Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

SKE.TO ·

Skeena Delivers Robust Project Economics for Eskay Creek: After-Tax NPV5% of C$638M, 51% IRR and 1.2 Year Payback

Economic Studies

Skeena Delivers Robust Project Economics for Eskay Creek:

After-Tax NPV5% of C$638M, 51% IRR and 1.2 Year Payback

Vancouver, BC (November 7, 2019) Skeena Resources Limited (TSX.V: SKE, OTCQX: SKREF)

(“Skeena” or the “Company”) is pleased to announce the initial Preliminary Economic Assessment

(“PEA”) completed by Ausenco Engineering Canada Inc. (“Ausenco”) , supported by SRK Consulting

(Canada), and AGP Mining Consultants, for the Eskay Creek gold-silver project (“Eskay Creek” or the

"Project") located in the Golden Triangle of British Columbia.

Eskay Creek 2019 PEA Highlights:

• High-grade open-pit averaging 3.23 g/t Au, 78 g/t Ag (4.17 g/t AuEq) (diluted)

• After-tax NPV5% of C$638M (US$491M) and 51% IRR at US$1,325/oz Au and US$16/oz Ag

• After-tax payback period of 1.2 years

• Pre-production capital expenditures (CAPEX) of C$303M (US$233M)

• After-tax NPV:CAPEX Ratio of 2.1:1

• Life of mine (“LOM”) average annual production of 236,000 oz Au, 5,812,000 oz Ag (306,000 oz

AuEq)

• LOM all-in sustaining costs (AISC) of C$983/oz (US$757/oz) AuEq recovered

• LOM cash costs of C$949/oz (US$731/oz) AuEq recovered

• 6,850 tonne per day (TPD) mill and flotation plant producing saleable concentrate

1. Exchange Rate (US$/C$) of 0.77

2. Cash costs are inclusive of mining costs, processing costs, site G&A, treatment and refining charges and royalties

3. AISC includes cash costs plus estimated corporate G&A, sustaining capital and closure costs

4. Gold Equivalent (AuEq) calculated via the formula: Au (g/t) + [Ag (g/t) / 82.8]

Skeena’s CEO, Walter Coles commented, “Eskay Creek was a remarkable discovery that became an

extraordinary underground mine in 1994 and produced until 2008. This PEA demonstrates that Eskay

Creek still has a bright future ahead, revitalized as an open-pit gold and silver mine, with the additional

possibility for underground mining . The Project has the potential to produce an average of 306,000

gold-equivalent ounces per year with a diluted mill feed grade of 4.17 grams per tonne gold-equivalent.

Also, as a brownfield site, Eskay Creek benefits from tremendous infrastructure installed by the

previous operators. Finally, by creating a gold concentrate rather than doré, we are able to keep initial

capital costs very low, at US$233 million, relative to the amount of precious metals produced; this also

simplifies and reduces technical risks for the Project.”

PEA Overview

The 2019 Eskay Creek PEA considers an open-pit mine with on-site treatment of the mined material

by conventional milling and flotation to recover a gold -silver concentrate for provision to third -party

smelters. The mine will be an owner -operated, standard truck and shovel open -pit, with a leased

mining fleet. At present, no contributions from previously reported underground resources are

NR: 19-18

November 7, 2019

incorporated into this study. The processing capacity of 6,850 tonnes per day will result in a production

lifespan of 8.6 years. An additional 1.5 years of pre -stripping, stockpiling and mine access

development is planned prior to the processing facility becoming fully operational in Year 1. The PEA

leverages Eskay Creek’s extensive existing infrastructure , including all -weather access roads,

previously permitted tailing storage facilities (TSF) and proximity to the recently commissioned

195 MW hydroelectric facilities and linked power grid.

The PEA is derived from the Company’s pit -constrained resource estimate (February 28, 2019), and

does not include results from the recently initiated and ongoing 2019 Phase I infill drilling program.

The effective date of the PEA is November 7, 2019 and a technical report will be filed on the

Company’s website and SEDAR within 45 days of this disclosure.

Mineral resources are not mineral reserves and do not have demonstrated economic viability. The

PEA is preliminary in nature and includes inferred mineral resources that are too speculative to have

economic considerations applied to them that would enable them to be categorized as mineral

reserves. There is no certainty that PEA results will be realized.

