STLLR Gold Provides its 2025 and Long-Term Plans and Introduces the Hollinger Tailings Project
Page 1 of 5
STLLR Gold Provides its 2025 and Long-Term Plans and
Introduces the Hollinger Tailings Project
TORONTO, ONTARIO, February 3, 2025 – STLLR Gold Inc. (TSX: STLR) (OTCQX: STLRF) (FSE: O9D)
(“STLLR” or the “Company ”) outlines its 2025 plans and long -term outlook for the Tower Gold
Project (“Tower”) in Timmins, Ontario, and the Colomac Gold Project (“ Colomac”) in the Northwest
Territories (“NWT”), Canada.
The Company is also thrilled to introduce its Hollinger Tailings Project in Timmins, Ontario,
highlighting its debut and outlining plans for 2025. Situated within the city of Timmins and
conveniently close to existing processing facilities, the project stands out as a strategic opportunity.
Recent changes to the Ontario Mining Act1 (“Mining Act”) simplify the permitting process to unlock
the economic potential of reprocessing mine tailings while encouraging environmental remediation
of legacy sites. With low capital requirements and a favourable gold price environment, the Hollinger
Tailings Project presents significant upside potential for STLLR.
Keyvan Salehi, P.Eng., MBA, President, CEO, and Director of STLLR, commented: “We believe 2025
will be a pivotal year for STLLR. With a strong balance sheet supporting our plans, we are focused on
advancing key projects. At Tower, we aim to deliver an updated MRE and PEA . InnovExplo2 will
oversee the completion of the MRE and G Mining Services will oversee the completion of the PEA.
Both reports are progressing in parallel and will be disclosed simultaneously and under one technical
report. Additionally, we will continue exploration in the Timmins area and progress environmental
baseline studies to secure the necessary permits, as we advance Tower to shovel-ready status.”
“We are enthusiastic about the potential of our Hollinger Tailings Project in Timmins. After months
of preparation, we are now set to quantify its value. Recent updates to the Mining Act could position
the project as a near- term cash flow opportunity at current gold prices, while furthering our
environmental commitment to reclaiming this historical site.”
1 Ontario’s new “Mining Act for Recovery of Minerals” regulation to be in effect July 1, 2025. For more details:
https://news.ontario.ca/en/release/1005407/ontario-supporting-recovery-of-residual-metals-and-minerals
2 InnovExplo is a member of Norda Stelo Inc.
TSX: STLR | OTCQX: STLRF | FSE: O9D
STLLRGOLD.COM
Page 2 of 5
“Located near existing processing facilities with available capacity, the project presents a promising
opportunity for additional mill feed within the Timmins camp. In Q1 2025, we plan to conduct a
tailings characterization program. Based on our findings, we will move forward with a mineral
resource estimate and, if justified, a preliminary economic assessment. With minimal capital
requirements, the Hollinger Tailings Project has the potential to be a game changer for STLLR Gold.
Stay tuned for updates as we advance this exciting opportunity!”
“Looking ahead, our long -term vision is to bring our Tower and Colomac projects to shovel-ready
status, with Tower as the priority due to its proximity to existing infrastructure. Our goal is reaching
a shovel-ready stage for Tower within 36 to 48 months.”
2025 Ontario Activities
• Updated Tower Mineral Resource Estimate (“ MRE”) and Preliminary Economic
Assessment (“PEA”) in H1-2025:
STLLR plans to release the Tower MRE and PEA together in H1-2025. The MRE will benefit from
over 120 km of infill drilling and improved geological models . Verification of historical drilling
at Garrison provides added confidence to the MRE data. The PEA will detail an updated mine
plan and economics for Tower, showcasing optimized throughput and production.
• Exploration, Technical and Permitting Activities:
STLLR plans to drill 5,000- 7,000 metres at Tower to enhance mineral resource confidence.
The Company will initiate a metallurgical program as well as other studies that will drive Tower
towards a pre- feasibility study (“ PFS”). Additionally, STLLR will continue environmental
baseline studies necessary for permitting.
• Hollinger Tailings Project:
The Hollinger Tailings Project, located i n the southeast area of the city of Timmins, Ontario
(see Figure 1), is where tailings from the Hollinger Mine were stored. The Hollinger Mine, which
operated from 1910-1968, was at one time the world’s largest gold mine. It produced 19 million
ounces of gold at an average grade of 9.9 grams per tonne .3 An estimated 50-60 million
tonnes of tailings were placed at the Hollinger Tailings Project . STLLR plans to conduct a
10,000-12,000-metre characterization program of the tailings, establishing a path forward
for a potential mineral resource estimate. There is a 1.5% net smelter royalty on the potential
gold content of the Hollinger Tailings Project property.
3 Hollinger Historical Production Statistics, Geology Ontario database:
https://www.geologyontario.mines.gov.on.ca/persistent-linking?mineral-inventory=MDI42A06NW00007
TSX: STLR | OTCQX: STLRF | FSE: O9D
STLLRGOLD.COM
Page 3 of 5
Figure 1: Map of Timmins, Ontario and Location of the Hollinger Tailings Project
TSX: STLR | OTCQX: STLRF | FSE: O9D
STLLRGOLD.COM
Page 4 of 5
2025 NWT Activities
STLLR plans to install solar panels at Colomac , under a lease agreement with the T łı̨chǫ Investment
Corporation4, evaluate high-priority drilling targets, perform reclamation, and assess permitting
activities. These site enhancements will enable more cost- effective, environmentally-conscious
drilling and permitting in the future.
