COMMENCEMENT OF CONTRACT MINING OPERATIONS AT OENA DIAMOND MINE 

VANCOUVER, BRITISH COLUMBIA — 13 JUNE 2022 — Southstone Mineral s Limited (“Southstone” or the 

“Company”)  ( T S X . V  –  S M L )  i s  p l e a s e d  t o  a n n o u n c e  t h a t  O r y x  M i n i n g  ( P t y )  L t d  (“Oryx”)  has  commenced 

diamond mining operations at Oena Diamond Mine (“Oena”), South Africa. 

Oena will be operated 23 hours a day, 6 days a week with total head feed capacity of 200 tonnes per hour to 

a desanding screen which feeds to an 18‐foot pan plant. Concent rate produced from the pan plant will be 

transferred  securely  to  a  high  security  processing  facility  where  diamonds  will  be  recovered  using  BVX 

technology. Diamonds will be sold monthly at a designated tende r facility (see news release dated 19 April 

2022 for detailed terms). 

Oena  consists  of  an  8,800‐hectare  mining  right  located  along  th e  Orange  River  (see  Figure  1).  Mining 

op erat ion s wi ll  c om men ce at  Bl okwe rf  Se ct ion wit h s ub se qu ent  expansion to the Sandberg  Section. Since 

November 2018, Southstone has bulk sampled an estimated 638,690 tonnes from Sandberg recovering 2,681 

c a r a t s  ( c t s )  ( 1 , 1 5 5  d i a m o n d s )  w i t h  a n  a v e r a g e  s t o n e  s i z e  o f  2 . 32  cts  and  has  bulk  sampled  an  estimated 

202,760 tonnes from Blokwerf recovering 550 cts (307 diamonds) with an average stone size of 1.79 cts.  

I m p o r t a n t l y ,  S a n d b e r g  m i n e d  t o n n e s  t o  d a t e  c o m p r i s e  o n l y  3 0 %  o f t h e  t o t a l  t o n n e s  m i n e d  a t  O e n a  b y  

Southstone since 2015, yet Sandberg has produced more than 50%  of the diamonds over 10 ct and valued 

>USD $5,000 per ct.  Table  1  lists some  of the exceptional  diamo n d s  t h a t  h a v e  b e e n  r ec o v e r e d  f ro m  b ot h  

Sandberg and Blokwerf Sections over 10 ct and Table 3 provides images of a select number of diamonds. The 

average run of mine diamond sale price to from July 2015 to April 2022 is USD $1,612 per ct (see Table 2). 

Figure 1 – Oena Mining License 

2 

Diamond  See Photo  Section  Sales Weight (ct)  USD per ct  Total USD 

1  below  Sandberg 44.250 $5'492  $243'000

2  below  Sandberg  37.030  $5'103  $188'962 

3  below  Sandberg  35.000  $15'286  $535'000 

4  below  Sandberg  32.218  $1'809  $58'289 

5  below  Sandberg  26.410  $12'680  $334'900 

6  below  Sandberg  26.340  $5'884  $155'000 

7    Sandberg  22.020  $7'720  $170'000 

8  below  Sandberg  20.112  $4'031  $81'084 

9    Sandberg  19.420  $2'034  $39'500 

10    Sandberg  18.730  $8'270  $154'889 

11  below  Blokwerf  17.550  $3'971  $69'499 

12    Sandberg  16.922  $3'137  $53'100 

13    Sandberg  15.250  $5'016  $76'499 

14    Sandberg  14.800  $2'910  $42'900 

15    Sandberg  13.200  $2'121  $27'999 

16    Sandberg  10.651  $5'330  $56'780 

17  below  Sandberg  10.510  $8'712  $91'560 

Table 1 – Sandberg and Blokwerf selection of diamonds recovered over 10 cts 

Sandberg represents a  target of  4.50  million  (M) to 5.75M cubic   meters (approximately  11M tonnes)  and 

Blokwerf  represents  a  target  of 6.25M  to  7.25M  cubic  meters  (approximately  18M  tonnes)  of  basal  and 

suspended gravel has been identified for continued exploration  and bulk sampling. (see news release dated 

1 December 2014). 

  Total 

ct 

sold 

Total Number 

of Diamonds 

Average 

Diamond Size 

ct 

Average 

USD per ct 

Approx. 