Table 1: 2019 Eskay Creek 2019 PEA Detailed Parameters and Outputs

Assumptions

Gold Price (US$) $1,325

Silver Price (US$) $16

Exchange Rate (US$/C$) 0.77

Discount Rate 5%

Royalties 1%

Contained Metals

Contained Gold Ounces (koz) 2,212

Contained Silver Ounces (koz) 53,404

Contained AuEq Ounces (koz) 2,857

Mining

Mine Life (Years) 8.6

Strip Ratio (Waste:Mineralization) 7.2:1

Total Tonnage Mined (t) 175,270

Total Mineralized Material Mined (t) 21,307

Processing

Processing Throughput (TPD) 6,850

Average Diluted Gold Grade (g/t) 3.23

Average Diluted Silver Grade (g/t) 78

Average Diluted Gold Equivalent Grade (g/t) 4.17

Production

Gold Recovery 91.1%

Silver Recovery 92.4%

LOM Gold Production (koz) 2,022

LOM Silver Production (koz) 49,872

LOM Gold Equivalent Production (koz) 2,624

LOM Average Annual Gold Production (koz) 236

LOM Average Annual Silver Production (koz) 5,812

LOM Average Annual Gold Equivalent Production (koz) 306

Operating Costs

Mining Cost (C$/t Mined) $3.44

Mining Cost (C$/t Milled) $26.32

Processing Cost (C$/t Milled) $21.64

G&A Cost (C$/t Milled) $6.06

1. Cash costs are inclusive of mining costs, processing costs, site G&A, treatment and refining charges and royalties

2. AISC includes cash costs plus corporate G&A, sustaining capital and closure costs

3. Gold Equivalent (AuEq) calculated via the formula: Au (g/t) + [Ag (g/t) / 82.8]

Sensitivities

After-tax economic sensitivities to commodity prices are presented in Table 2 illustrating

the effects of varying gold and silver prices as compared to the base -case. Additional

Project sensitivities will be presented in the Technical Report.

Table 2: After-Tax NPV (5%) and IRR Sensitivities to Commodity Prices

Lower

Case

Base

Case

Higher

Case

Gold Price (US$/oz) $1,200 $1,325 $1,500

Silver Price (US$/oz) $14 $16 $18

After-Tax NPV (5%) (C$M) $453 $638 $878

After-Tax IRR (%) 40% 51% 63%

After-Tax Payback (Years) 1.6 1.2 0.9

Average Annual After-Tax Free Cash Flow (Years 1-9) (C$M) $117 $147 $187

Eskay Creek Mineral Resource Estimate

The Company’s current Mineral Resource Estimate (MRE; effective date of February 28,

2019) completed by SRK Consulting (Canada) forms the basis for this PEA. The MRE

does not include drilling results from the Company’s recently initiated and ongoing 2019

Phase I infill program.

Total Operating Cost (C$/t Milled) $54.03

Cash Costs and AISC

LOM Cash Cost (US$/oz Au) Net of Silver By-Product $582

LOM Cash Cost (US$/oz AuEq) Co-Product $731

LOM AISC (US$/oz Au) Net of Silver By-Product $615

LOM AISC (US$/oz AuEq) Co-Product $757

Capital Expenditures

Pre-Production Capital Expenditures (C$M) $303

Sustaining Capital Expenditures (C$M) $27

Reclamation Cost (C$M) $52

Economics

After-Tax NPV (5%) (C$M) $638

After-Tax IRR 51%

After-Tax Payback Period (Years) 1.2

After-Tax NPV:CAPEX Ratio 2.1:1

Pre-Tax NPV (5%) (C$M) $993

Pre-Tax IRR 63%

Pre-Tax Payback Period (Years) 1.1

Pre-Tax NPV:CAPEX Ratio 3.3:1

Average Annual After-Tax Free Cash Flow (Year 1-9) (C$M) $147

LOM After-Tax Free Cash Flow (C$M) $959

Table 3: Pit constrained Mineral Resource Statement reported at 0.7 g/t AuEq cut-off:

Grade Contained Ounces

Tonnes AuEq Au Ag AuEq Au Ag

(000) g/t g/t g/t oz (000) oz (000) oz (000)

Total Indicated 12,650 5.8 4.3 110 2,340 1,740 44,660

Total Inferred 14,420 2.9 2.3 47 1,340 1,050 21,720

Table 4: Underground Mineral Resource Statement reported at a 5.0 g/t AuEq cut-off:

Grade Contained Ounces

Tonnes AuEq Au Ag AuEq Au Ag

(000) g/t g/t g/t oz (000) oz (000) oz (000)

Total Indicated 819 8.2 6.4 139 218 169 3,657

Total Inferred 295 8.2 7.1 82 78 68 778

1. Mineral resources are not mineral reserves as they do not have demonstrated economic viability. There is no certainty

that all or any part of the Mineral Resources estimated will be converted into Mineral Reserves.

