Vancouver, BC – November 16, 2021 - Silver One Resources Inc. (TSXV: SVE ; OTCQX: SLVRF; FSE: BRK1 -
“Silver One” or the “Company”) is pleased to announce the completion of 796 meters of the planned 1,500-
meter diamond drilling program on its 100% owned Cherokee Project located in eastern Nevada, USA (see
Company news release of August 15, 2021). Silver One experienced extremely slow drilling and technical
issues, which led to the early termination of this program. As such, the Company was unable to fully test all
desired targets.
Four of the nine holes intersected strongly anomalous silver and copper mineralization near to the historic
Cherokee and Southeast Cherokee workings (see Figure 1 and Table 1). The mineralization is associated with
thick quartz veining (up to 25 meters thick in hole GC21-01) hosting narrower silver and copper mineralized
intervals within the vein and structures (see Figures 2 and 3).
Figure 1. Geology map showing drill holes location of the Cherokee and Cherokee southeast areas.
Table 1. Relevant assays Cherokee drilling
Drill holes GC21-03, 05, 07, 08 and 09 are omitted as they had no significant mineral values. Estimated true
widths range from 70% to 90% of the reported intervals. Coordinates and identification drill hole data are in
Table 2 at the end of this release.
Figures 2 and 3. Drill hole GC21-01, 3 Native wire silver within quartz carbonate grains in hole GC21-01.
Figure 2 - Silver-copper mineralization Figure 3 – Native Wire Silver in Drill Core
From (m) To (m) Width (m) Ag (g/t) Cu (%) Area
GC21-01 13.56 19.85 6.29 118.0 0.47 Cherokee main
Includes 16.85 18.40 1.55 455.0 1.84 Cherokee main
GC21-02 40.10 42.00 1.90 70.3 0.28 Cherokee main
46.02 50.90 4.88 59.0 0.28 Cherokee main
GC21-04 18.80 19.70 0.90 48.9 0.13 Cherokee main
GC21-06 38.80 44.25 5.45 80.0 0.40 Cherokee main
Includes 39.47 42.50 3.03 126.5 0.64 Cherokee main
Drill hole
The highest intercepts were around the Cherokee Mine with values in hole GC21-01 averaging 455 g/t silver
plus 1.84% Cu over 1.55 meters from 16.85 meters, within a 6.29 meter interval averaging 118 g/t silver plus
0.47% copper from 13.56 meters. Hole GC21-02 intercepted 4.88 meters of 59 g/t silver plus 0.28% copper
from 46.02 meters. Hole GC21-06 intercepted 5.45 meters of 80 g/t silver plus 0.40% copper from 38.80
meters. All mineralized intervals occur within 50 meters of the surface. (Figure 1 and Table 1). Drilling around
the Cherokee Southeast workings returned anomalous, but low silver and copper values. Drilling immediately
to the northwest of the Cherokee workings returned only weakly anomalous silver and copper values. The
mineralized intervals are also highly anomalous in zinc and lead.
The drilling tested silver-copper-gold epithermal vein targets, on patented claims overlying the past producing
Cherokee and Southeast Cherokee historic workings. Several other targets on the property outside the
Patented Claims remain untested and permitting of some of these areas is planned for 2022. Some of the
more promising targets are the more gold-silver rich areas around the Johnnie Mine and Hidden treasure vein
systems, the relatively untested Mojoto vein and deeper porphyry mineralization that was the target of drilling
in the 1980’s in the Blue Nose and Viola areas of the property. See Figures 1 and 4
Gregory Crowe, President and CEO commented; “The results of this shortened program are encouraging in
that the mineralized structures remain open to depth and other anomalous surface values occur off the
patented claims to the northwest and southeast of the area drilled. More importantly, this program only
targeted one vein system on the patented claims. Numerous other veins and areas of alteration with high
silver-copper-gold select surface values occur over a 12 km strike length throughout the property and will be
targeted after permitting in 2022. The southeast area of the property is also highly prospective for potential
porphyry style copper and or molybdenum mineralization, with targets identified by geophysics and surface
geochemistry. The abundance of veins and alteration areas hosting strongly elevated silver-gold-copper values
identifies Cherokee as a high-priority exploration project.”
Figure 4. Total magnetic intensity map of the Cherokee project showing main target areas
Cherokee is an emerging epithermal silver, gold and copper district located approximately 75 kilometers south
of the historic Pioche silver-gold-copper-zinc-lead mining camp. Silver One’s property covers 5,200 hectares
(52 square kilometers) covering a 12-kilometre long by 4-kilometre wide structurally controlled silver-copper-
gold system. It is hosted by Paleozoic aged sediments, similar in part to the host rocks for the mineralized
systems at Pioche. From 1869 to present, the neighboring Pioche area mined over 6 million tons producing
over 1 million ounces of gold, 20 million ounces of silver, 7 million pounds of copper, 350 million pounds of
lead and 700 million pounds of zinc. Production was initially from gold-silver-copper epithermal veins and
later from underlying carbonate-hosted replacement-type mineralized bodies.
