Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

SPA.V ·

Spanish Mountain Gold Announces Results of New PEA for the First Zone

Economic Studies

1120-1095 West Pender Street

Vancouver, British Columbia, V6E 2M6

Tel: 604.601.3651

April 10, 2017

Spanish Mountain Gold Announces Results of New PEA

for the First Zone

VANCOUVER, B.C. Spanish Mountain Gold Ltd. (the “Company”) (TSX-V:SPA) is

pleased to announce the results of the Preliminary Economic Assessment (the “PEA”) for

the pit-delineated high grade core (the " First Zone ") of the 100% owned Spanish

Mountain gold project (the “Project”) located near Likely in central British Columbia,

Canada. The PEA, the commencement of which was announced in a news release dated

February 14, 2017, has been prepared in accordance with NI 43- 101 Standards of

Disclosure for Mineral Projects.

As disclosed in the previous news release , the PEA is based on a 20,000 tonnes per day

(tpd) processing rate with a streamlined flowsheet to process the Measured and Indicated

Resources within the First Zone. Please refer t o Section 1 below for details of the

proposed operation.

Highlights of the PEA are as follows:

• At the proposed 20,000 tpd throughput, the First Zone has a project life of 24

years and a total life of mine (LOM) production of approximately 2.2 million

ounces of gold and 1.5 million ounces of silver.

• The initial capital expenditure is expected to be C$507M (or US$380M) including

a contingency of C$51M . The sustaining capital over the life of the mine is

estimated at C$194M

• At an assumed LOM gold price of US$1,250 per ounce (the base case), the First

Zone generates a pre -tax NPV (@5%) of C$ 597M and a post -tax NPV of

C$482M. Pre -tax and post -tax Internal Rates of Return are 21% and 19%,

respectively. Payback of capital is expected to be less than four years.

• Selected operational and cost metrics for Years 1 - 5; Years 1 - 10 and LOM are

as follows:

Units Years 1 - 5

Avg.

Years 1 - 10

Avg.

LOM

Gold grade g/t 0.77 0.69 0.43

Strip Ratio 0.96 1.55 1.44

Annual Gold Production koz 157 142 92

Cash Cost/ oz US$ 469 555 595

All-in-sustainable Cash Cost US$ 533 619 659

Total Cost/ oz US$ 667 752 792

Larry Yau, CEO, commented: “ Once again our team's diligence has delivered impressive

results for our shareholders. I believe that this PEA has convincingly validated our two- zone

project approach for advancing our multi -million ounce resource: the First Zone alone gener ates

robust investment returns and an operation lasting 24 years whereas the Second Zone , comprised

of additional multi-million ounces of gold within the current geologic resource estimate, largely

as Inferred Resources, potentially adds development flexibility and leverage on the future gold

price.

“While there have been numerous improvements since the 2012 PEA, a few key comparisons

highlight the excellent progress our team has made in demonstrating the robust economics of our

project as follows:

• Compared with the previously (2012) estimated NPV ( @5%) for the entire resource, the

PEA has achieved an NPV for the First Zone alone that is up to 63% higher even at a

gold price that is US$210 lower than assumed for the 2012 PEA

• Post-tax IRR has increased from 12% to 19%

• Initial capital has decreased by up to C$257M (or 33%) from C$764M to C$507M

• LOM All-in-sustainable Cash Cost per ounce has decreased from US$834 to US$659

• Project life for the First Zone extends 24 years vs. 13 years for the entire resource in the

2012 PEA

The noted improvements to project economics are the result of focusing the study on a lower

throughput, smaller footprint and smaller impact Project.

We believe the current PEA provides a reasonable basis for the Company to advance the Project

in the present gold price environment.”

Please refer to the Company’s redesigned website for additional details on the new PEA

and the project: www.spanishmountaingold.com

Section 1: Proposed Operations

The mine plan adopted for the PEA includes 178 Mt of mill feed and 257 Mt of waste over the 24

year project life. The mill feed is comprised entirely of Measured and Indicated Resources.

Approximately 21 Mt of Inferred material within the pit has been treated as waste for this study.

