Silvercorp Reports Operational Results and Financial Results Release Date for Fiscal 2026, and Issues Fiscal 2027 Production, Cash Cost, and Capital Expenditure Guidance
1
NEWS RELEASE
Trading Symbol: TSX/NYSE American: SVM
Silvercorp Reports Operational Results and Financial Results Release Date for Fiscal 2026, and
Issues Fiscal 2027 Production, Cash Cost, and Capital Expenditure Guidance
VANCOUVER, British Columbia – April 16, 2026 – Silvercorp Metals Inc. (“Silvercorp” or the “Company”) (TSX/NYSE American:
SVM) reports production and sales figures for the fourth quarter (“Q4 Fiscal 2026”) and fiscal year ended March 31, 2026 ("Fiscal
2026") and the production and cost guidance for the 2027 fiscal year ending March 31, 2027 ("Fiscal 2027"). Silvercorp expects
to release its Fiscal 2026 audited financial results on Monday, May 25, 2026, after market close.
Q4 Fiscal 2026 Operational Highlights
• Record revenue of approximately $147.4 million, an increase of 96% over the same quarter last year (“Q4 Fiscal 2025”);
• Silver production of 1.5 million ounces, a decrease of 11% over Q4 Fiscal 2025; silver equivalent (only silver and gold) i
production of 1.6 million ounces, a decrease of 17% compared to 1.9 million ounces in Q4 Fiscal 2025;
• Lead production of 14.0 million pounds, a decrease of 14% over Q4 Fiscal 2025;
• Zinc production of 3.9 million pounds, a decrease of 12% over Q4 Fiscal 2025;
• Kuanping mine construction continued, with 1,335 metres ("m") of ramp development, 313 m of exploration tunneling
and 1,625 m of drilling completed;
• El Domo mine construction continued to advance under enhanced water and soil conservation measures during the
heavy rainfall season, with the haul roads and the ore stockpile shed completed; and
• MSCI ESG rating was upgraded from A to AA.
Fiscal 2026 Operational Highlights
• Record revenue of approximately $438.1 million, an increase of 47% over Fiscal 2025;
• Ore processed of 1,475,512 tonnes, up 12% over Fiscal 2025, and beat the high end of 1,369,000 tonnes in the Company's
annual production guidance;
• Silver production of approximately 6.8 million ounces, a 2% decrease over Fiscal 2025; gold production of approximately
8,723 ounces, a 16% increase over Fiscal 2025, and silver equivalent of 7.5 million ounces, even with Fiscal 2025; and
• El Domo mine completed the site preparation for the processing plant, 5,000 square metre ROM ore shed, construction
camp, internal roads, including roads to the TSF construction site, and orders of major equipment.
Q4 Fiscal 2026 Operational Results
2
The Ying Mining District processed 311,677 tonnes of ore, up 2% over Q4 Fiscal 2025. Approximately 1.4 million ounces of silver,
2,492 ounces of gold, or 1.5 million ounces of silver equivalent, plus 12.9 million pounds of lead, and 1.4 million pounds of zinc
were produced, representing production decreases of 20%, 11%, 18%, 17%, and 30% in gold, silver, silver equivalent, lead and
zinc, respectively, over Q4 Fiscal 2025. Lower production was due to lower head grades associated with an increase in shrinkage
mining. A total of 48,492 m of drilling and 13,239 m of exploration tunneling were completed in Q4 Fiscal 2026.
The GC Mine processed 48,840 tonnes of ore, up 17% over Q4 Fiscal 2025. Approximately 0.1 million ounces of silver, 1.1 million
pounds of lead, and 2.5 million pounds of zinc were produced, representing increases of 3%, 51% and 4% in silver, lead and zinc
over Q4 Fiscal 2025. A total of 6,050 m of drilling and 1,393 m of exploration tunneling were completed in Q4 Fiscal 2026.
