Skeena Completes PFS for Eskay Creek: After-Tax NPV(5%) of C$1.4B, 56% IRR and 1.4 Year Payback
Skeena Completes PFS for Eskay Creek: After-Tax NPV(5%) of C$1.4B,
56% IRR and 1.4 Year Payback
Vancouver, BC ( July 22, 2021) Skeena Resources Limited (TSX: SKE, OTCQX: SKREF)
(“Skeena” or the “Company”) is pleased to announce the results of the Prefeasibility Study (“PFS”)
completed by Ausenco Engineering Canada Inc. (“Ausenco”), supported by SRK Consulting
(Canada), and AGP Mining Consultants, for the Eskay Creek gold-silver project (“Eskay Creek” or the
"Project") located in the Golden Triangle of British Columbia.
Eskay Creek 2021 PFS Highlights:
• High-grade open-pit averaging 3.37 g/t Au, 94 g/t Ag (4.57 g/t AuEq) (diluted)
• Proven and Probable Mineral Reserves of 3.88 Moz AuEq (26.4 Mt at 3.37 g/t Au
and 94 g/t Ag).
• After-tax NPV5% of C$1.4 billion, (US$1.1 billion) and 56% IRR at US$1,550/oz
Au and US$22/oz Ag
• After-tax payback period of 1.4 years
• Pre-production capital expenditures (CAPEX) of C$488M (US$381M)
• After-tax NPV:CAPEX Ratio of 2.9:1
• Life of mine (“LOM”) average annual production of 249,000 oz Au, 7,222,000 oz
Ag (352,000 oz AuEq) over a 9.8-year mine life
• LOM all-in sustaining costs (“AISC”) of C$702/oz (US$548/oz) AuEq recovered
• LOM cash costs of C$651/oz (US$509/oz) AuEq recovered
• 7,945 tonne per day ( “tpd”) mill and flotation plant producing saleable
concentrate
• LOM average greenhouse gas (“GHG”) emissions of 0.18 t CO2e/oz AuEq
• Exchange Rate (US$/C$) of 0.78
• Cash costs are inclusive of mining costs, processing costs, site G&A, treatment and refining charges and royalties
• AISC includes cash costs plus estimated corporate G&A, sustaining capital and closure costs
• t CO2e = tonnes of carbon dioxide equivalent
Skeena’s CEO, Walter Coles Jr. commented, “Eskay Creek has a rare combination of attributes: scale,
impressive grade and location in a tier one mining jurisdiction with strong First Nations support. In the
first 5 years of operation, it is anticipated that Eskay Creek will produce, on average, 450,000 gold
equivalent ounces per year. We expect further increases to the annual production profile as we move
to the Feasibility Study in Q1 of 2022, and beyond. Our goal is to create a mine produc ing 500,000
gold equivalent ounces per year for 10 years. The PFS is only based on the current open-pit resources.
Skeena has a 35,000-metre exploration program underway at Eskay Creek to continue to grow the
open-pit resources, and we have yet to focus on the considerable underground exploration potential.”
NR: 21-29 | July 22, 2021
PFS Overview
The 2021 Eskay Creek PFS considers an open -pit mine with on-site treatment of the mined material
by conventional milling and flotation to recover a gold -silver concentrate. The mine will be an owner -
operated, standard truck and shovel open-pit, with a leased mining fleet. The plant will process ore at
a nominal rate of 2.0 million tonnes per year (“Mt/y”) (5,480 tpd) in Year 1 during ramp -up, 2.9 Mt/y
(7,945 tpd) for Years 2 to 4 then reduce to 2.7 Mt/y (7,400 tpd) in Year 5 onward as the mater ial
increases in hardness and competency over an expected production lifespan of 9.8 years. An
additional 30 months of pre-stripping, stockpiling and mine access development is planned prior to the
processing facility becoming fully operational in Year 1. The PFS leverages Eskay Creek’s extensive
existing infrastructure, including all-weather access roads, previously permitted tailing storage facilities
(“TSF”) and proximity to the 195 MW hydroelectric facilities and linked power grid.
