Drill Results

Spanish Mountain Gold Drills Extensive Mineralization Over 140.67 metres

Grading 0.68 g/t Including 1.07 g/t Over 17.00 metres and 0.95 g/t Over 67.31

metres and Extends the Orca Fault Target Trend 130 m to Southeast Drilling

26.46 metres Grading ...

VANCOUVER, British Columbia--(BUSINESS WIRE)--December 8, 2025--

Spanish Mountain Gold Drills Extensive Mineralization Over 140.67 metres Grading 0.68

g/t Including 1.07 g/t Over 17.00 metres and 0.95 g/t Over 67.31 metres and Extends the

Orca Fault Target Trend 130 m to Southeast Drilling 26.46 metres Grading 0.80 g/t Gold

Spanish Mountain Gold Ltd. (the "Company" or "Spanish Mountain Gold") (TSX-V: SPA)

(FSE: S3Y) (OTCQB: SPAUF) is pleased to provide additional assay results from exploration

drill holes 25-DH-1300, 25-DH-1302, and 25-DH-1304 that were completed as part of its 2025

Fall Diamond Drill program (“2025 Fall Drill Program”) for the Spanish Mountain Gold

(“SMG”) project, which is located in the Cariboo Gold Corridor, British Columbia, Canada.

The company has completed approximately 7,800 m of drilling to date of the 9,000 to 10,000

metres (“m”) of exploration drilling planned under the 2025 Fall Drill Program. Assays and

geochemistry are pending receipt from the laboratory and or reporting from sixteen (16)

additional drill holes completed on the newly defined Orca Fault area, and from three (3)

completed drill holes on the A12 target.

Highlights:

 25-DH-1300 intersected from 53.84 to 194.51 m, 140.67 m of 0.68 g/t gold including

two high-grade intervals of 17.00 m of 1.07 g/t gold and 67.31 m of 0.95 g/t gold with a

subset of 12.78 m of 2.85 g/t gold;

 25-DH-1302 intersected two key intervals:

o from 49.64 to 152.20 m, 102.56 m of 0.55 g/t gold including 47.99 m of 0.81 g/t

gold with a higher-grade subset of 12.63 m of 1.44 g/t gold;

o from 200.64 to 273.75 m, 73.11 m of 0.50 g/t gold including 33.15 m of 0.77 g/t

gold with a higher-grade subset of 16.38 m of 1.23 g/t gold; and

 25-DH-1304 intersected from 62.72 to 89.18 m, 26.46 m of 0.80 g/t gold including 8.03

m of 1.61 g/t gold with a higher-grade subset of 4.28 m of 2.26 g/t gold, noting that the

remainder of the drill hole results are still pending receipt from the laboratory

Key Findings:

 Current exploration drilling assay results continues to intersect significant higher-grade

mineralization over 430 m in strike length in the newly defined Orca Fault target (Figure

1 and 2) and the continuity can now be traced across multiple parallel, adjacent drill

sections.

Peter Mah, Spanish Mountain Gold’s President & CEO commented, “These most recent Orca

Fault area drill results continue to extend new higher grade gold mineralization in the heart of

the Main Deposit. Gold assays received from three new holes reported intersecting large, near

surface gold mineralization above the global average resource grade. Additionally, assays

included multiple near surface high-grade intersections in each hole approaching and exceeding

1 g/t gold. The company is pleased with the consistency and growing number of above 1 g/t gold

assays that further demonstrate the potential for growth through new high-grade gold

mineralization within the Main Deposit. This coupled with ore sorting defines the Company’s

twofold strategy to scale up gold production at its proposed mining operation in the Tier 1

Cariboo Gold Corridor, British Columbia, Canada.”

Main Deposit – Orca Fault area

Drill hole 25-DH-1300 (see Table 1) was designed to not only confirm the new Orca Fault target

but also to start building stronger continuity northeast to southwest across section lines to

increase the overall confidence in the geological interpretation of this important area (Figure 2).

