Silverco Mining Releases Robust PEA for the Cusi Mine Highlighting High-Margin, Low Capital Restart
Silverco Mining Releases Robust PEA for the
Cusi Mine Highlighting High-Margin, Low
Capital Restart
Vancouver, British Columbia--(Newsfile Corp. - April 13, 2026) - Silverco Mining Ltd. (TSXV: SICO)
(OTCQB: SICOF) (the
"Company"
) is pleased to announce the results of an independent Preliminary
Economic Assessment ("PEA") for the restart of its 100%-owned Cusi Mine located in Chihuahua,
Mexico.
Key Highlights:
After-tax NPV (5%) of US$104.1 million ("M"), IRR of 94.8% and a payback period of 0.9-years at
base case average silver price of US$44.58/ounce ("oz").
After-tax NPV (5%) of US$312.2 M, IRR of 186.9% and a payback period of 0.5-years at the
upside case of US$75.00/oz.
Average annual production of ~2.5 Moz silver equivalent (“AgEq”)
1
(2028-2033) with ~90%
revenue from silver.
Life-of-mine AISC of US$26.75 per payable oz AgEq.
Initial capital of only US$19.2 M, delivering 5.4x after-tax NPV/to initial capital at base case metal
prices.
Restart of processing targeted for late 2026 with full ramp-up by mid-2027
30,000 metre surface and underground drill program underway targeting infill, resource growth and
mine life extension.
Early restart work is underway at the mine and mill and discussions are underway to select an
underground contractor.
Mark Ayranto, President and CEO, commented:
"We believe the PEA confirms Cusi as one of the most compelling primary silver restart opportunities
globally. With low upfront capital, rapid payback, and strong leverage to rising silver prices, Cusi is
positioned to deliver near-term production and cash flow. Importantly, ongoing drilling and restart work
provide clear upside to both scale and mine life.
We have sufficient funds currently on hand to finance the restart and continue our previously
announced 30,000 m drill program that is testing for on strike and downthrown extensions, in addition
to infill drilling. Work is also well underway at the mine and mill to support the restart, including
dewatering and mine rehabilitation, hiring of key discipline managers, and commencement of the bid
process for an underground mine contractor. With concentrate production scheduled to begin in late
2026 and full ramp-up by mid-2027, we are looking at a very rapid timeline to meaningful production
and cash flow."
The results of the PEA are preliminary in nature and include Inferred Mineral Resources that are
considered too speculative geologically to have economic considerations applied to them that would
enable them to be categorized as Mineral Reserves.
A report supporting this news release will be available on SEDAR+ (
www.sedarplus.ca
) and on the
Company's website (
www.silvercomining.com
) within the next 45 days. All dollar amounts referenced in
this news release are in United States dollars (USD or US$) unless otherwise noted.
PEA Overview
The PEA was prepared by JDS Energy & Mining Inc. ("JDS"), Forte Dynamics ("Forte"), and SGS
Geological Services ("SGS").
The PEA outlines a low-capital restart of an existing underground mine with an initial approximately nine-
year mine life and steady-state throughput of 1,200 tonnes per day (“tpd”). Production is scheduled to
begin in late 2026, with full ramp-up by mid-2027, and average annual output of 2.47 million oz AgEq
produced from 2028-2033.
Table 1: PEA Summary Table
Units
Mill Feed
Mine Life
years
8.3
Mine Throughput
Mt/annum
4.4
Milling Throughput
t/d
1,200
Silver Recovery
%
84.0%
Lead Recovery
%
91.5
Zinc Recovery
%
73.0
Gold Recovery
%
79.0
Average AgEq Produced
(1)
M AgEqoz/year
2.1 (peak 2.8)
Average AgEq Payable
(1)
M AgEqoz/year
1.7 (peak 2.4)
Financial Analysis - Base Case (Average Ag - $44.58/oz)
(2)
Pre-Tax NPV5%
$M
188.2
Pre-Tax IRR
%
155.7
Pre-Tax Payback
years
0.6
After-Tax NPV(5%)
$M
104.1
After-Tax IRR
%
94.8%
After-Tax Payback
years
0.9
Financial Analysis - Upside Case (Fixed Ag - $75/oz)
(2)
After-Tax NPV(5%)
$M
312.2
After-Tax IRR
%
186.9
After-Tax Payback
years
0.5
Capital Costs
Initial
(3)
$M
19.2
Sustaining, including closure
$M
140.6
Operating Costs
Mining
$/t
40.27
Processing
$/t
23.23
G&A
$/t
9.03
Contingency
$/t
3.63
Cash Operating Costs
$/AgEqoz
17.24
Site AISC
$/AgEqoz
26.75
Notes:
1
.
Average Produced and Payable excludes values from 2026
2
.