The PFS is derived from the Company’s pit -constrained resource estimate (April 7, 2021) and does
not include results from the recently initiated and ongoing 2021 drill program. The effective date of the
PFS is July 22, 2021, and a technical report will be filed on the Company’s website and SEDAR within
45 days of this disclosure.
Table 1: 2021 Eskay Creek PFS Project Parameters
Economic Assumptions
Gold Price (US$/oz) $1,550
Silver Price (US$/oz) $22
Exchange Rate (US$/C$) 0.78
Discount Rate 5.0%
Contained Metals
Contained Gold (koz) 2,866
Contained Silver ounces (koz) 80,197
Mining
Mine Life 9.8 years
Strip Ratio (Waste:Ore) 8:1
Total Material Mined (excl. rehandle) (kt) 238,030
Total Mineralized Material Mined (kt) 26,419
Processing
Processing Throughput
5480 tpd (Yr 1)
7945 tpd (Yr 2-4)
7400 tpd (Yr 5
onwards)
Average Diluted Gold Grade 3.37 g/t
Average Diluted Silver Grade 94 g/t
Average Diluted AuEq Grade 4.57g/t
Production
Gold Recovery 84.2%
Silver Recovery 87.3%
LOM Gold Production (koz) 2,448
LOM Silver Production (koz) 70,902
LOM AuEq Production (koz) 3,455
LOM Avg. Annual Gold Production (koz) 249
LOM Avg. Annual Silver Production (koz) 7,222
LOM Avg. Annual AuEq Production (koz) 352
Operating Costs Per Tonne
Mining Cost (C$/t Mined) $3.58
Mining Cost (C$/t Milled) $30.56
Processing Cost (C$/t Milled) $18.22
G&A Cost (C$/t Milled) $6.23
Total Operating Costs (C$/t Milled) $55.01
Other Costs
Transport to Smelter (C$/wmt) $146
Royalty (NSR %) 2.0%
Cash Costs and All-in Sustaining Costs
LOM Cash Cost (US$/oz Au) net of silver by
product $84
LOM Cash Cost (US$/oz AuEq) co-product $509
LOM AISC (US$/oz Au) net of silver by -
product $138
LOM AISC (US$/oz AuEq) co-product $548
Capital Expenditures
Pre-production Capital Expenditures (C$M) $488
Sustaining Capital Expenditures (C$M) $47
Reclamation Cost (C$M) $92
Economics
After-Tax NPV (5%) (C$M) $1,399
After-Tax IRR 56%
After-Tax Payback Period (years) 1.4
After-Tax NPV / Initial Capex 2.9 x
Pre-Tax NPV (5%) (C$M) $2,174
Pre-Tax IRR 68%
Pre-Tax Payback Period (years) 1.3
Pre-Tax NPV / Initial Capex 4.5 x
Average Annual After-tax Free Cash Flow
(year 1-10) (C$M) $265
LOM After-tax Free Cash Flow (C$M) $2,118
• Cash costs are inclusive of mining costs, processing costs, site G&A and royalties
• AISC includes cash costs plus corporate G&A, sustaining capital and closure costs
• All dollar ($) figures are presented in CAD unless otherwise stated. Base case metal prices used in this economic
analysis are US$1,550/oz Au and US$22/oz Ag. These prices are based on long-term average prices.
Sensitivities
After-tax economic sensitivities to commodity prices , presented in Table 2 , illustrate the effects of
varying gold and silver prices as compared to the base -case. Additional Project sensitivities will be
presented in the Technical Report.
Table 2: After-Tax NPV (5%) and IRR Sensitivities to Commodity Prices (PFS)
Lower
Case
Base
Case
Higher
Case
Upside
Case
Gold Price (US$/oz) $1,400 $1,550 $1,700 $1950
Silver Price (US$/oz) $20 $22 $24 $26
After-Tax NPV (5%) (C$M) $1,162 $1,399 $1,635 $1,985
After-Tax IRR (%) 49% 56% 62% 70%
After-Tax Payback (Years) 1.6 1.4 1.2 1.1
After-Tax NPV/Initial Capex 2.4 x 2.9 x 3.4 x 4.1 x
Average Annual After-Tax Free Cash Flow
(Years 1-10) (C$M) $231 $265 $300 $352
Eskay Creek Mineral Resource Estimate
The Company’s current Mineral Resource Estimate (“MRE”; effective date of April 7, 2021) completed
by SRK Consulting (Canada) forms the basis for this PFS. The MRE does not include drilling results
from the Company’s recently initiated and ongoing 2021 drill program.