2. Results are reported in-situ and undiluted and are considered to have reasonable prospects for economic extraction

3. The quantity and grade of reported Inferred Mineral Resources in this estimation are uncertain in nature and there has

been insufficient exploration to define these Inferred Mineral Resources as an Indicated Mineral Resource and it is

uncertain if further exploration will result in upgrading them to an Indicated Mineral Resource category.

4. For the PEA study, the open-pit block model was regularized to 9 m x 9 m x 4 m whole blocks using mineralization greater

than 0.5 g/t AuEq within a single mineralization percent field; therefore a slight difference exists between the resources

reported herein, and the resources released in the February 28, 2019 press release

5. The number of metric tonnes and ounces were rounded to the nearest thousand. Any discrepancies in the totals are due

to rounding

6. Reported underground resources are exclusive of the resources reported within the conceptual pit shell

7. Cut-off grades are based on a price of US$1,275 per ounce of gold, US$17 per ounce silver, and gold recoveries of 80%,

silver recoveries of 90% and without considering revenues from other metals. AuEq = Au (g/t) + (Ag (g/t) / 75)

8. Estimates use metric units (meters, tonnes and g/t). Metals are reported in troy ounces (metric tonne * grade / 31.10348)

9. CIM definitions were followed for the classification of mineral resources

Mining Overview

An o pen-pit mining scenario is the basis for this PEA ; u nderground precious metal resource

contributions are not being considered at this time. The owner-operated, leased mining fleet will utilize

conventional truck and shovel methods with 22m 3 shovels and 142 tonne haul trucks. Support

equipment is comprised of track d ozers, graders and hydraulic excavators ; a dditional support

equipment to maintain production during seasonal periods of high snowfall has also been

incorporated.

The mine designs and scheduling were engineered to provide 2.5 Mt per year of mineralization to the

6,850 TPD process plant. A total of 21.3 Mt of diluted mill feed averaging 3.23 g/t gold and 78 g/t silver

(4.17 g/t AuEq), is expected to be processed over the life of mine from the main pit area and a smaller

satellite pit hosting the 22 Zone. Mill feed will be trucked to a primary crusher located to the west of

the main pit and then conveyed overland two kilometers to the process facility. Waste totaling 154.0

Mt will be stored in a dump adjacent to the main and satellite o pen pits with a portion backfilled into

the pit as the mining sequence advances towards the north. Open-pit mining dilution has been factored

at 15%.

Conservative pit slopes were applied to the mine design with recognition of areas that exhibit lower

rock quality. Default Inter Ramp Angles (IRA) are 42 degrees throughout the hanging wall andesites

and footwall rhyolites, with 32-degree IRA slope allowance in the less competent mudstones. Batter

angles of 65 degrees have been applied throughout the entire design.

Metallurgical Optimizations

The former Eskay Creek mine operated over 14 years from 1994 and produced approximately 3.3

million ounces of gold and 160 million ounces of silver , either in flotation concentrate, with average

grades of 45 g/t Au and 2,224 g/t Ag, or as Direct Shipped Ore (DSO).

To support this PEA, metallurgical test work was conducted by Blue Coast Research using recently

drilled samples from the 21A, 21B and 22 zones, which represent a significant proportion of the open-

pit mine plan. Test work included comminution, whole-ore leaching, with gravity recovery as well as

flotation of a bulk sulphide concentrate. Low recovery cyanide leach extractions were observed in the

testwork, attributable to the free gold occurring as fine particles associated with sulphide minerals. In

addition, in this test work gravity concentration did not increase the overall gold recovery.