Total Sales 

(USD) 

July 2015 to April 2022   7,967  3,958  2.01  1,612  $12,850,000 

Table 2 – Oena Diamond Mine production from July 2015 to April 2022 

Diamond  Size 

Date 

Value 

Photo 

1  44.25 carat ‐ $5,492 per carat ($243,000)

Sandberg 

20 March 2020 

3 

2  37.03 carat ‐ $5,103 per carat ($188,962)

Sandberg 

24 February 2020 

3  35.00 carat ‐ $15,286 per carat ($535,000)

Sandberg 

28 November 2019 

4 and 8  Sandberg – parcel of 16 stones 

32.218 carat ‐ $1,807 per carat ($58,289) 

20.112 carat ‐ $4,031 per carat ($81,084) 

4.75 carat     2.2 carat 

5.15 Carat     2.0 carat 

4.0 Carat     2.05 carat 

3.4 carat                     1.25 Carat 

4.0 carat                      0.95 carat 

3.15 carat     1.0 carat 

2.8 carat                     0.75 carat 

23 November 2020   

5  26.41 carat ‐$12,680 per carat ($334,900)

Sandberg – parcel of 3 stones 

3.85 carat 

3.25 carat 

24 January 2019 

6  26.34 carat ‐ $5,884 per carat ($155,000)

Sandberg 

18 September 2020 

4 

11  17.55 carat‐ $3,97 1 per carat ($69,499)

Blokwerf 

22 February 2019 

17  10.51 carat ‐$8,71 2 per carat ($91,560)

Sandberg 

23 January 2021 

Table 3 – Oena Diamond Mine diamond photos of select diamonds from Sandberg and Blokwerf production 

The technical disclosure in this news release has been approved by Terry L. Tucker, P.Geo., Executive Chairman 

of the Company and a Qualified Person as defined by National In strument 43‐101 of the Canadian Securities 

Administrators. 

ON BEHALF OF THE BOARD OF DIRECTORS OF SOUTHSTONE MINERALS LIMITED 

Terry L. Tucker, P.Geo. 

Executive Chairman 

[email protected] 

Neither TSX Venture Exchange nor its Regulation Services Provid er (as that term is defined in the policies of the TSX 

Venture Exchange) accepts responsibility for the adequacy or accuracy of this release. 

Forward‐Looking Statement 

Certain  information  set  forth  in  this  news  release  contains  “fo rward‐looking  statements”  and  “forward‐looking 

information”  under  applicable  securities  laws.  Except  for  statements  of  historical  fact,  certain  information  contained 

herein constitutes forward‐looking statements, which include ma nagement’s assessment of future plans and operations 

and are based on current internal expectations, estimates, proj ections, assumptions and beliefs, which may prove to be 

incorrect. Some of the forward‐looking statements may be identified by words such as “forecasts”, estimates”, “expects” 

“anticipates”,  “believes”,  “projects”,  “plans”,  “outlook”,  “capacity”  and  similar  expressions.  These  statements  are  not 

guarantees of future performance and undue reliance should not be placed on them. 

Such forward‐looking statements necessarily involve known and u nknown risks and uncertainties, which may cause the 

Company’s actual performance and financial results in future pe riods to differ materially from any projections of future 

performance or results expressed or implied by such forward‐loo king statements. These risks and uncertainties include, 

but are not limited to statements with respect to the estimation of mineral resources; the realization of mineral resource 

estimates;  anticipated  future  production,  capital  and  operating c o s t s ;  c a s h  f l o w s  a n d  m i n e  l i f e ;  p o t e n t i a l  s i z e  o f  a  

mineralized  zone;  potential  expansion  of  mineralization;  potential  types  of  mining  operations;  permitting  timelines; 

government  regulation  of  exploration  and  mining  operations;  risks  that  the  presence  of  diamond  deposits  mentioned 

nearby the Company’s property are not indicative of the diamond  mineralization on the Company’s property, the supply 

and demand for, deliveries of a nd the level and volatility of p rices of rough diamonds, risks that the actual revenues will 

be  less than projected;  risks that  the  target  production for  the  existing  mining contracts  will  be  less  than projected  or 

expected; risks that production will not commence as projected due to delay or inability to receive governmental approval 

of the Company’s acquisition or the timely completion of an NI43‐101 report; technical problems; inability of management 

to  secure sales  or  third  party  purchase contracts;  currency  and  interest  rate  fluctuations;  COVID‐19;  foreign  exchange 

fluctuations and foreign operations; various events which could disrupt operations, including labor stoppages and severe 

weather conditions; and management’s ability to anticipate and manage the foregoing factors and risks. 

5 

The  forward‐looking  statements  and  information  contained  in  this  news  release  are  based  on  certain  assumptions 

regarding, among other things, future prices for coal and diamo nds; future currency and exchange rates; the Company’s 

ability to generate sufficient cash flow from operations and ac cess capital markets to meet its future obligations; coal 

consumption levels; and the Company’s ability to retain qualifi ed staff and equipment in a cost‐efficient manner to meet 

its demand. There can be no assurance that forward‐looking stat ements will prove to be accurate, as actual results and 

future events could differ materially from those anticipated in such statements. The reader is cautioned not to place undue 

reliance  on  forward‐looking  statements.  The  Company  does  not  un dertake  to  update  any  of  the  forward‐looking 

statements contained in this news release unless required by law. The statements as to the Company’s capacity to achieve 

revenue are no assurance that it will achieve these levels of revenue.