Spanish Mountain Gold Provides Project Update and Announces 2025 Exploration Drill Program

Exploration Programs

1

Spanish Mountain Gold Ltd.

910-1111 Melville Street

Vancouver, British Columbia, V6E 3V6

Tel: 604.601.3651

Spanish Mountain Gold Provides Project Update and Announces 2025

Exploration Drill Program

Vancouver, B.C., January 21, 2025 - Spanish Mountain Gold Ltd. (the " Company" or "Spanish

Mountain Gold") (TSX-V: SPA) (FSE: S3Y) (OTC: SPAZF) is pleased to provide an update on its

Spanish Mountain Gold project (“ SMG Project ”), located in the Cariboo Gold Corridor, British

Columbia, Canada.

The Company’s strategy remains focused on optimizing, derisking and advancing the SMG Project

towards a build decision by 2027. The Company anticipates completing a new Mineral Resource

Estimate (“New MRE”) and Preliminary Economic Analysis (“New PEA”) before the end of the first

half of 2025 (“ H1 2025”). Based on positive conclusions and recommendations of the New PEA,

the Company anticipates beginning a Pre-feasibility Study (“ PFS”) or Feasibility Study (“ FS”) in

2025 and is well positioned to fast-track to a build decision by 2027. In addition to optimizing and

derisking the project, the rework and re-interpretation of historical geological information has led

to the identification of new exploration drill targets that could expand the mineral endowment,

affect the project footprint, and reduce existing pit constrained resource risks. An exploration drill

program (5,590 metres “m”) was completed on September 26, 2024 ( see press release dated

December 18, 2025, “Spanish Mountain Gold Intercepts Continuous Mineralization” ), and the

Company plans to conduct follow-up drilling beginning in the first quarter of 2025 (“Q1 2025”). A

private placement financing to support the 2025 exploration and drill program closed on

November 15th, 2024, and the Company is sufficiently funded to advance its plans with respect to

the SMG Project.

Status of the New MRE

Equity Exploration Consultants Ltd., alongside the Company’s geology team, have completed a

new three-dimensional geological model, incorporating new data from the 2024 exploration drill

program, the relogging of 174,228 m of historical diamond drill core, a structural geology

assessment, and a geochemical analysis of historical data. The New MRE is currently under third-

party review by Apex Geoscience Ltd., for inclusion in the New PEA.

HIGHLIGHTS

• The New PEA remains on track to complete during H1 2025.

• The New MRE will incorporate 5,590 m of diamond drilling from the 2024 exploration

program (the “2024 Drill Program”).

2

• The Whittle Optimization is progressing and will be completed in H1 2025 to assist in

determining the optimal operation , scale, and minimize d carbon footprint over the

proposed mine life.

• Partnered with International Technology Group ANDRITZ (“ANDRITZ”, see press release

dated May 24, 2024), and BCH to assess optimal power scenarios for various comminution

equipment options and circuits ranging from 10,000-50,000 tonnes per day (“ tpd”). A

draft report with recommendations has been received and is under review by the project

team.

• 2025 Exploration Drill Program is expected to commence in Q1 2025 targeting 10,000 m

of diamond drilling utilizing oriented core.

2025 Exploration Drill Program

During Q1 2025 , the Company will commence its 2025 exploration drill program (“ 2025 Drill

Program”), targeting 10,000 m of drilling. The targets identified in the 2025 Drill Program (see

Figure 1 – 2025 Drill Program Targets), will focus on extending mineralization near surface along

strike, and deeper high grade intercepts discovered in the 2024 Drill Program. Drilling also aims

to expand geological knowledge for specific mineralized areas such as the Slipper Zone, the K

Zone, a new third argillite horizon, and the Phoenix Target.

