El Domo - Curipamba Project Achieves Major Permitting Milestone

with Approval of the Tailings Storage Facility

Toronto, January 30 , 2024 – Adventus Mining Corporation (“Adventus”) (TSX-V: ADZN , OTCQX: ADVZF ) and Salazar

Resources Limited (“Salazar”) (TSX-V: SRL, OTCQB: SRLZF) (collectively the “Participants”) are pleased to announce that

the Ministry of Energy and Mines of Ecuador (“MEM”), in conjunction with the Agency of Regulation and Control for Non-

renewable Natural Resources of Ecuador, has issued a permit which grants approval for the design, construction,

operation, and maintenance of the tailings storage facility (“TSF”) for the El Domo - Curipamba copper-gold project located

in central Ecuador (“El Domo”). In conjunction with the recently granted Environmental License (see news release dated:

January 22, 2024), this permit and approval allows the Participants to further advance El Domo towards a construction

decision expected in the first half of 2024. The start of TSF construction is a key condition precedent to draw from the

financing package arranged with Wheaton Precious Metals Corp.

The permit application was submitted in June 2023 in compliance with the requirements established in the MEM

instructive for approval of tailings storage facilities for medium and large-scale mining projects. In addition to the detailed

design and the risk management plan, the 1,300-page permit application contained 12 specific technical studies covering

all aspects of the TSF design, construction, operations and maintenance. The application also includes certification of the

stability analysis by a qualified third-party expert.

In addition to complying with Ecuadorian regulations, the El Domo TSF design meets requirements of the Canadian Dam

Association guidelines . The construction method will be downstream , using rock-fill which is the safest tailings dam

configuration method. This major permitting milestone is a testament to Adventus and Salazar’s continuing commitment

to international best practices and to the highest technical standards of modern responsible mining.

About Adventus

Adventus Mining Corporation is an Ecuador -focused copper-gold exploration and development company. Adventus is advancing the

215 sq. km majority-owned Curipamba copper-gold project, which has a completed feasibility study on the shallow and high- grade El

Domo deposit. With the recent merger with Luminex Resources Corp. , Adventus Mining owns the Condor gold project and a large

exploration project portfolio that spans over 135,000 hectares – one of the largest holdings in Ecuador . The company’s strategic

shareholders include Ross Beaty’s Lumina Group, Altius Minerals Corporation, Wheaton Precious Metals Corp., and significant

Ecuadorian investors. Adventus Mining is based in Toronto, Canada, and is listed on the TSX Venture Exchange under the symbol ADZN

and trades on the OTCQX under the symbol ADVZF.

About Salazar

Salazar Resources Limited is focused on creating value and positive change through discovery, exploration, and development in

Ecuador. The team has an unrivalled understanding of the geology in-country and has played an integral role in the discovery of many

of the major projects in Ecuador, including the two newest operating gold and copper mines. Salazar Resources has a wholly ow ned

Date:

News Release:

Ticker Symbols:

January 30, 2024

24-04

ADZN (TSXV), ADVZF (OTCQX), SRL (TSXV) SRLZF (OTCQB)

– 2 of 2 –

pipeline of copper-gold exploration projects across Ecuador with a strategy to make another commercial discovery and farm-out non-

core assets. The Company actively engages with Ecuadorian communities and together with the Salazar family it co -founded The

Salazar Foundation, an independent non- profit organization dedicated to sustainable progress through economic development. The

Company already has carried interests in three projects. At its maiden discovery, Curipamba, Salazar Resources has a 25% stak e fully

carried through to production. At two copper -gold porphyry projects, Pijili and Santiago, the Company has a 20% stake fully carried

through to a construction decision.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Ven ture Exchange) accepts

responsibility for the adequacy or accuracy of this news release.

This release contains certain “forward looking statements” and certain “forward -looking information” as “defined under applicable Canadian and

U.S. securities laws. Forward -looking statements and information can generally be identified by the use of forwar d-looking terminology such as

“may”, “will”, “should”, “expect”, “intend”, “estimate”, “anticipate”, “believe”, “continue”, “plans” or similar terminology. The forward -looking

information contained herein is provided for the purpose of assisting readers in understanding management’s current expectations and plans relating

to the future. Readers are cautioned that such information may not be appropriate for other purposes.

Forward-looking statements relate to future events or future performance and reflect the Participants expectations or beliefs regarding future events.

Forward-looking statements include, but are not limited to: the discussions regarding strategies for the development of El Domo; the adoption of a

strategy and the timing thereof; the obtaining of key approvals, permits and environmental licensing approval for El Domo and the timing thereof;

and the start of construction at El Domo and the timing thereof. By their very nature, forward-looking statements involve known and unknown risks,

uncertainties and other factors that may cause our actual results, performance or achievements to be materially different fro m any future results,

performance or achievements expressed or implied by the forward- looking statements. Such factors include, amongst others, risks related to the

exploration, development, production, recoveries and other anticipated or possible future developments at El Domo, including, without limitation,

that exploration, development and production activities will not occur or be as anticipated and that parts of environmental licensing will not be

approved; failure to obtain parts of environmental licensing approval for El Domo along with other permits and approvals and to start construction;

and general economic, business and political conditions.

Forward-looking information are based on management of the parties' reasonable assumptions, estimates, expectations, analyses and opi nions,

which are based on such management's experience and perception of trends, current conditions and expected developments, and other factors that

management believes are relevant and reasonable in the circumstances, but which may prove to be incorrect. Such factors, amon g other things,

include: business integration risks; fluctuations in general macroeconomic conditions; f luctuations in securities markets; fluctuations in spot and

forward prices of copper or certain other commodities; change in national and local governments, legislation, taxation, contr ols, regulations and

political or economic developments; risks and haza rds associated with the business of mineral exploration, development and mining (including

environmental hazards, industrial accidents, unusual or unexpected formations pressures, cave-ins and flooding); discrepancies between actual and

estimated metallurgical recoveries; inability to obtain adequate insurance to cover risks and hazards; the presence of laws and regulations that may

impose restrictions on mining; employee relations; relationships with and claims by local communities and indigenous populati ons; availability of

increasing costs associated with mining inputs and labour; the speculative nature of mineral exploration and development (inc luding the risks of

obtaining necessary licenses, permits and approvals from government authorities); and title to properties.

The Participants undertake no obligation to update forward- looking information except as required by applicable law. Such forward- looking

information represents management's best judgment based on the information currently available. No forward-looking statement can be guaranteed

and actual future results may vary materially. Accordingly, readers are advised not to place undue reliance on forward -looking statements or

information.

For further information from Adventus Mining, please contact Christian Kargl- Simard, President and Chief Executive

Officer, at +1 -416-230-3440 or [email protected] . Please also visit the Adventus Mining website at

www.adventusmining.com and follow us on Twitter: https://twitter.com/AdventusMining and LinkedIn:

https://ca.linkedin.com/company/adventus-mining-corporation.

For further information from Salazar Resources, please contact Freddy D. Salazar, Manager – Corporate Development, at

+593 98 548 9355 or [email protected]. Please also visit the Salazar Resources website at

www.salazarresources.com.