Table 3: Pit constrained Mineral Resource Statement reported at 0.7 g/t AuEq cut-off:
Grade Contained Ounces
Tonnes
(Mt)
AuEq
(g/t)
Au
(g/t)
Ag
(g/t)
AuEq
(Moz)
Au
(Moz)
Ag
(Moz)
Measured 17.3 5.8 4.2 118.4 3.2 2.3 65.9
Indicated 20.3 2.9 2.2 52.5 1.9 1.4 34.4
Total M&I 37.7 4.2 3.1 82.8 5.1 3.8 100.3
• These mineral resources are not mineral reserves as they do not have demonstrated economic viability. Results
• are reported in-situ and undiluted and are considered to have reasonable prospects for economic extraction.
• As defined by NI 43-101, the Independent and Qualified Person is Ms. S Ulansky, PGeo of SRK Consulting
• (Canada) who has reviewed and validated the Mineral Resource Estimate.
• The effective date of the Mineral Resource Estimate is April 7, 2021.
• The number of metric tonnes and ounces were rounded to the nearest thousand. Any discrepancies in the totals
• are due to rounding.
• Pit constrained Mineral Resources are reported in relation to a conceptual Pit shell.
• Block tonnage was estimated from average specific gravity measurements using lithology groupings.
• All composites have been capped where appropriate.
• Pit mineral resources are reported at a cut- off grade of 0.7 g/t, cut off grades must be revaluated considering prevailing market conditions.
• Cut-off grades are based on a price of US$1,700 /oz Au, US$23/oz Ag, and gold recoveries of 90%, silver recoveries of 80% and without
considering revenues from other metals. AuEq = Au (g/t) + [Ag (g/t) / 74]
• Estimates use metric units (metres, tonnes and g/t). Metals are reported in troy ounces (metric tonne * grade /
• 31.10348)
• CIM definitions were followed for the classification of mineral resources.
• Neither the company nor SRK is aware of any known environme ntal, permitted, legal, title -related, taxation, socio-political,
marketing or other relevant issue that could materially affect this mineral resource estimate.
Mining Overview
An open-pit mining only scenario is the basis for this PFS. The underground precious metal resource
opportunity has not been considered at this time. The owner -operated, leased mining fleet will utilize
conventional truck and shovel methods with 22 m 3 shovels and 144 tonne haul trucks. Support
equipment is comprised of track dozers, graders , and hydraulic excavators; additional support
equipment to maintain production during seasonal periods of high snowfall has also been
incorporated.
The mine designs and scheduling were engineered to provide 2.9 Mt per year of ore to the process
plant in the first 4 years, followed by 2.7 Mt per year for the remainder of the mine life.
A total of 26.4 Mt of diluted mill feed averaging 3.37 g/t gold and 94 g/t silver (4. 57 g/t AuEq), is
expected to be processed over the life of mine from the main pit area and a smaller satellite pit hosting
the 22 Zone.
Mill feed will be trucked to a primary crusher located to the west of the main pit and then conveyed
overland to the processing facility. Non-acid generating waste totaling 161 Mt will be stored in a waste
storage facility adjacent to the main and satellite open pits with a portion backfilled into the pit as the
mining sequence advances towards the north. Potentially acid-generating waste totaling 50 Mt will be
hauled to the Tom MacKay storage facility and stored sub-aqueously together with tailings.
Open-pit mining dilution has been estimated to cause a 21% increase in tonnes delivered to the mill
and a 16.6% decrease in overall head grades. Pit slopes were grouped into weak and competent
lithology groups. The weak slope domains were applied to the mine design using an inter ramp angle
(“IRA”) of 34 degrees with recognition of areas tha t exhibit lower rock quality. A default IRA of 46
degrees is applied throughout for the competent rocks. Batter angles of 70 degrees have been applied
throughout the entire design with IRA achieved by variable berm widths.