Long-Term Strategy
STLLR management is focused on advancing the Tower and Colomac projects to shovel -ready
status, recognizing their potential to create value for the Company. Given its proximity to existing
infrastructure, Tower will be the near-term priority. The Company estimates the following milestones
for Tower:
• Deliver PFS in 24 months.
• Complete environmental baseline work and submit Federal Environmental Assessment (“EA”)
in 30 months.
• Deliver Feasibility Study (“FS”) in 36-48 months.
Colomac's advancement is contingent on securing additional funding, with priority given to Tower's
expenditures. The Company is continuing to evaluate various funding and strategic opportunities
for Colomac.
John McBride, MSc., P.Geo., VP Exploration of STLLR , is a “Qualified Person” as defined by National
Instrument 43-101, has reviewed and approved of the scientific and technical disclosure contained
in this news release.
About STLLR Gold
STLLR Gold Inc. (TSX: STLR; OTCQX: STLRF; FSE: O9D) is a Canadian gold development company actively
advancing two cornerstone gold projects in Canada: The Tower Gold Project in the Timmins Mining Camp in
Ontario and the Colomac Gold Project located north of Yellowknife, Northwest Territories. Each of these two
projects has the potential for a long- life and large -scale operation and are surrounded by exploration land
with favourable upside potential. STLLR’s experienced management team, with a track record of successfully
advancing projects and operating mines, is working towards rapidly advancing these projects.
Contact Us
STLLR Gold Investor Relations
+1 (416) 863-2105 | [email protected] | www.STLLRgold.com
4 See STLLR May 29, 2024 news release for more details
TSX: STLR | OTCQX: STLRF | FSE: O9D
STLLRGOLD.COM
Page 5 of 5
Cautionary Statement Regarding Forward-Looking Information
This news release contains “forward-looking information” within the meaning of applicable Canadian securities legislation.
Forward-looking information includes, but is not limited to the potential completion and timing of the delivery of the Tower
PEA and MRE, the timing of the potential advancement of Tower towards PFS and DFS within 24-48 months, the completion
of the environmental baseline work and submission of an EA in 30 months, the infill and expansion of the known
mineralization at the Tower Gold Project, the planned drilling metres, the planned characterization program of the Hollinger
Tailings Project, the potential and strategic nature of the Hollinger Tailings Project, the potential contents of the Hollinger
Tailings Project and the ability to advance it towards a mineral resource estimate and preliminary economic assessment,
the capex requirements, the ability to secure permits and toll -milling agreements for the Hollinger Tailings Project, the
ability to advance the Hollinger Tailings Project towards potential cash flow at current gold prices, timing of the release of
the assay results, the completion of the solar farm installation at Colomac, the funding of activities in 2025 and beyond,
the future financial or operating performance of STLLR and STLLR’s mineral properties and project portfolios, the
advancement of the Tower Gold and Colomac Gold Projects towards ‘shovel-ready’ status, long -life and large-scale
potential of the Tower and Colomac Gold Projects and exploration upside of the land packages. Generally, forward-looking
information can be identified by the use of forward -looking terminology such as “accelerate”, “add” or “additional”,
“advancing”, “anticipates” or “does not anticipate”, “appears”, “believes”, “can be”, “conceptual”, “confidence”, “continue”,
“convert” or “conversion”, “deliver”, “demonstrating”, “estimates”, “encouraging”, “expand” or “expanding” or “expansion”,
“expect” or “expectations”, “fast-track”, “forecasts”, “forward”, “goal”, “improves”, “increase”, “intends”, “justification”,
“leading”, “plans”, “potential” or “potentially”, “pro -forma”, “promise”, “prospective”, “prioritize”, “reflects”, “re-rating”,
“robust”, “scheduled”, “stronger”, “suggesting” or “suggests”, “support”, “updating”, “upside”, “will be” or “will consider”,
“work towards”, or variations of such words and phrases or state that certain actions, events or results “may”, “could”,
“would”, “might”, or “will be taken”, “occur”, or “be achieved”.
Forward-looking information is based on the opinions and estimates of management at the date the information is made,
and is based on a number of assumptions and is subject to known and unknown risks, uncertainties and other factors that
may cause the actual results, level of activity, performance or achievements of STLLR to be materially different from those
expressed or implied by such forward-looking information, including risks associated with required regulatory approvals,
the exploration, development and mining such as economic factors as they effect exploration, futu re commodity prices,
changes in foreign exchange and interest rates, actual results of current exploration activities, government regulation,
political or economic developments, the ongoing wars and their effect on supply chains, environmental risks, COVID -19
and other pandemic risks, permitting timelines, capex, operating or technical difficulties in connection with development
activities, employee relations, the speculative nature of gold exploration and development, including the risks of
diminishing quantities of grades of reserves, contests over title to properties, and changes in project parameters as plans
continue to be refined as well as those risk factors discussed in the Company’s Annual Information Form for the year
ended December 31, 2023 , available on www.sedarplus.ca. Although STLLR has attempted to identify important factors
that could cause actual results to differ materially from those contained in forward -looking information, there may be
other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such
information will prove to be accurate, as actual results and future events could differ materially from those anticipated in
such information. Accordingly, readers should not place undue reliance on forward- looking information. STLLR does not
undertake to update any forward-looking information, except in accordance with applicable securities laws.