3
Q4 Fiscal 2026 Q4 Fiscal 2025
Ying Mining
District GC Consolidated
Ying Mining
District GC Consolidated
Silver-lead Ore Processed (tonnes) 279,627 48,840 328,467 265,199 41,760 306,959
Silver (grams/tonne) 161 52 198 61
Lead (%) 2.2 0.9 2.9 0.9
Zinc (%) 0.4 2.6 0.5 2.9
Gold Ore Processed (tonnes) 32,050 — 32,050 39,025 — 39,025
Gold (grams/tonne) 1.1 — 1.4 —
Silver (grams/tonne) 54 — 62 —
Lead (%) 0.9 — 0.7 —
Total Ore Processed (tonnes) 311,677 48,840 360,517 304,224 41,760 345,984
Recovery Rates
Silver (%) 95.0 86.3 94.2 83.7
Gold (%)* 90.8 — 91.7 —
Lead (%) 93.2 93.5 92.3 87.4
Zinc (%) 63.9 90.6 67.3 90.3
Metals Produced
Silver (million ounces) 1.4 0.1 1.5 1.6 0.1 1.6
Gold (ounces) 2,492 — 2,492 3,110 — 3,110
Silver equivalent (million ounces) 1.5 0.1 1.6 1.9 0.1 1.9
Lead (million pounds) 12.9 1.1 14.0 15.6 0.7 16.3
Zinc (million pounds) 1.4 2.5 3.9 2.0 2.4 4.4
Metals Sold
Silver (million ounces) 1.4 0.1 1.5 1.5 0.1 1.6
Gold (ounces) 2,623 — 2,623 3,465 — 3,465
Lead (million pounds) 12.8 0.8 13.6 15.5 0.8 16.3
Zinc (million pounds) 1.4 2.4 3.9 2.1 2.4 4.5
*Only representing the gold recovery rate for Gold Ore.
Fiscal 2026 Operational Results
At the Ying Mining District, 1,188,459 tonnes of ore were processed, up 17% over Fiscal 2025. A total of 6.3 million ounces of
silver, 8,723 ounces of gold, or 7.0 million ounces of silver equivalent, 55.1 million pounds of lead and 6.6 million pounds of zinc
were produced, representing an increase of 16% in gold and decreases of 1%, 1%, 3% and 23% in silver, silver equivalent, lead
and zinc, respectively, over Fiscal 2025.
4
At the GC Mine, 287,053 tonnes of ore were processed, representing a decrease of 4% over Fiscal 2025. A total of 0.5 million
ounces of silver, 5.2 million pounds of lead, and 15.1 million pounds of zinc were produced, representing an increase of 3% in
zinc, and decreases of 11% and 2% in silver and lead, respectively, over Fiscal 2025.
Year ended March 31, 2026 Year ended March 31, 2025
Ying Mining
District GC Consolidated
Ying Mining
District GC Consolidated
Silver-lead Ore Processed (tonnes) 1,066,970 287,053 1,354,023 927,171 299,036 1,226,207
Silver (grams/tonne) 193 59 225 67
Lead (%) 2.5 0.9 3.0 0.9
Zinc (%) 0.4 2.7 0.6 2.5
Gold Ore Processed (tonnes) 121,489 — 121,489 86,488 — 86,488
Gold (grams/tonne) 1.3 — 1.7 —
Silver (grams/tonne) 61 — 72 —
Lead (%) 0.9 — 0.9 —
Total Ore Processed (tonnes) 1,188,459 287,053 1,475,512 1,013,659 299,036 1,312,695
Recovery Rates
Gold (%)* 92.7 — 92.9
Silver (%) 95.4 85.7 94.7 83.1
Lead (%) 93.7 93.4 93.6 89.3
Zinc (%) 64.1 91.3 69.7 90.3
Metals Produced
Silver (million ounces) 6.3 0.5 6.8 6.4 0.5 6.9
Gold (ounces) 8,723 — 8,723 7,495 — 7,495
Silver equivalent (million ounces) 7.0 0.5 7.5 7.1 0.5 7.6
Lead (million pounds) 55.1 5.2 60.4 56.8 5.3 62.2
Zinc (million pounds) 6.6 15.1 21.7 8.6 14.8 23.3
Metals Sold
Silver (million ounces) 6.4 0.5 6.8 6.4 0.5 6.9
Gold (ounces) 8,857 — 8,857 7,577 — 7,577
Lead (million pounds) 55.0 5.0 60.0 56.8 5.5 62.3
Zinc (million pounds) 6.6 15.1 21.7 8.6 14.9 23.5
*Only representing the gold recovery rate for Gold Ore.