The drill hole intersected higher-grade mineralization approximately 36 m northeast of drill hole

25-DH-1299 (see December 1, 2025 news release) intersecting 140.67 m of 0.68 g/t gold

including two high-grade intervals of 17.00 m of 1.07 g/t gold and 67.31 m of 0.95 g/t gold with

a subset of 12.78 m of 2.85 g/t gold. It should be noted that this intercept aligns closely to the

intersections in 25-DH-1299, which had a first interval near surface from 48.18 to 188.00 m of

0.82 g/t gold over 139.82 m and a second near the base of constraining open pit shell for the

2025 Mineral Resource Estimate (see July 3, 2025 news release) from 284.00 to 329.54 m,

grading 1.67 g/t gold over 45.54 m, including 33.54 m of 2.19 g/t gold. The deeper intercept in

25-DH-1299 highlights the mineral potential at depth that will require additional drilling to

further delineate, but investors should be cautioned it is not guaranteed that additional drilling

will result in conversion of this area into the mineral resource estimate.

Drill hole 25-DH-1302 (Table 2) was designed to examine a critical area along the northwest

trend of the new Orca Fault target at edge of the block model from the last mineral resource

estimate (“MRE”) in the recent Preliminary Economic Assessment (see July 3, 2025 news

release). The drill hole was collared 33 m northeast of 25-DH-1292 (Figure 3) and it intersected

two key intervals of higher-grade mineralization (Figure 1), the first interval from 49.64 to

152.20 m, 102.56 m of 0.55 g/t gold including 47.99 m of 0.81 g/t gold with a higher-grade

subset of 12.63 m of 1.44 g/t gold, and the second from 200.64 to 273.75 m, 73.11 m of 0.50 g/t

gold including 33.15 m of 0.77 g/t gold with a higher-grade subset of 16.38 m of 1.23 g/t gold.

These results compare very favorably with drill hole 25-DH-1292 (see November 3, 2025 news

release) and extend gold mineralization to the northwest, highlighting the opportunity of

systematically exploring these new structural trends both inside and outside of the MRE block

model (Figure 1).

Drill hole 25-DH-1304 (Table 3), like 25-DH-1296 (see November 17, 2025 news release), it

was designed to step into the structural domain between Fault 2 and Fault 3, looking to extend

the high-grade gold mineralization to the southeast, where it is interpreted to be a southeasterly

extension of the new Orca Fault target (Figure 1). This drill hole intersected 26.46 m of 0.80 g/t

gold from 62.72 to 89.18 m, including 8.03 m of 1.61 g/t gold with a higher-grade subset of 4.28

m of 2.26 g/t gold (Figure 1) within the constraining open pit for the MRE (see July 3, 2025

news release). Although gold mineralization has been successfully hit historically in this area, it

has not been through applying a systematic exploration approach using the preferred drilling

orientation of 120-degrees that has proven successful in this work program.

The results from these three new exploration drill holes add significant confidence to the

geological and structural interpretation of the new Orca Fault target area, when incorporating 25-

DH-1281 and 25-DH-1282 (see April 21, 2025 news release), 25-DH-1292 and 25-DH-1293 (see

November 3, 2025 news release), 25-DH-1294 and 25-DH-1296 (see November 17, 2025 news

release), and 25-DH-1297, 25-DH-1298, and 25-DH-1299 (see December 1, 2025 news release).

All these results continue to show that tighter exploration drill spacing at the preferred azimuth

of 120-degrees is unlocking additional mineral potential in the Main deposit. These exploration

drill holes are presented on a drill section (Figure 1 and Figure 2) that shows the alignment of the

higher-grade mineralization to the new Orca Fault target.

Table 1: Assay Results for 25-DH-1300

Drill hole From (m) To (m) Width (m) Gold (g/t) Apparent True Thickness

25-DH-1300 53.84 194.51 140.67 0.68 Note 3)

including 53.84 85.83 31.99 0.70 Note 3)

including 67.00 84.00 17.00 1.07 Note 3)

including 127.20 202.40 75.20 0.86 Note 3)

including 127.20 194.51 67.31 0.95 Note 3)

including 162.00 194.51 32.51 1.37 Note 3)

including 181.73 194.51 12.78 2.85 Note 3)

253.94 257.80 3.86 1.99 Note 3)