Figure 1 – 2025 Drill Program Targets (Plan View and Long Sections)

3

The Phoenix Target (“Phoenix”) is an area where quartz vein mineralization was previously

identified through drilling. The geological model of Phoenix was further refined following the core

relogging campaigns conducted in 2024, which warranted follow-up. Mineralization at Phoenix is

predominantly associated with quartz veins of varying orientations, including both high and low

angles. Additionally, coarse gold associated with quartz veins has been observed, guiding the

focus of future drilling. Drilling efforts will concentrate around the historic drill hole 11-CCR-023,

which returned an interval of 203.9 meters at 0.4 g/t Au and ended in anomalous Au values.

New PEA

After extensive review of the 2021 mineral resource and reserve estimate and PFS (, the “2021

PFS”), refer to the Spanish Mountain Gold Project - Prefeasibility Study (PFS) and Mineral Resource

Estimate, and associated NI 43-101 Technical Report, effective date May 10, 2023 , available on

the Company’s website or under the Company’s profile on Sedarplus.ca), the Company determined

that certain elements of the SMG Project may benefit from being redesigned. Additionally, during

this review, management identified further data requirements that would assist in evaluating

various redesign options. The collection and modelling of this information is ongoing to better

understand the geochemical and geologic characteristics that impact the project. During this

process, several opportunities were also identified such as the potential for extensions of the

mineralization endowment beneath or near the project area, scale o ptimization, improved

flowsheet options considering coarse ore floatation, reduction of carbon intensity such as the

electrification of the mine and a staged construction/expansion approach that could derisk the

time and cost to first production.

Phase 2 metallurgical testing was completed in the third quarter of 2024, which supports coarse

ore flotation, and therefore a new flowsheet will be incorporated in the New PEA. The results of

the metallurgical testing have supported new solutions for tailing s and water management

systems that could positively affect the project’s production scale, costs, sustainability and

permitting requirements . A high-level review of plans integrating tailings, water and waste

management has been completed by BGC Engineering, and recommendations are currently being

incorporated into the New PEA. The particle and bulk ore sorting amenability test programs have

been completed and an economic trade -off analysis is currently being conducted to determine

the potential viability of ore sorting for an enhanced feed grade and gold production, offsetting

potential mineralization losses due to the ore sorting process . Results of the optimization and

derisking improvement initiatives will be incorporated in the Whittle Optimization on the new

resource model. The Company intends to use the results of the Whittle Optimization to propose

a sustainable , permittable and executable business case for the SMG Project to ultimately

advance towards development.

Summary of the New PEA Anticipated Improvements

In August of 2024, the Company awarded Ausenco as lead consultant for a NI 43 -101 technical

report incorporating the New MRE and New PEA. As discussed above, the New PEA is targeting

several improvements and benefits over the 2021 PFS, with a summary of those targeted benefit

improvements highlighted in the table below.

Factor 2021 PFS 2025 New PEA Target Target Benefit

SCALE • 20 ktpd • Assessing range of

20ktpd – 50ktpd

Larger scale provides

greater efficiency, lower

costs and NPV uplift

4

PIT

SELECTION

• Sub-optimal Pit

Selected

• Larger Optimized Pit

• Lower Strip Ratio

Pit selection optimized

with larger pit and lower

strip ratio; detailed mine

plan options underway

MINING • Diesel • Electrification (mine

fleet and equipment)

Electrification to increase

productivity; lower

carbon intensity &

operating costs

PROCESSING • Conventional Flotation

with Gravity

• Coarse Ore Flotation

with Gravity

Improved gold

production at low capex,

power and operating

costs

WASTE

ROCK

MANAGEMENT

• Moderate Strip Ratio • Lower Strip Ratio

Enhanced sustainability

by using mine waste for

tailings

WATER

MANAGEMENT

• Large Volumes in

Valley

• New location would be

High & Dry

Lower volumes to

minimize treatment, risks

& closure costs; Targeting

innovation towards zero

discharge

GEOTECHNICAL

• Valley less suitable for

TMF (high water

run-off with overly

conservative pit slope

angles)

• Higher Risk

• New Location (TMF

requires less water)

• Improved Pit Slope

Design

• Lower Risk

Lowers safety,

environmental, and

geotechnical risk; avoids

valley bottom

infrastructure

construction

TAILINGS

MANAGEMENT

FACILITY (TMF)