A PEA level mine operation design, approximately 14- year LOM production schedule, and cost

model have been developed for the open pit. The in-pit resource is summarized in the following

table:

Pit Delineated Resources

Measured & Indicated Resource Unit Amount

Measured and Indicated Pit Delineated Resource kt 177,968

Gold Grade g/t 0.44

Measured and Indicated Gold koz. 2,480

Silver Grade g/t 0.67

Measured and Indicated Silver koz. 3,837

Pit Delineated Waste kt 257,102

Strip Ratio t/t 1.4

Inferred Resource Unit Amount

Inferred Pit Delineated Resource (included in Waste)

kt 21,226

Gold Grade g/t 0.30

Silver Grade g/t 0.67

Notes: Cutoff gold grade of 0.15g/t calculated, and utilized in pit delineated resources.

Whole block diluted grades, with an additional 1% of block to block dilution at 0g/t gold, and 99% mining

recovery, included in pit delineated resources

To maintain the assumed mill feed grades during the initial 11 years of production, a mill -feed

cut-off grade of 0.3 to 0.4 g/t Au is utilized with material between the mining cut -off grade and

mill feed cut-off grade being stockpiled for treatment during years 12 through 24.

Processing of the mill feed is by means of a conventional process flowsheet including primary

grinding, flotation, regrinding of the concentrate , and cyanidation via a CIL circuit to produce

doré. The process achieves an average overall LOM gold recovery of 89% with a recovery of

90% being achieved during the initial higher grade years. A silver recovery of 40% is assumed

for the life of the project. Tailings from the plant are stored in a tailings management facility that

has been designed to minimize water above the dam. The balance of the site water is managed

through a separate water management pond that includes a water treatment plant for any water to

be discharged.

Section 2: Capital Expenditures

The following table summarizes the estimated capital costs:

Direct Costs Initial Capital

Cost (C$ Million)

Overall Site 16.6

Open Pit Mining 97.3

Processing Plant (including Ore Handling)

140.0

Tailing Management Facility & Water

56.8

Environmental 12.0

On-Site Infrastructure 28.6

Off-Site Infrastructure 14.3

Sub-Total 365.6

Indirect Costs

Project Indirects 84.6

Owner’s Costs 5.8

Contingencies 51.1

Sub-Total 141.5

Total Initial Capital Cost 507.1

LOM sustaining capital requirements are estimated at C$ 193.5 million.

Section 3: Operating Costs

Area Unit Cost

(C$)

Mining ($/t mined) $1.96

Mining ($/t milled) $4.79

Processing ($/t milled) $4.01

Tailings ($/t milled) $0.05

G&A ($/t milled) $1.09

Total ($/t milled) $9.94

Section 4: First Zone’s Economics

The following pre-tax financial parameters were calculated:

• 21% IRR

• 3.7-year payback on C$507 million capital

• C$597 million NPV at 5% discount value.

The following post-tax financial parameters were calculated:

• 19% IRR

• 3.7-year payback on C$507 million capital

• C$482 million NPV at a 5% discount rate.

The following parameters are used for the financial analysis throughout the life of mine:

• Gold price of US$1,250/oz.

• Silver price of US$18/oz.

• Exchange rate of US$0.75 to C$1.00.

• 99.8% payable gold and 90% payable silver.

• US$1.00/oz. gold refining charges and US$0.60/oz. silver refining charges.

• US$1.00/oz. transport charges on produced gold and silver.

• 0.15% insurance on value of produced gold and silver.

• 1.5% NSR royalty.

Section 5: Sensitivity to Gold Price

Section 6: The Second Zone

While the development of the balance of the geologic resource referred to as the "Second Zone"

has not been incorporated into the PEA, it has the potential to benefit significantly from the

infrastructure, equipment and labour put in place as a result of the development of the First Zone.

The Second Zone comprises multi -million ounces of gold contained within the current geologic

resource estimate, primarily as Inferred Resources, and surrounds the pit that has been delineated

for the current study. The C ompany believes that the Second Zone, while not included in the

PEA, could deliver additional value over time by expanding or extending the Project's overall

production profile. There is no assurance that all or any part of an Inferred Resource will ever be

upgraded to a higher category.

