Spanish Mountain Gold Reports Results on Environmental Assessment & Project Optimization; Sets Tangible Targets for 2022

Permits & Approvals

1120‐1095 West Pender Street 

Vancouver, British Columbia, V6E 2M6 

Tel: 604.601.3651 

January 25, 2022 

Spanish Mountain Gold Reports Results on Environmental Assessment & Project 

Optimization; Sets Tangible Targets for 2022  

Vancouver,  BC ‐   Spanish  Mountain  Gold  Ltd.  (the  “Company”)  (TSX‐V:  SPA)  is  pleased  to  report 

encouraging  results  based  on  significant  progress  achieved  on  a  number  of  value‐added  initiatives  for 

the Spanish Mountain Gold Project (the "Project") located in British Columbia, Canada.  As announced on 

September  9,  2021,  the  work  programs  underway  build  on  the  successful  completion  of  the  Project’s 

Pre‐feasibility  study  (PFS  filed  in  June  2021)  in  which  a  multi‐million  ounce  Mineral  Reserve  has  been 

delineated along with robust economics and a 14‐year mine plan. 

Environmental Assessment 

The Company continues to execute its stated strategy of fast‐tracking its multi‐million ounce  Resource 

through  the  process  for  environmental  assessment/  permitting.   In  addition  to  ongoing  technical 

analyses  and  comprehensive  field  surveys,  the  Company  has  launched  multiple  initiatives  to  intensify 

ongoing engagements with all three Indigenous Nations whose traditional territories include the project 

area.  Significant progress has been made as follows: 

 Indigenous  Nations  Engagement  —   the  Company  signed  an  Engagement  Protocol  Agreement 

with Xatśūll First Nation in October 2021 and Lhtako Dené Nation in December 2021 formalizing 

the  engagement  process  between  the  Nations  and  the  Company;  and  proceeded  with  the 

process  of  completing  a  Life‐of‐Mine  relationship  agreement  with  Williams  Lake  First  Nation. 

Management has also initiated pre‐submission review of the draft Initial Project Description (see 

details below) with all three First Nations.  Continuous engagement with Indigenous Nations will 

remain an integral part of the Project. 

 Initial Project Description (IPD) —  the draft Initial Project Description for the Project is now in 

pre‐submission  review  with  all  three  First  Nations.   Management  has  adopted  an  engagement 

practice in which the First Nations communities will have opportunities to address their interests 

and concerns throughout  the  EA  process.   The Company expects to submit the IPD to  the  B.C. 

Environmental  Assessment  Office  and  Impact  Assessment  Agency  of  Canada  within  the  first 

quarter of the year and thereby formalize the first stage of both the provincial and the federal EA 

processes.  

 Site‐wide  Water  Balance  —   the  Company  commenced  a  field  program  in  September  2021  to 

study  groundwater  flows  in  the  area  of  the  planned  open  pit  and  Tailings  Storage  Facility.   In 

spite  of  challenging  operating  environment  caused  by  extreme  weather  events  and  the 

pandemic, the field staff successfully completed the targeted drill holes over a wide area where 

monitors  will  be  installed.   The  drilling  crew  was  demobilized  in  December.   The  field  work 

resumed in mid‐January to perform pump test in order to monitor and gather ground water data 

needed for the development of the site‐wide water balance for the Project.   The water balance 

model  is  a  critical  tool  for  formulating  effective  water  management  strategy  and  cost 

optimization. 

The Company has targeted ambitious environmental assessment milestones to be achieved within 2022 

as follows: 

 submission of the Initial Project Description to the provincial and federal agencies 

 submission of Detailed Project Description to the provincial and federal agencies 

 signing of Life‐of‐Mine relationship agreement with all three First Nations 

 launching open houses and consultations with surrounding communities to the extent allowed 

by pandemic restrictions 

 formulating  critical  environmental  strategies  based  on  comprehensive  data  collected  and  the 

Best Practice in Environmental, Social & Governance.     

Project Optimization 

The  Company  has  initiated  a  number  of  optimization  exercises  with  the  objective  of  front‐  identifying 

areas where enhancement of project economics and process improvements are potentially achievable.  

In  due  course,  the  feasibility  study  is  expected  to  capture  the  full  benefit  of  these  exercises  without 

causing delays in its delivery.  

Gold Recovery 

The  Company  has  engaged  Ausenco  as  an  independent  expert  consultant  to  conduct  a  targeted 

metallurgical  program  to  further  optimize  the  milling  process  incorporated  in  the  PFS.   The  current 

flowsheet is characterized by low input costs for reagents and power as well as an average gold recovery 

of 90%.   

The  Company  is  pleased  to  announce  that  preliminary  testing  has  demonstrated  the  viability  of 

incorporating Direct Flotation Reactor technology in the milling process, which has the potential to lead 

to  savings  in  capital  and  operating  costs.   Building  on  the  results  of  the  latest  metallurgical  work,  the 

Company expects to commence Phase 2 of the program later in the year which will include a number of 

trade‐off  studies  and  variability  testing  on  fresh  bulk  samples.   Once  the  program  is  complete,  the 

optimized flowsheet and the detailed processing configuration will be the basis for ore processing and 

the recovery of gold in the definitive feasibility study.   

Water Management & Treatment 

The  Project’s  sustainability  strategy  is  formulated  to  ensure  effective  protection  for  local  surface  and 

ground waters around the project area.   Baseline water quality monitoring is continuing; adding to the 

expansive database for the project area.   

The Company has engaged Linkan Engineering to develop preliminary designs for the passive treatment 

systems concept presented in the PFS and to conduct a study of measures to potentially inhibit sulphide 

oxidation and any associated neutral metal leaching from the non‐acid generating waste rock.   