Table 2: Assay Results for 25-DH-1302

Drill hole From (m) To (m) Width (m) Gold (g/t) Apparent True Thickness

25-DH-1302 49.64 152.20 102.56 0.55 Note 3)

including 49.64 97.63 47.99 0.81 Note 3)

including 67.45 94.72 27.27 1.15 Note 3)

Including 82.09 94.72 12.63 1.44 Note 3)

200.64 273.75 73.11 0.50 Note 3)

Including 225.75 258.90 33.15 0.77 Note 3)

including 242.52 258.90 16.38 1.23 Note 3)

Table 3: Assay Results for 25-DH-1304

Drill hole From (m) To (m) Width (m) Gold (g/t) Apparent True Thickness

25-DH-1304 39.50 42.70 3.20 1.34 Note 3)

42.00 42.70 0.70 5.44 Note 3)

62.72 89.18 26.46 0.80 Note 3)

including 62.72 81.89 19.17 0.97 Note 3)

including 62.72 70.75 8.03 1.61 Note 3)

including 62.72 67.00 4.28 2.26 Note 3)

Notes for Table 1, 2, and 3:

1)

Reported intersections are calculated using a 0.15 g/t Au cut -off grade.

2)

The complete assay table is available on the Company’s website

3)

True thickness of mineralization is unknown as the project is still at the exploration stage

The integration of assay results from 25-DH-1300, 25-DH-1302, and 25-DH-1304 with other

recently released drill holes, strengthens the continuity for the new Orca Fault target and the

association of higher-grade mineralization over a strike length of 430 m, northwest to southeast

(see Figure 1 and Figure 2) now spanning two parallel, adjacent drill sections.

The current interpretation is that there is strong continuity between these section lines linking

geology, structure and the higher-grade mineralization. The mineralization in these drill holes

occurs in faults and quartz-dominated veins that appear to extend for more than 25 m beyond

each drill hole. Two dominant sets of veins were identified, high-angle and low-angle. The

lower-angle veins (~45 degrees) occur in proximity to the Orca Fault (see November 3, 2025

news releases).

Figure 3 illustrates the locations for three drill hole results outlined in this news release and the

drill holes currently in the assay lab, or in process of being drilled. Drill collar location

coordinates are summarized for the 2025 Fall Drill Program in Table 4 at the end of this news

release.

Abbreviations: metres = m, grams per tonne = g/t, gold = Au, mineral resource estimate = MRE,

Spanish Mountain Gold = SMG

Drill Core Processing, Data Verification and Quality Assurance – Quality Control Program

(QAQC)

Once received from the drill and processed, all drill core samples were sawn in half, labeled, and

bagged. The remaining half of the drill core was securely stored on-site. Numbered security tags

were applied to sample shipments to ensure chain of custody compliance. The Company inserts

quality control (QC) samples at regular intervals, including blanks and reference materials, for

all sample shipments to monitor laboratory performance. Standards and blanks account for a

minimum of 20% of the samples in addition to the laboratory’s internal quality assurance

programs. The QAQC program was overseen by the Company’s Qualified Person, Julian Manco,

P.Geo, Director of Exploration (as described below).

The data verification process involved a multi-step approach to ensure accuracy and integrity.

This included a detailed quality control (QC) analysis of the data, which was performed using

both internal and external platforms, such as the MxDeposit™ software. These QC checks

involved the analysis of certified reference materials (CRMs), blanks, and duplicates to confirm

the reliability of the assay results. In addition, a field inspection of the specific drill intervals

mentioned in this release has been conducted to directly observe the geological features and

verified the nature of the results presented.

Drill core samples were submitted to MSALABS’s analytical facility in Prince George, British

Columbia, for sample preparation and PhotonAssay™ analysis. The MSALABS facilities are

accredited to the International Standards ISO/IEC 17025 and ISO 9001 standard for gold and

multi-element assays, with all analytical methods incorporating quality control materials at

defined frequencies and established data acceptance criteria. MSALABS Inc. is independent of

the Company.