(Base Case)

0%

5%

10%

15%

20%

25%

30%

0

100

200

300

400

500

600

700

$1,100 $1,150 $1,200 $1,250 $1,300 $1,350 $1,400

Post Tax IRR

Post Tax NPV (C$ millions)

Gold Price (US$/oz)

Post Tax NPV (5%) Post Tax IRR

Section 7: Comparisons to 2012 PEA

2012 PEA-

100%

Resource

First Zone

(Standalone

Operations) Change

Assumed LOM Gold Price per ounce US$ $1,462 $1,250 - $212

Post-tax NPV@5% C$million $295 $482 + $187

Post-tax Internal Rate of Return (IRR) 12% 19% + 7%

Payback Period Years 4.4 3.7 - 0.65

LOM Cumulative Free Cashflow including

Initial Capex (undiscounted) C$million $704 $963 + $259

Initial Capital C$million $764 $507 - $257

LOM Production koz 2,799 2,210 - 589

Mine Life Years 14 24 + 10

LOM Strip Ratio 2.3 1.4 - 0.86

LOM Cash Cost per Ounce US$ $774 $595 - $179

LOM AISC per Ounce US$ $834 $659 - $175

Section 8: Resource Estimates

The following tables summarize the total resource estimate, inclusive of the First Zone and

Second Zone resources, used as the basis for the current PEA.

Table 1: Spanish Mountain Gold October 2016 Measured Resource

Au Cut-off

(g/t)

Tonnes > Cut-off

(tonnes)

Grade > Cut-off Contained Metal

Au (g/t) Ag (g/t) Oz. Gold Oz. Silver

0.15 45,730,000 0.53 0.66 770,000 970,000

0.20 38,470,000 0.59 0.66 730,000 810,000

0.25 32,530,000 0.66 0.65 690,000 680,000

0.30 27,840,000 0.72 0.64 650,000 570,000

0.40 20,750,000 0.85 0.64 570,000 430,000

0.50 15,740,000 0.98 0.65 500,000 330,000

Table 2: Spanish Mountain Gold October 2016 Indicated Resource

Au Cut-off

(g/t)

Tonnes > Cut-off

(tonnes)

Grade > Cut-off Contained Metal

Au (g/t) Ag (g/t) Oz. Gold Oz. Silver

0.15 260,800,000 0.37 0.67 3,110,000 5,650,000

0.20 200,370,000 0.43 0.69 2,780,000 4,450,000

0.25 154,710,000 0.49 0.70 2,450,000 3,470,000

0.30 121,410,000 0.55 0.70 2,160,000 2,730,000

0.40 75,280,000 0.68 0.70 1,650,000 1,700,000

0.50 49,310,000 0.80 0.71 1,270,000 1,120,000

Table 3: Spanish Mountain Gold October 2016 Measured plus Indicated Resource

Au Cut-off

(g/t)

Tonnes > Cut-off

(tonnes)

Grade > Cut-off Contained Metal

Au (g/t) Ag (g/t) Oz. Gold Oz. Silver

0.15 306,530,000 0.39 0.64 3,880,000 6,280,000

0.20 238,840,000 0.46 0.66 3,510,000 5,030,000

0.25 187,240,000 0.52 0.67 3,140,000 4,020,000

0.30 149,260,000 0.59 0.68 2,810,000 3,240,000

0.40 96,030,000 0.72 0.69 2,210,000 2,130,000

0.50 65,040,000 0.85 0.69 1,770,000 1,450,000

Notes: Tonnages and Contained metals may not exactly equal individual tables due to rounding.

Whole block diluted grades shown, with no other dilution or recovery factors applied.

Table 4: Spanish Mountain Gold October 2016 Inferred Resource

Au Cut-off

(g/t)

Tonnes > Cut-off

(tonnes)

Grade > Cut-off Contained Metal

Au (g/t) Ag (g/t) Oz. Gold Oz. Silver

0.15 450,640,000 0.28 0.61 4,110,000 8,900,000

0.20 307,410,000 0.34 0.63 3,320,000 6,250,000

0.25 203,740,000 0.39 0.65 2,580,000 4,240,000

0.30 136,250,000 0.45 0.66 1,980,000 2,900,000

0.40 61,590,000 0.59 0.69 1,160,000 1,360,000

0.50 32,180,000 0.72 0.69 740,000 710,000

Notes: Tonnages and Contained metals may not exactly equal individual tables due to rounding.

Whole block diluted grades shown, with no other dilution or recovery factors applied.

This Mineral Resource Estimate was prepared by Gary Giroux, P. Eng. in accordance with NI 43-101 with an

effective date of October 3, 2016.