Site‐wide water balance and water quality models are expected to be completed by the end of the year, 

which  will  allow  the  development  of  comprehensive  water  management  methodology.   The  water 

models are also critical for completing the Project’s environmental assessment process/ permitting.   

Power Line 

As  detailed  in  the  PFS,  the  Project’s  location  is  supported  by  excellent  infrastructure  including  an 

abundance of connectivity to the provincial power grids supplied with low‐cost, renewable hydro power.  

There is also an established right‐of‐way between various substations and the proposed mine site.   

The Company has commissioned a study investigating the routing for a power line to the proposed mine 

that may have the potential combined benefits of utilizing existing route corridors and traversing more 

accommodating terrains over a shorter distance.  If successful, the selected route is expected to result in 

lower permitting risks and construction costs.  

The Company is pleased to report that the technical team has completed the LIDAR survey for reviewing 

the route alternates and has not identified any significant constructability issues for a power line from 

the substation to the proposed mine.  The technical team will continue to work with consultants and BC 

Hydro to refine the parameters for the new power line and address technical and permitting issues.  

Resource Expansion 

While the Company’s current priority is to de‐risk and optimize the Project through the environmental 

assessment/  permitting  phase,  the  technical  team  will  continue  to  advance  the  objective  of  resource 

expansion.   

The  geological  model  for  the  deposit  suggests  that  the  Mineral  Resource  is  open  at  depth  and  along 

strike.  The latest drill program (results of which were announced in July, 2021) has identified four broad 

areas near the proposed pit boundary that could potentially expand the overall Mineral Resource.   

In addition, the geological team conducted a grassroots exploration program last fall testing targets as 

far as two kilometres northwest of the pit boundary.  The results for this program are pending and could 

demonstrate the potential extent of the deposit’s mineralized trend.   Areas with the best prospect for 

adding ounces to the overall Mineral Resource will be prioritized for drilling in due course. 

Acquisition of Placer Claims  

The Company has recently staked and acquired a contiguous block of placer claims covering an area of 

approximately 220 hectares.   These claims overlay the Company’s existing mineral claims and cover an 

area where critical infrastructures for the proposed mine are planned.  

Larry Yau, Chief Executive Officer, commented: “As we have seen multiple cases of disruptions in other 

BC  mining  operations  caused  by  recent  weather  events  and  the  pandemic,  we  are  indebted  to  our 

employees  and  consultants  for  their  diligence  in  keeping  our  work  place  safe  and  our  project  work  on 

track without any noticeable disruptions.  We look forward to delivering on our 2022 project milestones 

to further de‐risk and optimize our multi‐million ounce gold resource.”   

Annual Stock Option Grant 

The  Board  of  Directors  has  authorized  granting  of  incentive  stock  options  to  acquire  an  aggregate  of 

2,450,000 common shares of the Company to employees, consultants and directors.  The options, which 

will be vested in accordance with the Company’s Incentive Stock Option Plan, have an exercise price of 

$0.21 per share expiring January 24, 2027.  The foregoing is subject to regulatory acceptance. 

About Spanish Mountain Gold 

Spanish Mountain Gold Ltd. is focused on advancing its 100%‐owned Spanish Mountain gold project in 

southern  central  British  Columbia.   The  Company  is  simultaneously  pursuing  the  dual  objectives  of 

delivering critical project milestones for the multi‐million ounce Mineral Reserve and further expanding 

the overall Mineral Resource.  The Pre‐Feasibility Study (2021) demonstrates the Project’s potential to be 

a mining operation with a robust production profile (>150,000 oz per year) and profitability (AISC $801 

per  oz)  over  a  mine  life  of  14  years.    Details  on  the  Project  and  the  Company  are  available  on 

www.sedar.com and on the Company’s website: www.spanishmountaingold.com 

On Behalf of the Board, 

SPANISH MOUNTAIN GOLD LTD. 

Larry Yau 

Chief Executive Officer 

Inquiries:  

Spanish Mountain Gold Ltd. 

Phone: (604) 601‐3651 

E‐mail: [email protected]  

Website: www.spanishmountaingold.com 

FORWARD  LOOKING  STATEMENTS:  Certain  of  the  statements  and  information  in  this  press  release  constitute  "forward ‐looking  

statements"   or   "forward ‐looking   information"   Any   statements   or   information   that   express   or   involve   discussions   with   respect  

to   predictions,   expectations,   beliefs,   plans,   projections,   objectives,   assumptions   or   future   events   or   performance   (often,   but  

not   always,   using   words   or   phrases   such   as   "expects",   "anticipates",   "believes",   "plans",   "estimates",   "intends",   "targets",  

"goals",   "forecasts",   "objectives",   "potential"   or   variations   thereof   or   stating   that   certain   actions,   events   or   results   "may",  

"could",   "would",   "might"   or   "will"   be   taken,   occur   or   be   achieved,   or   the   negative   of   any   of   these   terms   and   similar  

expressions)  are  not  statements  of  historical  fact  and  may  be  forward ‐looking  statements  or  information.  

The  Company's  forward ‐looking  statements  and  information  are  based  on  the  assumptions,  beliefs,  expectations  and  opinions  

of   management   as   of   the   date   of   this   press   release,   and   other   than   as   required   by   applicable   securities   laws,   the   Company  

does   not   assume   any   obligation   to   update   forward ‐looking   statements   and   information   if   circumstances   or   management's  

assumptions,   beliefs,   expectations   or   opinions   should   change,   or   changes   in   any   other   events   affecting   such   statements   or  

information.   For   the   reasons   set   forth   above,   investors   should   not   place   undue   reliance   on   forward ‐looking   statements   and  

information.  