Fiscal 2027 Production, Cash Cost, and Capital Expenditure Guidance
• Guidance for Fiscal 2027 production, cash and all-in sustaining costs (AISC)
5
In Fiscal 2027, the Company expects to process 1,526,600 to 1,607,000 tonnes of ore, yielding approximately 6.8 to 7.1 million
ounces of silver, 9,500 to 10,000 ounces of gold, or 7.5 to 7.8 million ounces of silver equivalent, 62.7 to 65.8 million pounds of
lead, and 22.3 to 23.4 million pounds of zinc. The guidance represents increases of 3% to 9% in ore processed, 0.04% to 4% in
silver, 9% to 15% in gold, 4% to 9% in lead, and 3% to 8% in zinc production compared to the Fiscal 2026 results.
Fiscal 2027 Guidance Year ended March 31, 2026
Production Ying Mining District GC Consolidated
Ying Mining
District GC Consolidated
Low High Low High Low High Actual
Silver-lead Ore
Processed (tonnes) 1,106,000 1,164,000 290,000 305,000 1,396,000 1,469,000 1,066,970 287,053 1,354,023
Silver (gram/t) 201 68 193 59
Lead (%) 2.7 1.0 2.5 0.9
Zinc (%) 0.4 2.7 0.4 2.7
Gold Ore Processed
(tonnes) 131,000 138,000 — — 131,000 138,000 121,489 — 121,489
Gold (gram/t) 1.7 1.3
Silver (gram/t) 42 61
Lead (%) 0.5 0.9
Total Ore Processed
(tonnes) 1,237,000 1,302,000 290,000 305,000 1,526,600 1,607,000 1,188,459 287,053 1,475,512
Metal Production
Silver (million ounces) 6.4 6.6 0.5 0.5 6.8 7.1 6.3 0.5 6.8
Gold (ounces) 9,500 10,000 — — 9,500 10,000 8,723 — 8,723
Silver Equivalent
(million ounces) 7.1 7.3 0.5 0.5 7.5 7.8 7.0 0.5 7.5
Lead (million pounds) 56.4 59.2 6.3 6.6 62.7 65.8 55.1 5.2 60.4
Zinc (million pounds) 6.8 7.1 15.5 16.3 22.3 23.4 6.6 15.1 21.7
Fiscal 2027 Guidance Nine months ended December 31, 2025
Costs Ying Mining District GC Consolidated
Ying Mining
District GC Consolidated
Cash Cost ($/t) 88.2 90.4 63.1 64.6 83.3 85.4 80.2 57.8 75.5
AISC ($/t) 155.4 161.2 90.4 93.3 155.3 161.2 134.1 82.9 137.2
The Ying Mining District plans to process 1,237,000 to 1,302,000 tonnes of ore, including nominal development ore from
Kuanping, to produce 6.4 to 6.6 million ounces of silver, 9,500 to 10,000 ounces of gold, 56.4 to 59.2 million pounds of lead, and
6.8 to 7.1 million pounds of zinc for Fiscal 2027. This production guidance represents production increases of 4% to 10% in ore,
0.1% to 4% in silver, 9% to 15% in gold, 2% to 7% in lead and 3% to 8% in zinc, compared to the Fiscal 2026 results.