The 2019 metallurgical program has focused on optimizing bulk sulphide flotation, resulting in higher

recoveries and lower mass pull than was historically realized at Eskay Creek during its previous

operation. Flotation tests were performed on samples over a range of gold and silver head grades to

generate recovery relationships which were used to estimate the annual concentrate production over

the mine life. The results indicate that at an average head grade of 3.2 g/t gold and 78 g/t silver,

recoveries of 91% for gold and 92% for silver were estimated , with production of a saleable

concentrate containing 25 g/t Au, 604 g/t Ag, 620 ppm Hg, 0.71% As and 1.25% Sb.

Processing Overview

Run-of-mine (ROM) material is trucked from the mine and either stockpiled or direct tipped into the

primary crusher. Primary crushed feed material is in turn conveyed overland two kilometers to the mill

facility and stacked onto a covered coarse stockpile. The ROM material is considered relatively

competent with a design competency measurement of 32 and bond rod and ball mill work indices of

21.0 kWh/t and 19.4 kWh/t, respective ly. To provide the target particle size of P80 75 µm the

comminution circuit comprises a 3.3 MW semi semi -autogenous grinding (SAG) mill, 7.9 m diameter

by 3.7 m effective grinding length, and a 6.0 MW ball mill, 6.1 m diameter by 8.8 m length. A pebble

crushing circuit is also included. Ground material is processed through a conventional flotation circuit

including rougher/scavenger tank cells. Rougher-scavenger concentrate is subsequently ground to a

target size of P80 20 µm prior to multiple stages of cl eaning to produce a gold -silver concentrate.

Ultimately, flotation tailings are pumped to the existing Tailings Storage Facility (TSF), for disposal.

Flotation concentrate is thickened and filtered, and trucked to the port at Stewart, BC for loading onto

ships and transportation to third-party smelters worldwide.

Concentrate Marketing Studies

Multiple marketing assessments have been completed to support this PEA which confirm that Eskay

Creek concentrate, at a target grade of 25 g/t Au, is readily saleable. The preferred preliminary contract

terms for the concentrate have been provided by Chinese smelters, however multiple offtakes are

available. S melters onshore and within Europe have also been identified as potential markets ,

however they may apply higher penalties for non-payable elements. The Company has been offered

a term sheet for the entire concentrate production, which has been used as the basis for the financial

model, and includes gold and silver payabilities, industry standard treatment and refining charges, and

penalties for impurities; antimony is not considered to be a payable element at this time.

Capital Costs

Table 5: Project Capital Cost Estimates (C$M) (totals may differ due to rounding):

Contingency Initial Sustaining LOM

Total

Mine

Pre-Stripping $62 $62

Mining Equipment $14 $6 $20

Mine Capital $7 $3 $9

Sub-Total Mine $4 $83 $9 $91

Processing

Bulk Earthworks $7 $7

Processing $74 $7 $81

Reagents & Plant Services $7 $1 $8

Tailings & Water Treatment $19 $2 $21

Onsite Infrastructure $22 $2 $23

Sub-Total Processing $21 $129 $12 $141

Infrastructure

Power $13 $13

TSF, Water Supply & Treatment $2 $4 $6

Sub-Total Infrastructure $5 $15 $4 $19

Total Directs $226 $24 $250

Indirects $7 $27 $27

Total Directs + Indirects $253 $24 $277

Owner’s Costs $4 $10 $10

Total excluding contingency $263 $24 $287

Project Contingency $40 $3 $43

Sub-total including contingency $303 $27 $330

Closure $52 $52

Total $303 $79 $382

Environmental and Permitting Considerations

Eskay Creek represents a closed mine with existing permits for mine discharge and waste disposal.

The site has been maintained in good standing and environmental monitoring has been ongoing during

operations and since the site was closed in 2008. There is a substantia l database of environmental

information for the site and region spanning almost 30 years. To accommodate the mine design

contemplated by the PEA, updated environmental assessment and mine permits will be required. The

Company is currently performing a gap analysis of existing environmental data to identify additional

data needs with the intent of carrying out environmental baseline studies to advance the permitting

process.

Community Relations

Eskay Creek has maintained a long-standing relationship with the Tahltan Nation. Previous operators

maintained agreements with the Tahltan which included provisions for training, employment, and

contracting opportunities. The Company has been working in the Tahltan Territory since 2016 and has

developed a strong wor king relationship with the Nation. Skeena also maintains formal agreements

with the Tahltan Central Government which guide communications, environmental practices, and

contracting and employment opportunities for projects in Tahltan Territory. Skeena participates in the

BC Regional Mining Alliance (BCRMA) which is a partnership between First Nations, the BC

Government, AME BC and exploration companies operating in the Golden Triangle region of BC. The

BCRMA provides a platform for all parties to collaborate in communications with potential investment

partners on opportunities in the region.