The reserves for Eskay Creek are based on the conversion of the Measured and Indicated resources
within the current Technical Report mine plan. Measured resources are converted to Proven Reserves
and Indicated resources are converted directly to Probable Reserves. The total reserves for Eskay
Creek are shown in Table 4 below. Some variation may exist due to rounding.
Table 4: 2021 Proven and Probable Reserves (Metric Units)
Reserve
Class Tonnes Grade Contained Ounces
(Mt)
AuEq
(g/t)
Au
(g/t)
Ag
(g/t)
AuEq
(Moz)
Au
(Moz)
Ag
(Moz)
Proven 13.5 5.81 4.25 124 2.53 1.85 53.7
Probable 12.9 3.26 2.46 64 1.35 1.02 26.5
Total 26.4 4.57 3.37 94 3.88 2.87 80.2
Note: This mineral reserve estimate is as of June 30th, 2021 and is based on the mineral resource estimate dated
April 7, 2021 for Skeena Resources by SRK Consulting. The mineral reserve calculation was completed under the
supervision of Willie Hamilton, P.Eng. of AGP, who is a Qualified Person as defined under NI 43-101. Mineral reserves
are stated within the final design pit based on a US$1,475/oz gold price and US$20.00/oz silver price. The NSR cut -
off grade of C$30.56/t was used to define the marginal cut-off material. The life-of-mine mining cost averaged C$3.14/t
mined, preliminary processing and G&A costs are C$24.50/t ore and C$6.06/t ore respectively. The ore recoveries
were varied according to gold head grade and concentrate grades. Gold concentrate grades varied from 20 to 60 g/t
gold. The gold equivalent grades are based on 79.3 Ag ounces yielding similar value to an Au ounce.
Production Profile
The P FS outlines an average production profile of 450 ,000 oz AuEq over the first five years of
production. Average annual production over the full LOM is expected to be 352,000 oz AuEq. Further
optimization or exploration discoveries may increase the production profile or extend the LOM
schedule in the future.
It is anticipated that Skeena will have accumulated approx imately 500,000 tonnes of mineralized
material on surface when the processing plant is expected to reach its designed throughput capacity,
providing flexibility in the early stages of production. This ramp-up profile is expected to lower the risk
of start -up and minimizes sustaining capital investment at the outset of the production. There is
potential for the ramp up profile to be accelerated with further optimization work.
Graph 1: Eskay Creek LOM Production Profile
Metallurgical Optimizations
PFS Test Work
Skeena completed additional Prefeasibility test work in 2020. The samples used in the PFS test
program as well as fresh core intervals from the 21A, 21B, 21C, 21E and HW Zones were evaluated
by Base Metallurgic al Laboratories Ltd. in Kamloops BC. Composite samples representing the first
three years of plant feed were also prepared. An extensive flotation testing program was completed,
resulting in a modified process flowsheet.
Mineralogical studies indicated a portion of the gold was associated with non -sulphide gangue and
flotation performance was negatively influenced by the presence of soft minerals. The solution was to
include a desliming stage where these soft minerals were isolated and floated separately. The result
was improved flotation response for the coarse material. This mill-float-mill-float circuit (“MF2”) is used
in platinum processing for fine-grained precious metal recovery.
Improved Metallurgy
The MF2 flowsheet was tested on both the annual com posites and variability samples to evaluate its
suitability to process a range of Eskay Creek material. The result was the ability to generate a higher
concentrate grade without significant loss in gold recovery. This is a significant improvement over the
PEA flowsheet.
A 45 g/t Au concentrate is being targeted to maximize gold recovery although samples generated final
concentrate grades of more than 55 g/t Au. Concentrate silver grades are expected to be between
900 g/t and 2,400 g/t with the average LOM concentrate grade being 60 g/t AuEq. Arsenic, mercury,
and antimony penalties are primarily incurred during the first three years of operation with an average
cost of approximately C$18M per year. The highest penalties are incurred in the first year of operation
(when the higher gold grade feed is processed). From Year 4 onwards, arsenic in concentrate is
expected to be at or below 1% and mercury below 350 ppm.