• Conventional Slurry

Containment

• Higher Risk

• Clean Coarse Gangue

rejection from coarse

ore floatation

• Free Draining vs

Filtered Tails

• Lower Risk

Stable landforms utilizing

mine-waste; New

location avoids borrow-

pit costs; Eliminates

starter dyke with

expensive borrow pit

material

NEW

POWER LINE • 30 MW • 60 MW

Increased to enable

electrification and

support a larger scale

CARBON

INTENSITY • High • Lower Leverage clean renewable

power source

PERMIT &

EXECUTION • Higher risk • Lower risk

Use state of the art

commercially available

solutions

RELENTLESS PURSUIT FOR BETTER GOLD

• Lowering Carbon Intensity and Green-House Gas Emissions – Through collaboration with

BC Hydro, there are several opportunities that may potentially reduce capital and

operating costs, carbon intensity and green-house gas emissions.

• Renewable Diesel – The Company utilized alternative non fossil based fuel sources for its

2024 Drill Program and achieved a 72% reduction in emissions or a 63,653 kilogram

decrease of CO2e (see press release dated October 16, 2024 , “Spanish Mountain Gold

5

Provides 2024 Drill Program Update with Initial Results that Confirm Mineralization

Extensions”).

• Upcycled Sample Crates (“Sample Crates”) – The Company completed a small upcycling

project utilizing un-safe trees to create Sample Crates for shipping core samples achieving

a Triple Bottom Line win with a 54% cost savings, environmental and sustainable best

practices, and employing local contractors.

About Spanish Mountain Gold Ltd.

Spanish Mountain Gold Ltd. is focused on advancing its 100% -owned Spanish Mountain Gold Project

towards construction of the next gold mine in the Cariboo Gold Corridor, British Columbia . We are

conducting an integrated Whittle Enterprise Optimization to identify the highest potential value -add

improvements while increasing the understanding of the high-grade geologic controls and associated

drill targets that could upgrade and expand the gold resource. We are striving to be a leader in

community and Indigenous relations by leveraging technology and innovation to build the 'greenest'

gold mine in Canada. The Relentless Pursuit for Better Gold means seeking new ways to achieve

optimal financial outcomes that are safer, minimize environmental impact and create mean ingful

sustainability for communities. Details on the Company are available on www.sedarplus.ca and on the

Company's website: www.spanishmountaingold.com.

On Behalf of the Board,

“Peter Mah”

President, Chief Executive Officer and Director

Spanish Mountain Gold Ltd.

For more information, contact:

Suzette N Ramcharan

(604) 601-3651

[email protected]

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined

in policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of

this release.

FORWARD-LOOKING INFORMATION:

Certain of the statements and information in this press release constitute "forward -looking information".

Any statements or information that express or involve discussions with respect to predictions, expectations,

beliefs, plans, projections, objectives, assumptions or future events or performance (often, but not always,

using words or phrases such as "expect s", "anticipates", "believes", "plans", "estimates", "intends",

"targets", "goals", "forecasts", "objectives", "potential" or variations thereof or stating that certain actions,

events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved, or the negative

of any of these terms and similar expressions) are not statements of historical fact and may be considered

forward-looking information. The Company's forward -looking information is based on the assumptions,

beliefs, expectations and opinions of management as of the date of this press release, and include but are

not limited to information with respect to : the disclosure of a NI 43-101 technical report incorporating the

New MRE and PEA, and the timing and results thereof; the commencement of the 2025 Drill Program, and

the timing and results thereof; and the completion of all additional steps and technical reports among other

requirements needed to make a decision of advancing the project towards development by 2027. Other than

as required by applicable securities laws, the Company does not assume any obligation to update forward -

looking information if circumstances or management's assumptions, beliefs, expectations or opinions should

change, or changes in any other events affecting such statements or information. For the reasons set forth

above, investors should not place undue reliance on forward-looking statements and information.