 2019 budget cost projections, and the same

metal prices as in the Mineral Reserve estimation, namely:

Silver US$19.0/oz

Lead US$1.00/lb

Zinc US$1.25/lb

A provision for government fees and mineral resource taxes at 5% of net revenue is made in the summary

economic analysis, together with an exchange rate assumption of 1US$ = 6.50RMB.

Based on the LOM production profile and the metal price and other assumptions shown above, a base

case NPV at 8% discount rate of $160M (pre-tax), $120M (post-tax) is projected.

Qualified Persons

D. B. Nussipakynova, P.Geo., H. A. Smith, P.Eng., A. Riles , MAIG and P. R. Stephenson, P.Geo. of AMC

Mining Consultants (Canada) Ltd. are Qualified Persons as defined by National Instrument 43 -101. D. B.

Nussipakynova, H. A. Smith, P. R. Stephenson and A. Riles have reviewed and cons ented to this press

release and believe it fairly and accurately represents the information in the Technical Report that

supports the disclosure.

5

About Silvercorp

Silvercorp is a low-cost silver-producing Canadian mining company with multiple mines in China.

The Company’s vision is to deliver shareholder value by focusing on the acquisition of under

developed projects with resource potential and the ability to grow organically. For more

information, please visit our website at www.silvercorp.ca.

For further information

Lorne Waldman

Senior Vice President

Silvercorp Metals Inc.

Phone: (604) 669-9397

Toll Free: 1(888) 224-1881

Email: [email protected]

Website: www.silvercorp.ca

CAUTIONARY DISCLAIMER - FORWARD LOOKING STATEMENTS

Certain of the statements and information in this press release constitute “forward -looking statements”

within the meaning of the United States Private Securities Litigation Reform Act of 1995 and “forward -

looking information” within the meaning of applicable Canadian provincial securities laws. Any statements

or information that express or involve discussions with respect to predictions, expectations, beliefs, plans,

projections, objectives, assumptions or future events or performance (often, but not alway s, using words

or phrases such as “expects”, “is expected”, “anticipates”, “believes”, “plans”, “projects”, “estimates”,

“assumes”, “intends”, “strategies”, “targets”, “goals”, “forecasts”, “objectives”, “budgets”, “schedules”,

“potential” or variations thereof or stating that certain actions, events or results “may”, “could”, “would”,

“might” or “will” be taken, occur or be achieved, or the negative of any of these terms and similar

expressions) are not statements of historical fact and may be forward -looking statements or information.

Forward-looking statements or information relate to, among other things: the price of silver and other

metals; the accuracy of mineral resource and mineral reserve estimates at the Company’s Gaocheng

property; the sufficiency of the Company’s capital to finance the Company’s operations; estimates of the

Company’s revenues and capital expenditures; estimated production from the Company’s Gaocheng

mine; timing of receipt of permits and regulatory approvals; availability of fund s from production to

finance the Company’s operations; and access to and availability of funding for future construction, use of

proceeds from any financing and development of the Company’s properties.

Forward-looking statements or information are subject to a variety of known and unknown risks,

uncertainties and other factors that could cause actual events or results to differ from those reflected in

the forward-looking statements or information, including, without limitation, risks relating to: fluctuatin g

commodity prices; calculation of resources, reserves and mineralization and precious and base metal

recovery; interpretations and assumptions of mineral resource and mineral reserve estimates; exploration

and development programs; feasibility and enginee ring reports; permits an d licenses; title to properties;

property interests; joint venture partners; acquisition of commercially mineable mineral rights; financing;

recent market events and conditions; economic factors affecting the Company; timing, estim ated amount,

capital and operating expenditures and economic returns of future production; integration of future

acquisitions into the Company’s existing operations; competition; operations and political conditions;

regulatory environment in China and Ca nada; environmental risks; foreign exchange rate fluctuations;

insurance; risks and hazards of mining operations; key personnel; conflicts of interest; dependence on

6

management; internal control over financial reporting as per the requirements of the Sarb anes-Oxley Act;

and bringing actions and enforcing judgments under U.S. securities laws.

This list is not exhaustive of the factors that may affect any of the Company’s forward -looking statements

or information. Forward -looking statements or information ar e statements about the future and are

inherently uncertain, and actual achievements of the Company or other future events or conditions may

differ materially from those reflected in the forward -looking statements or information due to a variety of

risks, u ncertainties and other factors, including, without limitation, those referred to in the Company’s

Annual Information Form for the year ended March 31, 2018 under the heading “Risk Factors”. Although

the Company has attempted to identify important factors that could cause actual results to differ

materially, there may be other factors that cause results not to be as anticipated, estimated, described or

intended. Accordingly, readers should not place undue reliance on forward -looking statements or

information.

The Company’s forward -looking statements and information are based on the assumptions, beliefs,

expectations and opinions of management as of the date of this press release, and other than as required

by applicable securities laws, the Company does not assume any obligation to update forward -looking

statements and information if circumstances or management’s assumptions, beliefs, expectations or

opinions should change, or changes in any other events affecting such statements or information. For the

reasons set forth above, investors should not place undue reliance on forward -looking statements and

information.