February 20, 2019 

Spanish Mountain Gold Announces Results from Archaeological Impact 

Assessment: No Concerns Identified in Entire Proposed Project Area 

Vancouver,  BC ‐   Spanish  Mountain  Gold  Ltd.  (the  “Company”)  (TSX‐V:  SPA)  is  pleased  to 

announce the findings and   conclusions of the Archaeological Impact Assessment conducted on 

the entire project area for its Spanish Mountain gold project (the “Project”)   located in British 

Columbia, Canada.   The results are based on a comprehensive field program performed during 

the summer of 2018 by independent archaeological experts in extensive collaboration with field 

technicians  and  heritage  specialists  representing  all  three  First  Nations  communities  whose 

traditional territories encompass the project area.   

The Company is appreciative of the participation by the Williams Lake Indian Band, Xatśūll First 

Nation and Lhtako Dené Nation and has shared the AIA findings and reports with each band.  All 

three bands have accepted the reports without raising any issues or concerns.  The final reports 

have now been filed with the BC Archaeological Branch of the Ministry of Forests, Lands, Natural 

Resource Operations and Rural Development. 

Results 

The comprehensive survey found that the investigated area has sustained previous disturbance 

through  extensive  forestry‐related  and  placer  mining  activities.   Specifically,  no  further 

archaeological  work  is  recommended  prior  to  any  project  activities  within  the  entire  project 

area  where  future  mining  infrastructure  has  been  proposed  under  the  2017  Preliminary 

Economic Assessment.   

If the project footprint changes or expands to include unassessed areas, additional AIA work will 

be  required.   While  it  is  not  currently  anticipated,  any  ground‐disturbing  operations  within 

previously or newly identified archaeological sites must be conducted under the authority of a 

Site Alteration Permit under Heritage Conservation Act Section 12.  

AIA Methodology 

Prior  to  the  commencement  of  field  work,  a  desk‐top  review  was  conducted  for  the  entire 

assessed areas in order to determine the archaeological potential and guide the subsequent in‐

field assessment.   The review utilized topographical data, aerial images, regional archaeological 

potential models as well as the Archaeological Branch’s Remote Access to Archaeological Data 

(RAAD) application, which identifies previously recorded archaeological sites within or near the 

assessed areas. 

Field surveys were conducted during summer months of 2018 by crews of five to six members.  

Vehicle  surveys  were  performed  along  existing  access  roads  in  locations  predicted  by  the 

regional model to have low archaeological potential and the findings of which were also used to 

guide the pedestrian survey program. 

Under the pedestrian survey program, crew members were spaced at approximately 10 metre 

intervals  along  pedestrian  survey  transects,  all  ground  exposures  encountered  were  inspected 

for archaeological materials, and all trees (all species standing or fallen, including stumps) along 

survey  transects  were  examined  for  indications  of  cultural  modification.   The  survey  was 

intensified  in  areas  that  are  considered  to  have  higher  archaeological  potential  based  on 

topographic  and  hydrological  terrain  features  observed  in  the  field.   Subsurface  tests  were 

performed in areas of field‐assessed as having moderate to high archaeological potential.   The 

interval of testing in such areas varied between 3 m to 5 m.  Each sample covered an area of at 

least  0.35  m  by  0.35  m  and  was  shovel‐excavated  until  sterile  matrix  was  encountered.  

Excavated  materials  were  screened  through  6  mm  mesh  for  any  items  of  potential 

archaeological significance.   In total, 826 shovel tests were completed throughout the assessed 

areas. 

CEO Comments 

Larry Yau, CEO, states: “This marks the conclusion of another successful program during 2018, 

which delivered tangible benefits for our Project.  Given the fact that the field work in proposed 

areas cannot and should not start without first completing this time‐intensive program, we have 

preempted the potential for delays in future seasonal‐ and weather‐dependent field work and 

project activities.  Just as important, our continuing collaborations and dialogues with members 

of  our  First  Nations  communities  can  help  us  understand  their  concerns  so  that  we  can 

effectively address them. 

“We  have  now  achieved  a  significant  milestone  in  the  overall  permitting  process  and  have 

thereby further de‐risked our project.  We are satisfied that the proposed project footprint does 

not  appear  to  impact  areas  that  may  be  of  archaeological  significance  to  our  First  Nations 

communities.   Spanish Mountain has always been and will remain committed to advancing our 

project in an environmentally responsible and culturally respectful manner.”   

About Spanish Mountain Gold 

Spanish Mountain Gold Ltd is focused on advancing its flagship Spanish Mountain gold project in 

southern central British Columbia.   The Company has adopted a two‐zone project approach in 

which the pit‐delineated high grade core (the First Zone) of the multi‐million ounce resource is 

expected to sustain a robust stand‐alone operation exceeding 24 years.  The positive economics 

of the First Zone have been demonstrated in a Preliminary Economic Assessment completed in 

2017.   Additionally,  the  resource  ounces  not  included  in  the  PEA  (the  Second  Zone)  present 

future opportunities for the project.   Additional information about the Company is available on 

its website: www.spanishmountaingold.com. 

On Behalf of the Board, 

SPANISH MOUNTAIN GOLD LTD. 

Larry Yau 

Chief Executive Officer 

Inquiries:  

Spanish Mountain Gold Ltd. 

Phone: (604) 601‐3651 

E‐mail: [email protected]  

Website: www.spanishmountaingold.com 

Neither  TSX  Venture  Exchange  nor  its  Regulations  Services  Provider  (as  that  term  is  defined  in  policies  of  the  TSX 

Venture Exchange) accepts responsibility for the adequacy or accuracy of this release. 

This news release contains forward‐looking information, which involves known and unknown risks, uncertainties and 

other factors that may cause actual events to differ materially from current expectation. Important factors that could 

cause actual results to differ materially from the Company's expectations are disclosed in the Company's documents 

filed  from  time  to  time  on  SEDAR.   Readers  are  cautioned  not  to  place  undue  reliance  on  these  forward‐looking 

statements, which speak only as of the date of this press release.  The company disclaims any intention or obligation, 

except to the extent required by law, to update or revise any forward‐looking statements, whether as a result of new 

information, future events or otherwise.