PhotonAssay™

The PhotonAssay™ method utilizes gamma ray analysis for gold detection using the Chrysos

PhotonAssay™ instrument (PA1408X). This non-destructive, fully automated technique offers

high accuracy for analyzing ores and pulps. Sample preparation begins with drying and crushing

up to 1 kg of material to achieve at least 70% passing through a 2-millimetre (mm) sieve. The

sample is then riffle split to obtain a suitable aliquot for 2 testing cycles (MSALABS Method

CPA-Au1).

The PhotonAssay™ instrument bombards 400- to 600-gram samples contained in sealed

containers with gamma rays. These containers remain sealed throughout the process, preserving

the sample for potential further testing. The analysis is performed robotically, with results that

integrate into existing laboratory management systems. Each sample is accompanied by a

reference disc traceable to a Certified Reference Material (CRM). Both the sample and reference

disc undergo gamma ray exposure, with signals detected and analyzed to ensure accurate and

reliable results. The method offers a gold detection range from 0.015 parts per million (ppm -

lower limit) to 10,000 ppm (upper limit). Quality control includes the use of reference materials

and blanks, with all results reviewed by a competent person before reporting.

Spanish Mountain Gold implemented two QAQC methodologies to validate the accuracy of

PhotonAssay™ results, both demonstrating good comparability: 1) comparative analysis of

diverse mineralization styles using Total Au screen metallic methods with both FAS-415

(gravimetric finish) and FAS-211 (AAS finish), and 2) comprehensive testing of both sample

aliquots and rejects using FAS-211 (AAS finish). QAQC Testing typically can include the

following spot checks: 1) Pulverizing tests to evaluate variability in sample preparation, 2)

Cross-analysis at external laboratories using screen metallic method, and 3) Four-cycle radiation

testing to identify and calibrate potential variability in gold results with variable radiation

intensity.

Multi-Elemental Analysis

For the 2025 drilling campaign Spanish Mountain Gold used IMS-230 method to provide multi-

element determination using a four-acid digestion followed by ICP-OES and ICP-MS analysis.

Key Process Steps:

Sample Preparation: Samples are dried and ground to a specific criterion (85% passing 75

microns (μm) for rocks and drill core; 180μm for soils and sediments). A homogeneous 10-gram

sample is required. Digestion: Samples undergo sequential digestion with nitric, perchloric,

hydrofluoric, and hydrochloric acids, followed by dilution with deionized water.

Analysis: The solution is analyzed via ICP-OES and ICP-MS for multi-element quantification.

Quality Control: The process includes reference materials, blanks, and duplicates, with

corrections for spectral interferences and thorough review before final reporting.

Qualified Person

Julian Manco, M.Sc., P.Geo., Director of Exploration with Spanish Mountain Gold, is the

Qualified Person as defined under National Instrument 43-101 who has reviewed the technical

information in this news release and has approved the content for dissemination.

About Spanish Mountain Gold Ltd.

Spanish Mountain Gold Ltd. is focused on advancing its 100%-owned Spanish Mountain Gold

Project (Project) towards construction of the next gold mine in the Cariboo Gold Corridor,

British Columbia. On August 18, 2025, the Company filed an NI 43-101 Technical Report on

SEDAR+ that sets out the Project’s de-risked and optimized Preliminary Economic Assessment

(PEA), with an updated Mineral Resource Estimate (MRE). We will continue to advance the

Project to position the Company to make a construction decision in 2027. We are striving to be a

leader in community and Indigenous relations by leveraging technology and innovation to build

the 'greenest' gold mine in Canada. The Relentless Pursuit for Better Gold means seeking new

ways to achieve optimal financial outcomes that are safer, minimize environmental impact and

create meaningful sustainability for communities. Details on the Company are available on

www.sedarplus.ca and on the Company's website: www.spanishmountaingold.com.

On Behalf of the Board,

“Peter Mah”

President, Chief Executive Officer and Director

Spanish Mountain Gold Ltd.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is

defined in the policies of the TSX Venture Exchange) accepts responsibility for the

adequacy or accuracy of this release.