Metal prices for Lead, Zinc, and Gold for both Base and Upside cases are $0.91/lb, $1.21/lb, and $3,000/oz respectively.
3
.
Initial capital is inclusive of all capital spend and owners costs to end of Q1 2027 and includes revenue generation during commissioning
period from Q4 2026 to Q1 2027
Silver Revenue
The Cusi Project's economic profile is defined by its substantial leverage to silver prices, with 88% of the
projected life-of-mine Net Smelter Return (NSR) revenue generated directly from silver production. The
remaining 12% of the NSR revenue is comprised of by-product metals, including lead (8%), gold (3%),
and zinc (1%), as calculated using the PEA's metallurgical recovery, metal price assumptions, and
payabilities.
Figure 1 - Life-of-Mine Net Smelter Return by Metal
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/10393/292137_silvercofig1.jpg
Mining activities will focus on three primary zones: Promontorio, San Miguel, and Eduwiges. Initial
production will prioritize the Promontorio zone to leverage extensive existing underground infrastructure
and advanced mine development. Development of the newly defined San Miguel zone is slated to
proceed concurrently, with a target to be fully ramped up by the end of H1 2027. The extraction will utilize
conventional sublevel long-hole open stoping in a retreat strategy, performed by specialized contract
miners. To optimize grade delivery, the Company will employ a stockpiling strategy for lower-grade
material.
Table 2: Production Schedule
Units
Y-1
Y1
Y2
Y3
Y4
Y5
Y6
Y7
Y8-9
LOM
Mill Feed
Milled (kt)
Kt
40
370
432
432
432
432
432
432
554
3,556
Ag Feed Grade
g/t
175.3
162.6
186.7
160.3
193.5
125.6
132.7
158.8
101.3
151.0
Au Feed Grade
g/t
0.06
0.17
0.21
0.22
0.13
0.15
0.10
0.13
0.10
0.15
Pb Feed Grade
%
0.25
0.50
0.73
078
0.92
1.57
1.15
0.83
0.43
0.85
Zn Feed Grade
%
0.28
0.46
0.75
1.88
1.21
1.92
1.85
1.18
0.68
1.10
Metal Recovered to Concentrate
Ag
Koz
188
1,624
2,178
1,871
2,258
1,465
1,548
1,853
1,516
14,502
Au
Koz
0.1
1.6
2.3
2.4
1.5
1.7
1.0
1.4
1.4
13.4
Pb
Mlbs
0.2
3.8
6.4
6.8
8.0
13.6
10.1
7.2
4.8
60.9
Zn
Mlbs
0.2
2.7
5.2
6.1
8.4
13.3
12.8
8.2
6.1
63.1
AgEq Produced
(1)
koz
198
1,818
2,534
2,346
2,821
2,377
2,308
2,416
1,950
18,768
Payable Metals
Ag
Koz
179
1,543
2,069
1,777
2,145
1,392
1,471
1,761
1,441
13,777
Au
Koz
0.0
1.0
1.6
1.7
0.7
1.0
0.3
0.7
0.5
7.4
Pb
Mlbs
0.1
2.5
4.9
5.3
6.5
12.1
8.6
5.7
2.9
48.6
Zn
Mlbs
0.0
0.0
0.4
0.5
0.7
1.1
1.0
0.7
0.1
4.4
AgEq Payable
(2)
koz
181
1,644
2,268
2,037
2,398
1,823
1,766
2,004
1,589
15,711
Units
Y-1
Y1
Y2
Y3
Y4
Y5
Y6
Y7
Y8-9
LOM
Notes:
1
.
AgEq Produced represents the total value of all recovered metals expressed in silver ounces. This is calculated by converting byproduct
metal production (gold, lead, and zinc) into silver ounces based on the relative value of their price assumptions compared to the silver price
assumption.
2
.
AgEq Payable represents the total value of all payable metals expressed in silver ounces. This is calculated by converting byproduct
payable metal (gold, lead, and zinc) into silver ounces based on the relative value of their price assumptions compared to the silver price
assumption.
Figure 2: Life-of-Mine Payable Revenue by Metal and Silver Equivalent Production
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/10393/292137_silvercofig2.jpg
The Cusi underground mine is located approximately 120 kilometre ("km") West from the city of
Chihuahua and 20 km south of Cuauhtemoc city. The location allows for access to an experienced
labour pool with a population of more than one million people. Ore will be transported from the mine via
30-tonne highway trucks to the Company's existing 1,200 tpd processing facility, located approximately
40 km from the mining areas. The mill utilizes a conventional comminution and flotation circuit designed
to produce a high-value bulk lead-silver concentrate. The project currently maintains constructed tailings
storage capacity for the first 12 months of production. Permitting is already in place for additional
capacity required by the end of 2027.