QA/QC
The QA/QC program included the submission of Certified Reference Materials, blanks and core duplicates, at
random intervals. Certified Standards were inserted at a rate of one standard for every 20 samples (5% of
total) and one blank for every 20 samples (5% of total). Core duplicates were inserted at a rate of one duplicate
per every 20 samples (5% of total). The standards used in Cherokee’s drilling program range in grade from
5.88 g/t Ag to 493.0 g/t Ag, and were sourced from Analytical Solutions, Ltd., in Mulmur, ON, Canada and from
OREAS, Bayswater North, VIC, Australia. Blanks have been sourced locally from barren silica. Core duplicates
were obtained from quartered core.
Samples were assayed by American Assay Laboratories (“AAL” in Sparks, NV, USA. (IAS accredited Laboratory,
ISO/IEC 17025:2005. AAL also inserts blanks, standards and includes duplicate analyses to ensure proper
sample preparation and equipment calibration.
Company’s Projects Update
The company is also advancing its Phoenix Silver project in Arizona and Candelaria in Nevada.
Drill permitting is underway at Phoenix Silver. A Plan of Operations has been filed at the Tonto National Forest
(TNF) and, barring TNF delays, permitting is expected by the end of December-2021.
A 15,000meter RC and diamond drilling campaign was recently completed in Candelaria, with final assays
reported in the July 15, 2021 news release. Metallurgical testing is underway. A second phase of drilling is
scheduled to commence in December 2021 or January 2022. This drill program will be followed by a resource
estimate in preparation for an economic evaluation scheduled to be completed by 2H 2022.
Qualified Person
The technical content of this news release has been reviewed and approved by Greg Crowe, P. Geo, President
and CEO of Silver One, and a Qualified Person as defined by National Instrument 43-101.
Table 2. RC holes coordinates (UTM WGS84) and other identification data
About Silver One
Silver One is focused on the exploration and development of quality silver projects. The Company holds an
option to acquire a 100%-interest in its flagship project, the past-producing Candelaria Mine located in
Nevada. Potential reprocessing of silver from the historic leach pads at Candelaria provides an opportunity
for possible near-term production. Additional opportunities lie in previously identified high-grade silver
intercepts down-dip and potentially increasing the substantive silver mineralization along-strike from the two
past-producing open pits.
The Company has staked 636 lode claims and entered into a Lease/Purchase Agreement to acquire five
patented claims on its Cherokee project located in Lincoln County, Nevada, host to multiple silver-copper-gold
vein systems, traced to date for over 11 km along-strike.
Silver One holds an option to acquire a 100% interest in the Silver Phoenix Project. The Silver Phoenix Project
is a very high-grade native silver prospect that lies within the “Arizona Silver Belt”, immediately adjacent to
the prolific copper producing area of Globe, Arizona.
For more information, please contact:
Silver One Resources Inc.
Gary Lindsey - VP, Investor Relations
Phone: 604-974-5274
Mobile: (720) 273-6224
Email: [email protected]
Hole ID East
UTMWGS84
North
UTMWGS84
Elevation
(m) Bearing Inclination TD (m)
CK21-01 731,854 4,127,495 1,378 45 -60 57.61
CK21-02 731,838 4,127,479 1,378 45 -75 73.46
CK21-03 731,843 4,127,411 1,372 45 -50 103.02
CK21-04 731,881 4,127,453 1,380 45 -50 43.28
CK21-05 731,940 4,127,371 1,385 45 -50 99.36
CK21-06 731,797 4,127,510 1,370 45 -50 76.48
CK21-07 731,797 4,127,510 1,370 45 -85 154.53
CK21-08 731,750 4,127,519 1,365 45 -50 83.82
CK21-09 732,714 4,126,749 1,426 40 -50 105.77
Forward-Looking Statements
Information set forth in this news release contains forward-looking statements that are based on assumptions as of the
date of this news release. These statements reflect management's current estimates, beliefs, intentions and expectations.
They are not guarantees of future performance. Silver One cautions that all forward-looking statements are inherently
uncertain, and that actual performance may be affected by a number of material factors, many of which are beyond Silver
One's control. Such factors include, among other things: risks and uncertainties relating to Silver One's limited operating
history, ability to obtain sufficient financing to carry out its exploration and development objectives on the Candelaria
Project, obtaining the necessary permits to carry out its activities and the need to comply with environmental and
governmental regulations. Accordingly, actual and future events, conditions and results may differ materially from the
estimates, beliefs, intentions and expectations expressed or implied in the forward-looking information. Except as
required under applicable securities legislation, Silver One undertakes no obligation to publicly update or revise forward-
looking information.
NEITHER TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER (AS THAT TERM IS DEFINED
IN THE POLICIES OF THE TSX VENTURE EXCHANGE) ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR
ACCURACY OF THIS RELEASE.