Project Opportunities and Value Enhancements

The 2019 PEA clearly demonstrates that Eskay Creek has the potential to b ecome an economically

viable project. Additional opportunities and next steps include:

• Continued drill conversion of inferred resources to the measured and indicated categories

• Potential for expansion and upgrading of the existing pit constrained and inclusion of

underground resources

• Mine scheduling investigations allowing for the further optimization of blending scenarios

• Supplementary metallurgical optimizations including deposit-wide variability testing

• Geotechnical investigations to complement a nd potentially enhance the current pit slope

designs

• Gap analyses and environmental baseline studies to support expedited permitting

• Further optimization of water management infrastructure

Qualified Persons

In accordance with National Instrument 43 -101 Standards of Disclosure for Mineral Projects, Paul

Geddes, P.Geo. Vice President Exploration and Resource Development, is the Qualified Person for

the Company and has prepared, validated and approved the technical and scientific content of this

news release.

Sheila Ulansky, P .Geo., Senior Resource Geologist for SRK Consulting (Canada) Inc ., is an

independent Qualified Person as defined by NI43 -101 and has reviewed and approved the contents

of this news release. Ms. Ulansky is responsible for the 2019 Mineral Resource Estimate for the Eskay

Creek Project.

Robin Kalanchey, P.Eng, Director, Minerals & Metals - Western Canada for Ausenco Engineering Inc.,

is an independent Qualified Person as defined by NI43 -101 and has reviewed and approved the

contents of this news release. Mr. Kalanchey is responsible for processing, process and infrastructure

capital and operating cost estimation, financial analysis and marketing.

Gordon Zurowski, P.Eng, Principal Mining Engineer for AGP Mining Consultants Inc., is an

independent Qualified Person as defined by NI43 -101 and has reviewed and approved the con tents

of this news release. Mr. Zurowski is responsible for mine capital and operating cost estimation and

supervision of the mine design.

Adrian Dance, P.Eng , Principal Consultant (Metallurgy) for SRK Consulting (Canada) Inc. , is an

independent Qualified Person as defined by NI43 -101 and has reviewed and approved the contents

of this news release. Dr. Dance is responsible for mineral processing and metallurgical testing.

The Company strictly adheres to CIM Best Practices Guidelines in conducting, documenting, and

reporting the exploration and development activities on its projects.

About Skeena

Skeena Resources Limited is a junior Canadian mining exploration company focused on developing

prospective precious and base metal properties in the Golden Triangle of northwest British Columbia,

Canada. The Company’s primary activities are the exploration and development of the past-producing

Snip mine and the Eskay Creek mine, both acquired from Barrick . In addition, the Company has

completed a Preliminary Economic Assessment on the GJ copper-gold porphyry project.

On behalf of the Board of Directors of Skeena Resources Limited,

Walter Coles Jr.

President & CEO

Cautionary note regarding forward-looking statements

Certain statements made and information contained herein may constitute “forward looking information” and “forward

looking statements” within the meaning of applicable Canadian and United States securities legislation. These statements

and information are based on facts currently available to the Company and there is no assurance that actual results will

meet management’s expectations. Forward -looking statements and information may be identified by such terms as

“anticipates”, “believes”, “targets”, “estimates”, “plans”, “expects”, “may”, “will”, “could” or “would”. Forward -looking

statements and information contained herein are based on certain factors and assumptions regarding, among other things,

the estimation of mineral resources and reserves, the realization of resource and reserve estimates, metal prices, taxation,

the estimation, timing and amount of future exploration and development, capital and operating costs, the availability of

financing, the receipt of regulatory approvals, environmental risks, title disputes and other matters. While the Company

considers its assumptions to be reasonable as of the date hereof, forward -looking statements and information are not

guarantees of future performan ce and readers should not place undue importance on such statements as actual events

and results may differ materially from those described herein. The Company does not undertake to update any forward -

looking statements or information except as may be required by applicable securities laws.

Neither TSX Venture Exchange nor the Investment Industry Regulatory Organization of Canada accepts responsibility for

the adequacy or accuracy of this release.