Processing Overview
Run-of-mine (“ROM”) material is trucked from the mine and either stockpiled or direct fed into the
primary crusher. Primary crushed feed material is in turn conveyed to the mill facility and stacked onto
a coarse ore stockpile. The ROM material is considered relatively competent with average Bond Rod
and Ball Mill Work Indices of 15.8 kWh/t and 17.9 kWh/t, respectively. To achieve the target primary
particle P80 (80% passing) size of 100 µm the comminution circuit comp rises a 3.8 MW semi -
autogenous grinding (SAG) mill, 7.3 m diameter by 4.3 m effective grinding length, and a 4.9 MW ball
mill, 5.5 m diameter by 9.0 m length. A pebble crushing circuit is also included and will be
commissioned in year 4. Ground material is processed through a split flotation circuit consisting of
roughers, scavengers, fines roughers, cleaners and fines cleaner flotation, along with regrinding of
rougher concentrate, slimes classification of rougher tailings and secondary grinding prior to
scavenger flotation. Rougher concentrate is re -ground to a target P 80 size of 15 µm and slimes
classification underflow is secondary ground to a target P 80 size of 30 µm, prior to multiple stages of
cleaning to produce a combined gold -silver concentrate with the slimes circuit concentrate. Flotation
tailings are pumped to the existing Tom MacKay Storage Facility and sub-aqueously stored together
with the potentially acid generating (“PAG”) waste rock. Flotation concentrate is thickened and filtered,
and trucked to the port at Stewart, BC for loading onto ships and transportation to third-party smelters
worldwide.
Concentrate Marketing Studies
Multiple marketing assessments have been completed to support the PFS which indicate that the
Eskay Creek concentrate is readily saleable at a target grade of 45 g/t Au . The preferred preliminary
contract terms for the concentrate have been provided by Asi an smelters, however multiple offtakes
are available. Smelters/traders within Europe have also provided draft term sheets, and these have
also been identified as potential markets given the high concentrate grades. The Company has been
offered several preliminary term sheets for the entire concentrate production, which ha ve been used
as the basis for the financial model, and include gold and silver payabilities, industry standard
treatment and refining charges, and penalties for impurities. For the purposes of the PFS, smelter
payabilities average 84% for gold and 83% for silver.
Capital Costs
Table 5: Project Capital Cost Estimates (C$M) (totals may differ due to rounding):
Initial
Sustaining
LOM
Total
Mine
Pre-Stripping $88 $88
Mining Equipment $14 $17 $31
Mine Capital $18 $23 $40
Sub-Total Mine $120 $40 $160
Processing
Bulk Earthworks $14 $14
Processing $114 $1 $115
Reagents & Plant Services $1 $1
Onsite Infrastructure $54 $54
Sub-Total Processing $183 $1 $184
Infrastructure
Power $29 $29
TSF, Water Supply & Treatment $8 $6 $14
Sub-Total Infrastructure $37 $6 $44
Total Directs $340 $47 $388
Indirects $68 $68
Total Directs + Indirects $408 $47 $455
Owner’s Costs $27 $27
Total excluding Contingency $435 $47 $483
Project Contingency $53 $53
Sub-total including Contingency $488 $47 $535
Closure $92 $92
Total $488 $140 $627
Environmental and Permitting Considerations
Eskay Creek represents a closed mine with existing permits for mine disturbance and development,
mine discharge and waste disposal. The site has been maintained in good standing and environmental
monitoring has been ongoing during operations and since the site was closed in 2008. There is a
substantial database of environm ental information for the site and region spanning almost 30 years.
To accommodate the mine design contemplated by the PFS, updated environmental assessment and
mine permits will be required. The Company is completing environmental and socio -economic
baseline studies and recently entered the environmental assessment and permitting process.
Eskay Creek is projected to be one of lowest GHG emission open-pit gold mines worldwide, emitting
an average of 0.18 tonnes of CO2e per gold equivalent ounce produced. Several factors contribute to
this low number, such as the high-grade nature of the deposit and access to clean, green hydro energy
near the site.