FORWARD-LOOKING INFORMATION:

Certain of the statements and information in this press release constitute "forward-looking

information". Any statements or information that express or involve discussions with respect to

predictions, expectations, beliefs, plans, projections, objectives, assumptions or future events or

performance (often, but not always, using words or phrases such as "expects", "anticipates",

"believes", "plans", "estimates", "intends", "targets", "goals", "forecasts", "objectives",

"potential" or variations thereof or stating that certain actions, events or results "may", "could",

"would", "might" or "will" be taken, occur or be achieved, or the negative of any of these terms

and similar expressions) are not statements of historical fact and may be considered forward-

looking information. The Company's forward-looking information is based on the assumptions,

beliefs, expectations and opinions of management as of the date of this press release and include

but are not limited to information with respect to, the potential for adding more higher-grade

gold mineralization within the pit or below current pit design; and the timing and size (m) of the

2025 Fall Drill Program, and the results thereof. Other than as required by applicable securities

laws, the Company does not assume any obligation to update forward-looking information if

circumstances or management's assumptions, beliefs, expectations or opinions should change, or

changes in any other events affecting such statements or information. For the reasons set forth

above, investors should not place undue reliance on forward-looking information.

Table 4: Drill Collar Information for Drill Holes

Hole ID EAST NORTH ELEV AZIMUTH DIP DEPTH COMMENT

25-DH-1325 604385 5827966 1103 120 -60 N/A In Progress

25-DH-1324 604343 5828053 1080 120 -60 N/A In Progress

25-DH-1323 604286 5828046 1097 120 -60 338 Successfully completed per design

25-DH-1322 604279 5827995 1106 120 -60 231 Successfully completed per design

25-DH-1321 604350 5828016 1099 120 -60 348 Successfully completed per design

25-DH-1320 604561 5827809 1126 120 -60 57 Ended early due to major fault zone

25-DH-1319 604404 5827992 1095 120 -70 198 Successfully completed per design

25-DH-1318 604445 5828098 1055 120 -60 243 Successfully completed per design

25-DH-1317 604186 5828166 1076 120 -60 282 Successfully completed per design

25-DH-1316 604514 5828073 1050 120 -60 177 Successfully completed per design

25-DH-1315 604231 5828163 1075 120 -60 282 Successfully completed per design

25-DH-1314 604160 5828218 1056 120 -70 270 Successfully completed per design

25-DH-1313 604566 5827908 1100 120 -60 204 Successfully completed per design

25-DH-1312 604538 5827921 1095 120 -60 205 Successfully completed per design

25-DH-1311 604590 5827935 1084 120 -60 330 Successfully completed per design

25-DH-1310 604592 5827961 1091 120 -60 211 Successfully completed per design

25-DH-1309 604592 5827958 1071 120 -60 237 Successfully completed per design

25-DH-1308 603280 5829250 966 120 -60 150 Successfully completed per design

25-DH-1307 604565 5827974 1068 120 -60 200 Successfully completed per design

25-DH-1306 603451 5829400 927 120 -60 123 Successfully completed per design

25-DH-1305 603657 5829226 919 120 -60 126 Successfully completed per design

25-DH-1304 604536 5827986 1067 120 -60 225 Successfully completed per design

25-DH-1303 603960 5828754 943 100 -55 156 Successfully completed per design

25-DH-1302 604194 5828180 1066 120 -63 282 Successfully completed per design

25-DH-1301 603708 5829029 929 150 -55 188 Successfully completed per design

25-DH-1300 604388 5828063 1085 120 -60 274 Successfully completed per design

25-DH-1299 604369 5828043 1093 120 -60 336 Successfully completed per design

25-DH-1298 604402 5828088 1074 120 -59 334 Successfully completed per design

25-DH-1297 604354 5828069 1084 120 -59 342 Successfully completed per design

25-DH-1296 604484 5828054 1061 120 -50 180 Successfully completed per design

25-DH-1295 604484 5828054 1061 120 -60 33 Ended early due to drill trace spacing

25-DH-1294 604345 5828120 1075 120 -58 351 Successfully completed per design

25-DH-1293 604284 5828149 1076 120 -60 453 Successfully completed per design

25-DH-1292 604223 5828189 1068 120 -62 270 Successfully completed per design

Contacts

For more information, contact:

Peter Mah

(604) 601-3651

[email protected]