The cash costii at the Ying Mining District is expected to be $88.2 to $90.4 per tonne of ore, compared to the cash cost of $80.2
for the first nine months of Fiscal 2026 ended December 31, 2025. The all -in sustaining cost (AISC)ii is estimated at $155.4 to
$161.2 per tonne, higher than the AISC of $134.1 recorded in the first nine months of Fiscal 2026. The higher cash cost and AISC
6
are due to anticipated increases in contractor unit costs and more development tunnels and facilities planned for higher ore
production in Fiscal 2027 and beyond. More details on the near and longer term mine plan will be contained in an updated NI
43-101 technical report expected to be released in the coming weeks.
The GC Mine plans to process 290,000 to 305,000 tonnes of ore to produce 0.46 to 0.49 million ounces of silver, 6.3 to 6.6 million
pounds of lead, and 15.5 to 16.3 million pounds of zinc. Fiscal 2027 production guidance at the GC Mine represents production
increases of 1% to 6% in ore and 0.4% to 7% in silver, 20% to 26% in lead and 2% to 8% in zinc compared to the Fiscal 2026
results.
The cash cost at the GC Mine is expected to be $ 63.1 to $64.6 per tonne of ore, compared to $57.8 recorded in the first nine
months of Fiscal 2026. The AISC is estimated at $90.4 to $93.3 per tonne of ore processed, compared to $82.9 recorded in the
first nine months of Fiscal 2026 as more exploration tunneling has been planned in Fiscal 2027.
The consolidated cash cost in Fiscal 2027 is expected to be $83.3 to $85.4 per tonne, while the consolidated AISC is expected to
be $155.3 to $161.2 per tonne.
Fiscal 2027 capital expenditure guidance for China Operations
The table below summarizes the capital expenditures the Company expects to incur for our China Operations in Fiscal 2027.
Fiscal 2027 Guidance
Ying Mining
District GC Mine Kuanping Total
Capitalized
Expenditures
Ramp and Development Tunneling (Metres) 53,200 4,500 7,600 65,300
($ Million) 37.2 2.7 3.9 43.8
Exploration Tunneling (Metres) 90,200 14,200 4,400 108,800
($ Million) 35.3 5.9 1.4 42.6
Diamond Drilling (Metres) 91,100 34,300 5,300 130,700
($ Million) 2.8 0.8 0.2 3.8
Facilities and Equipment ($ Million) 26.1 0.7 1.3 28.1
No. 3 Mill ($ Million) 22.7 — — 22.7
Total ($ Million) 124.1 10.1 6.8 141.0
1. Ying Mining District
The total capital expenditures at the Ying Mining District in Fiscal 2027 is estimated at $124.1 million as the Company continues
to increase production and grow its mineral resources.
• $37.2 million to develop 53,200 m of ramps and tunnels, enabling access for mining of new areas where exploration
has identified additional material, to be outlined in the upcoming technical report;
• $35.3 million to develop 90,200 m of exploration tunnels and to spend $ 2.8 million to drill 91,100 m of exploration
diamond drill holes;
• $26.1 million in facilities and equipment upgrades. Major items include $6.8 million for mining equipment replacement,
$7.6 million for waste dump construction, $4.5 million for substation upgrades and $5.6 million for infrastructure and
the TSF; and
7
• $22.7 million out of the total $31.6 million to build a new mill, the No. 3 Mill, expected to add 3,000 tonnes per day of
capacity, and be commissioned in Q1 Fiscal 2028.
The No. 3 Mill is under design and construction, and intended to meet the increasing demand on ore processing at the Ying
Mining District where annual mine throughput is expected to reach 1.6 million tonnes per year by fiscal year 2029. The No. 1
Mill will be decommissioned, leaving Ying with a net effective 6,300 tonnes per day of milling capacity.