Figure 3 and 4 - Cusi Property Location (Left) and Property Claims (Right)
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/10393/292137_silvercofig3.jpg
Figure 5 - Cusi Mine Layout
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/10393/292137_67cbaf69f4928a63_005full.jpg
Figure 6 - Promontorio and San Juan Mine Design - Long Section View, Looking North
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/10393/292137_67cbaf69f4928a63_006full.jpg
Figure 7 - San Miguel Mine Design - Long Section View, Looking North
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/10393/292137_67cbaf69f4928a63_007full.jpg
Figure 8 - Eduwiges Mine Design - Long Section View, Looking North
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/10393/292137_67cbaf69f4928a63_008full.jpg
Forecast Operating Cost Estimates
Operating costs were estimated as a combination of historical operating costs at Cusi (based on data
from 2022 and 2023 operations at a reduced throughput), updated with new contractor rates for
development, reagent and consumable pricings, and benchmarked against comparable Mexican
operations.
Operating costs include a contingency of 5%.
Life-of-mine cash operating costs have been estimated at $76.15/t and all-in-sustaining-costs ("AISC")
are estimated at $26.75/AgEq oz.
Table 3: Operating Cost Estimates
Operating Costs
LOM Total ($M)
Unit Cost ($/AgEq oz)
Unit Cost ($/t)
Mining
$139.0
$9.12
$40.27
Processing
$80.2
$5.26
$23.23
General & Administrative
$31.2
$2.04
$9.03
Contingency (5%)
$12.5
$0.82
$3.63
Total Cash Operating Costs
$262.9
$17.24
$76.15
TC/RCs & Royalties
$4.35
$0.29
$1.26
Total Cash Costs
$267.2
$17.53
$77.38
Net Sustaining Capital Costs
$140.6
$9.22
$40.72
Total Site AISC
(1)
$407.8
$26.75
$118.13
Notes:
1
.
PEA AISC excludes exploration and corporate costs. AISC does include grade control and infill drilling.
Life-of-Mine Capital Summary
The initial net capital requirements are forecasted to be $19.2 M. This includes revenue contributions
from initial concentrate production during ramp-up. The initial construction capital estimate consists
primarily of mine development at both Promontorio and San Miguel, refurbishment of the existing 1,200
tpd mill, installation of a tailing's thickener for reduced water consumption, capitalized operating costs
during the ramp-up phase, miscellaneous mine and surface infrastructure upgrades, and working capital.
Working capital has been excluded from capital but included within the financial model.
Initial capital
costs include 25% contingency
.
Sustaining capital is estimated at $140.6 M over the life-of-mine, primarily related to ongoing
underground mine development and associated infrastructure, tailings expansions, underground grade
control drilling, and closure costs.
Sustaining capital includes an average of 22% contingency
.
Table 4: Life-of-Mine Capital Estimates
LOM Capital
Cost ($M)
Construction Capital
(1)
$47.5
Commissioning Revenue
(2)
($28.3)
Net Initial Capital
$19.2
Sustaining Capital
$109.3
Closure
$31.3
Net Sustaining Capital
$140.6
Total LOM Capital
$159.8
Notes:
1
.
Construction capital includes all capital and operating cost from initial restart works to achieving commercial throughput. This period is
forecasted until the end of Q1 2027. Concentrate production is planned to begin at the start of Q4 2026. Continued ramp up to full throughput
is completed by end of H1 2027.
2
.
Commissioning revenue is all revenue generated up to the end of Q1 2027.
Metal Price Assumptions
The base case utilizes fixed metal prices for gold, lead, and zinc. Silver uses a simplified silver curve
starting at $65/oz for 2026 and tapering off to a long-term price of $38/oz beginning in year 5. The
average life-of-mine realized price is $44.58/oz. The silver prices in the early years of the project are
based on the restart of production in late 2026, current spot prices and consensus price projections.
Base case silver prices are discounted on average approximately 13% below consensus pricing of 32
banks and financial institutions.
The upside case utilizes a fixed average silver price of $75.00/oz. Other metal prices remain unchanged
from the base case assumptions.
Table 5: Base Case Metal Price Assumptions
Life of Mine
2026
2027
2028
2029
2030+
Ag ($/oz)
$44.58
$65
$60
$55
$45
$38
Au ($/oz)
$3,000
$3,000
$3,000
$3,000
$3,000
$3,000
Pb ($/lb)
$0.91
$0.91
$0.91
$0.91
$0.91
$0.91
Zn ($/lb)
$1.29
$1.29
$1.29
$1.29
$1.29
$1.29
Forecast Return Estimates
The economic analysis outlines a base case after-tax Net Present Value ("NPV") of $104.1M at a 5%
discount rate with a payback of 0.9-years. The upside case outlines an after-tax NPV of $312.2M with a
payback of 0.5-years at the same discount rate.