Vancouver, British Columbia – February 8, 2024 – Sierra Madre Gold and Silver Ltd. (TSXV: SM,

OTCQX: SMDRF) (“Sierra Madre” or the “Company”) is pleased to provide an in-depth update of

its activities at the 100% owned past -producing La Guitarra Silver-Gold Mine Complex in Estado

de Mexico, Mexico, 130 km southwest of Mexico City.

Mine Restart Study

The Company has retained TechSer Mining Consultants Ltd., of Vancouver, B.C., to complete the

Mine Restart Study (“MRS”). This work will include an estimation of underground mine material

for the Guitarr a, Coloso and Nazareno mines and the Los Angeles bulk tonnage deposit .

Additional evaluations will include a n operating cost estimate covering the mine and recovery

plant, based on reagent and consumable usage, energy, and diesel consumption, from the 2013

to 2018 operating period which will be updated for current pricing. Labour, staff and management

costs will be based on the current wage structure and union labour contracts that have recently

been signed. As part of the study, a capital cost estimate will be prepared to cover restart needs

and will evaluate a potential throughput expansion within 24 months of commercial production.

This data is to be supported by contractor bids and vendor prices. The above data will then be

used in an economic evaluation to determine project viability. The MRS is expected to be

completed in Q2 of this year.

Mine and Infrastructure

Work has been ongoing to determine necessary steps for the potential re-start of production. In

accordance with recommendations made by officials with the Secretaria de la Defensa Nacional,

SEDENA, improvements to the underground powder magazines have been completed.

On January 29, 2024, SEDENA approved Guitarra’s 2024 explosives permit. This explosives permit

must be renewed every year and was a milestone event for any potential resum ption of

operation. All other operating permits are current and in good standing.

Compressed 6-inch air lines have been installed from the stationary compressors near the main

San Rafael portal to the La Cruz portal, a distance of over one kilometre with a 240 metre gain in

elevation. Compressors and electrical substations have been serviced and are operational.

Minimizing initial development costs is one of the key factors being used to develop the near-

term plan for advancement of the Project. As areas are identified and scheduled in the

development plan, the existing haulage ways, access drives and ramps are being inspected for

safety and rock stability, cleaned and readied.

Figure 1: Underground Powder Magazine

Processing Plant

All circuits in the processing plant are undergoing maintenance and rehabilitation work which

would be required for the resumption of operations. In the grinding circuit, the three ball mills

are being relined, all parts of the central drive shaft mechanisms overhauled, and the motors

cleaned and tested. A fourth ball mill with limited capacity will not be rebuilt at this time.

Figure 2: La Guitarra Ball Mills

Overall, the crushing circuit was found to be in good shape with no costly equipment replacement

or major repair items identified. Normal maintenance and overhaul work is ongoing. The fine ore

storage bin has had the interior divider s and portions of the walls replate d with heavy steel.

Conveyor belts and a ssociated motors have been serviced and wear and tear items have been

replaced where needed.

The flotation circuit is in good shape. Some piping is being replaced and the pumps are being

overhauled and serviced. The Wemco flotation cells are in very good shape, needing only some

replating work, along with normal maintenance. No repair work requiring a significant outlay of

capital has been identified. The Denver cell circuit will not be needed at this time.

The company’s plant operations and maintenance team have advanced the preparation work for

a potential plant restart within budget expectations.

The MRS will study an initial production level of 350 tonnes per day. Additional evaluation will

be completed on potentially increasing the grinding circuit’s capacity to greater than 500 tonnes

per day. As part of the MRS, an assessment was made of the throughput capacity of each circuit

in order to determine where bottlenecks might exist in potentially expanding processing

throughput using the current plant equipment . Below is a flow diagram showing the overall

arrangement of plant equipment and throughput capacity

Currently, the identified capacities and expansion choke points in the four circuits making up the

processing plant are:

• Crushing - 640 tonnes per day, second cone crusher needed for expanded capacity

• Grinding - 516 tonnes per day, a new ball mill will be needed for additional throughput

• Flotation - 620 tonnes per day plus an additional 580 tonnes per day, conditioner tank

needs replumbing, flotation tanks have a total joint 1,200 tonnes per day capaci ty with

some physical re-arrangement.

