Tango Q2 Operational Update
1
Tango Mining Limited
202 – 5626 Larch Street
Vancouver, British Columbia
V6M 4E1, Canada
TSX Venture: TGV
www.tangomining.com
TANGO Q2 OPERATIONAL UPDATE
VANCOUVER, BRITISH COLUMBIA — 11 March 2019 – Tango Mining Limited (“Tango” or the “Company”)
(TSX.V:TGV) is pleased to provide an update for the period of 1 December 2018 to 28 February 2019 (2nd
Quarter) on its project portfolio located in South Africa, Angola and Liberia.
COAL – Metallurgical and Mining Projects, Republic of South Africa
Production
Three months run of mine (ROM) and discard throughput for the three Exxaro Coal Central Proprietary Limited
(ECC) operations were in line with budget:
Actual
(tonnes)
Budget
(tonnes)
Variance
(tonnes) Comments
Dorstfontein East Coal Mine (DECM) 610 502 574 972 35 530
Dorstfontein West Coal Mine (DWCM) 217 151 226 991 (9 840) Coal supply from underground
Forzando Coal Mine (FZN) 793 632 866 549 (72 917) Coal supply from underground
Employees: Number of full time employees: 231
Number of part time employees: 23
Health and Safety
No reportable incidents recorded for the three ECC operations for the 2nd Quarter.
Safety Awards
DCME – 42 months loss time incident free.
FZN – 36 months loss time incident free
DIAMOND PRODUCTION
OENA, Republic of South Africa
Mining and Processing Contractor – Bluedust 7
During the most recent production period, December 2018 – February 2019, a total of 297.94 carats (111
diamonds) were produced. A total of 104 stones totalling 284 carats were placed on tender in Kimberley or sold
to the state trader. The average price of sold carats was US$3,170 per carat. This includes a 26.41 carat diamond
which sold at US$12,681 per carat.
A total of 95,490 t of both ROM materials were processed during the most recent production period with average
grade of 0.31 carats per ton.
Bluedust 7 is operating five pan plants using 13 pieces of earth moving equipment (EME) and 42 employees.
2
African Star Minerals (ASM)
During the course of the 2nd Quarter, Tango completed the transportation and installation of all outstanding
equipment and infrastructure onsite. Bulk sampling began in February. Hiring and training is scheduled for March.
Full scale processing of pan tailings and bantam material is targeted to commence in April.
ASM is operating two pan plants with 2 EME and 8 employees.
MOQUITA PROJECT, Republic of Angola
Endiama gave the green light to restart operations at Moquita in February. Tango has been active since in
assisting Cooperativa Mineira Do Moquita, SCRL with mine set up and plant rehabilitation as well as securing EME
and finalizing the mine plan. Start of bulk sampling operations is targeted for April 2019.
DIAMOND EXPLORATION
MIDDLEPITS PROJECT, Republic of Botswana
After further internal analysis, Tango has decided against progressing with the Middlepits Project. The MoU
announced 21 December 2017 has been terminated. The Company will focus its efforts on brown field projects
with a shorter time to development and production.
MANO RIVER PROJECT, Republic of Liberia
Tango has established a local company in Liberia, Tango Mining (Liberia), and is in the process of transferring
100% of the mineral exploration license (MEL) to this company. The agreement with West Mining Ltd (see news
release dated 10 September 2018) has been amended as such that West Mining Ltd. will own a 10% carried
interest of Tango Mining (Liberia) with Tango Mining Ltd owning 90%. Tango Mining will also pay a royalty of 1.5%
to West Mining Ltd. on all future production from the MEL.
Mr. Samer Khalaf
Chief Executive Officer
Tango Mining Limited
Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX
Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.
Forward‐Looking Statement
Certain information set forth in this news release contains “forward‐looking statements” and “forward‐looking
information” under applicable securities laws. Except for statements of historical fact, certain information contained herein
constitutes forward‐looking statements, which include management’s assessment of future plans and operations and are
based on current internal expectations, estimates, projections, assumptions and beliefs, which may prove to be incorrect.
Some of the forward‐looking statements may be identified by words such as “forecasts”, estimates”, “expects”
“anticipates”, “believes”, “projects”, “plans”, “outlook”, “capacity” and similar expressions. These statements are not
guarantees of future performance and undue reliance should not be placed on them.
Such forward‐looking statements necessarily involve known and unknown risks and uncertainties, which may cause the
Company’s actual performance and financial results in future periods to differ materially from any projections of future
performance or results expressed or implied by such forward‐looking statements. These risks and uncertainties include, but
are not limited to statements with respect to the estimation of mineral resources; the realization of mineral resource
estimates; anticipated future production, capital and operating costs; cash flows and mine life; potential size of a
mineralized zone; potential expansion of mineralization; potential types of mining operations; permitting timelines;
government regulation of exploration and mining operations; risks that the presence of diamond deposits mentioned
nearby the Company’s property are not indicative of the diamond mineralization on the Company’s property, the supply
3
and demand for, deliveries of and the level and volatility of prices of rough diamonds, risks that the actual revenues will be
less than projected; risks that the target production for the existing mining contracts will be less than projected or
expected; risks that production will not commence as projected due to delay or inability to receive governmental approval
of the Company’s acquisition or the timely completion of an NI43‐101 report; technical problems; inability of management
to secure sales or third party purchase contracts; currency and interest rate fluctuations; foreign exchange fluctuations and
foreign operations; various events which could disrupt operations, including labor stoppages and severe weather
conditions; and management’s ability to anticipate and manage the foregoing factors and risks.
The forward‐looking statements and information contained in this news release are based on certain assumptions
regarding, among other things, future prices for coal and diamonds; future currency and exchange rates; the Company’s
ability to generate sufficient cash flow from operations and access capital markets to meet its future obligations; coal
consumption levels; and the Company’s ability to retain qualified staff and equipment in a cost‐efficient manner to meet its
demand. There can be no assurance that forward‐looking statements will prove to be accurate, as actual results and future
events could differ materially from those anticipated in such statements. The reader is cautioned not to place undue
reliance on forward‐looking statements. The Company does not undertake to update any of the forward‐looking
statements contained in this news release unless required by law. The statements as to the Company’s capacity to achieve
revenue are no assurance that it will achieve these levels of revenue.