The following table summarizes the estimated budget and construction schedules for the new Mill:
Category Description
Target
Completion
Schedule
Estimated Expenditures
(in millions of US$)
Fiscal 2027 Beyond Fiscal
2027 Total
Design & Permitting
Land Lease & Rezoning Apr-26 0.6 - 0.6
Design & Engineering May-26 0.2 - 0.2
Environmental & Safety Assessment Jul-26 0.1 - 0.1
Construction &
Equipment
Site Preparation Apr-26 0.8 0.3 1.1
Road Construction Jun-27 0.4 0.2 0.5
Mill Construction Mar-27 6.5 2.8 9.2
Equipment Acquisition Nov-26 10.8 0.6 11.4
Installation Mar-27 1.0 2.7 3.7
Contingency Apr-27 2.4 2.4 4.7
Total Expenditures 22.7 8.9 31.6
• Development tunneling, equipment replacement and facilities upgrades, other than the new mill, have been included
in AISC.
2. GC Mine
The total capital expenditures at the GC Mine in Fiscal 2027 is estimated at $10.1 million to maintain its production and mineral
resources.
• $2.7 million to develop 4,500 m of ramps and tunnels;
• $5.9 million to develop 14,200 m of exploration tunnels and to spend $ 0.8 million to drill 34,300 m of exploration
diamond drill holes; and
• $0.7 million on equipment replacement, facility upgrades and construction.
• Development tunneling, equipment replacement and facilities upgrade have been included in AISC.
3. Kuanping Project
Underground mine construction continues as preparations for production move forward, with a total investment of $6.8 million
which includes $3.9 million for 7,600 m of ramp and tunnel development, $1.4 million for 4,400 m of exploration tunnels, $0.2
million for 5,300 m of diamond drilling and $1.3 million for equipment and facilities.
Fiscal 2027 capital expenditure guidance for Ecuador Operations
1. El Domo Project
8
The table below summarizes the costs to construct the El Domo Project:
Fiscal 2027
($ Million)
1 Package #1 - Site preparation/Roads/Channels/TSF/SWD $ 27.7
2 Package #2 - Open Pit Mining and Stripping 23.1
3 Package #3 - Processing Plant Construction and Equipment 36.1
4 Temporary and Permanent Camps 3.0
5 Packages #4, 5 -Site Infrastructure (bypass roads, power line, standby diesel
generators, water treatment plant)
23.8
Direct costs sub-total $ 113.7
6 Owner's Contingency 11.5
7 Owner's Cost 12.8
8 Value added tax (VAT) 21.8
Total $ 159.8
The total budget for the El Domo project remains unchanged at $283.6 million, consistent with the February revised budget,
with an expected completion date of July 1, 2027. Spending in Q4 Fiscal 2026 totaled $15.9 million. Key activities included site
preparation for the processing plant, construction of the ore shed, camp and internal roads, and ordering of major equipment.
Package #1 - Site Preparation/Roads/Channel/TSF/SWD
Package #1 earthworks and related activities have been conducted by CRCC 14 since January 2025, with the capital costs
estimated based on the unit prices as indicated in the contract multiplied by the design quantities of each activity.
Package #2 – Open Pit Mining and Stripping
The mining contract for the construction and operation of Package #2 was awarded to China Railway 19th B ureau Group Co.,
Ltd. ("CRCC19") with the cost estimated based on the optimized mine plan and contracted unit rates of drilling, blasting, and
hauling etc received from CRCC19. The Company expects to commence stripping of the open pit in April 2026 and a total of 4.1
million cubic metres of sediments and waste rocks will be stripped.
Package #3 - Processing Plant Construction and Equipment
The detailed process flowsheet and equipment selection for the processing plant construction and equipment have been
finalized by Yantai Jinpeng Mining Machinery Co., Ltd, with the cost estimated based on the engineering design, actual contract
and purchase prices for major equipment from international vendors, market prices for minor equipment in China plus shipping
cost, current construction cost in Ecuador .
Power line construction and Stand-by Diesel Power Generators
The construction of the power line is expected to be initiated in June 2026 and should take approximately 12 months to be
completed. The 14MW diesel generator sets will be delivered to site by December 2026 for installation and operation before