• Concentrate Filtration and Drying - 620 tonnes per day , assuming the historical ore

processed to concentrate produced mass reduction of 95%, filters are the limiting factor.

These capacities and the needed equipment to increase plant throughput will be used in the long-

term economic analysis portion of the MRS.

Qualified Person

Mr. Gregory Smith, P . Geo, Director of Sierra Madre, is a Qualified Person as defined by NI 43-101,

and has reviewed and approved the technical data and information contained in this news

release. Mr. Smith has verified the technical and scientific data disclosed herein.

About Sierra Madre

Sierra Madre Gold & Silver (TSXV:SM),(OTCQX:SMDRF) is a precious metals development and

exploration company, focused on evaluating the potential of restarting the La Guitarra Mine in

the Temascaltepec mining district, Mexico, and the exploration and development of its Tepic

and La Tigra properties in Nayarit, Mexico. The La Guitarra Mine is a permitted, past-producing

underground mine which includes a 500 t/d processing facility that operated until mid-2018.

The +2,600 ha Tepic Project hosts low-sulphidation epithermal gold and silver mineralization

with an existing historic resource.

Sierra Madre´s management has played key roles for managing exploration and development of

more than 22Moz gold and 600Moz silver in combined reserves and resources. Sierra Madre´s

team of professionals has collectively raised over $1B for mining companies.

On behalf of the board of directors of Sierra Madre Gold and Silver Ltd.,

"Alexander Langer"

Alexander Langer

President, Chief Executive Officer and Director

1-604-765-1604

Contact:

[email protected]

Cautionary Note

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in

the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of

this news release.

This press release contains "forward-looking information" and "forward-looking statements"

within the meaning of applicable securities legislation. The forward-looking statements herein

are made as of the date of this press release only, and the Company does not assume any

obligation to update or revise them to reflect new information, estimates or opinions, future

events or results or otherwise, except as required by applicable law. Often, but not always,

forward-looking statements can be identified by the use of words such as "plans", "expects", "is

expected", "budgets", "scheduled", "estimates", "forecasts", "predicts", "projects", "intends",

"targets", "aims", "anticipates" or "believes" or variations (including negative variations) of such

words and phrases or may be identified by statements to the effect that certain actions "may",

"could", "should", "would", "might" or "will" be taken, occur or be achieved. Forward-looking

information in this press release includes, but is not limited to, statements with respect to the

completion of the Transaction on the terms set out in the definitive agreement (or at all) and the

ability of the Company to obtain requisite corporate and regulatory approvals for the

Transaction, including but not limited to the approval of the Exchange, Mexican antitrust

approval and other governmental approvals as currently anticipated.

In making the forward-looking statements included in this news release, the Company has

applied several material assumptions, including that the Company will be able to receive all

required regulatory approvals by the timelines currently anticipated (or at all); and that the

Company will be able to complete the Transaction on the terms of the definitive agreement.

Forward-looking statements and information are subject to various known and unknown risks

and uncertainties, many of which are beyond the ability of the Company to control or predict,

that may cause the Company´s actual results, performance or achievements to be materially

different from those expressed or implied thereby, and are developed based on assumptions

about such risks, uncertainties and other factors set out herein, including, but not limited to, the

risk that the Company is not able to complete Transaction on the terms set out in the definitive

agreement (or at all) and the risk that the Company is unable to obtain requisite corporate and

regulatory approvals, including but not limited to the approval of the TSX Venture Exchange, the

Mexican antitrust approval and governmental approval as currently anticipated.

Such forward-looking information represents management´s best judgment based on

information currently available. No forward-looking statement can be guaranteed and actual

future results may vary materially. Accordingly, readers are advised not to place undue reliance

on forward-looking statements or information.

SOURCE: Sierra Madre Gold and Silver