Sonoro Announces Final Assay Results from 2020 Drilling Program

Drill Results

SONORO ANNOUNCES FINAL ASSAY RESULTS FROM 2020 DRILLING PROGRAM

VANCOUVER, Canada, January 19, 2021 – Sonoro Gold Corp. (TSXV: SGO | OTCQB: SMOFF | FRA: 23SP)

(“Sonoro” or the “Company”) is pleased to report the remaining assay results from its 2020 drilling

campaign at the Cerro Caliche gold project in Sonora, Mexico. The 2021 drilling program is currently

underway with approximately 50 additional RC and core holes expected to be completed by the end of

the first quarter. The latest assays further support the Company’s consideration of the viability for a bulk

mining heap-leach development proposal with a conceptual throughput of up to 20,000 tonnes per day

(tpd).

El Colorado Zone Enlarged

At the El Colorado gold mineralized zone, located in the southwestern region of the concession, four core

holes were drilled to test the periphery of the zone's intensely drilled higher grade gold shoots where drill

holes announced December 18, 2020 include:

• SCR-044 intercepted 12.19 m averaging 11.22 g/t Au, including 6.09 m averaging 21.58 g/t Au

• SCD-008 intercepted 11.7 m averaging 0.92 g/t Au, including 4.55 m averaging 1.84 g/t Au

Three of the four new holes successfully tested the southeastern and northwest periphery of the higher-

grade shoots:

• SCD-026 intercepted 8.4 m averaging 0.718 g/t Au

• SCD-027 intercepted 7.2 m averaging 0.601 g/t Au

• SCD-028 intercepted 6.0 m averaging 0.885 g/t Au

At the southeastern periphery, SCD-027 extended the shoots lengths by approximately 50 meters whereas

at the shoot’s northern periphery, SCD-028 intercepted three different mineralized intervals. SCD-028 is

located approximately 30 meters north of where previously announced drill hole SCD-016 also intercepted

several mineralized intervals including 11.25 meters averaging 1.08 g/t Au. Furthermore, the SCD-028

intercepts appear to be the western splay of the adjacent Guadalupe or Cabeza Blanca vein systems.

Another drill hole, SCD-025, tested the eastern edge of the higher-grade gold shoot and intercepted two

short, mineralized intervals.

Guadalupe Zone

At the Guadalupe gold mineralized zone, located in the western region of the concession, scout drill hole

SCD-029 intercepted 3.9 meters averaging 0.358 g/t Au, including 3.9 meters averaging 0.234 g/t Au. The

drill hole investigates the northernmost area of the Guadalupe zone and is approximately 250 meters

north of the previously announced SCR-030 which intercepted 22.86 meters averaging 0.725 g/t Au.

Additional drill holes are planned to determine the potential for Guadalupe to increase the project’s gold

mineralization.

Cabeza Blanca Zone Continues to Grow

At the Cabeza Blanca gold mineralization zone, located directly north of the El Colorado zone, core holes

SCD-030 and SCD-031 confirm the zone’s extension more than 50 meters to the north:

• SCD-030 intercepted 9.3 m averaging 0.719 g/t Au

• SCD-031 intercepted 15 m averaging 0.503 g/t Au

Veta de Oro – Abejas Zone

At the southeastern end of the Veta de Oro gold mineralized zone, four core drill holes, SCD-032, SCD-033,

SCD-034 and SCD-035, and two RC holes, SCR-156 and SCR-157, tested an area of vein stockwork and

confirmed narrowing vein zone in the covered area between the Veta de Oro zone and the Abejas zone,

located 500 meters to the south.

SCD-032 through SCD-035 were the final core drill holes of 2020 and are located directly south of drill hole

SCD-015 which, as announced on December 8, 2020, intercepted 16.25 meters averaging 0.741 g/t AuEq,

including 3.0 meters averaging 2.11 g/t AuEq. Management believes these drill holes establish the

potential for a higher-grade zone of gold mineralization to extend to the north approximately one

kilometer to El Rincon. In addition, the Company built roads and drill pads in preparation for the drilling

to test the north striking zone between El Rincon and Veta de Oro. Drilling at this very high potential zone

is currently under way with results expected by the end of February.

Table of Selected Core Drill Results: El Colorado, Guadalupe, and Cabeza Blanca

Cerro Caliche Project, holes composites with cutoff 0.15 Au g/t

Hole Target

From To Interval Au Ag AuEq

(meters) g/t g/t g/t

SCD-025 EL COLORADO 96.15 97.00 0.85 1.100 6.90 1.199

SCD-026 EL COLORADO

8.50 10.85 2.35 1.117 3.40 1.165

and 19.00 21.95 2.95 0.254 1.80 0.279

and 24.95 26.45 1.50 1.221 1.20 1.238

and 38.75 47.15 8.40 0.718 3.80 0.772

includes 40.70 42.75 2.05 1.563 5.00 1.634

includes 44.80 45.70 0.90 1.537 4.40 1.600

SCD-027 EL COLORADO

27.60 28.80 1.20 1.897 2.70 1.936

and 41.00 48.20 7.20 0.601 2.20 0.633

includes 42.15 43.95 1.80 1.512 4.60 1.578

and 91.80 93.00 1.20 2.765 3.70 2.818

SCD-028 EL COLORADO

62.00 66.80 4.80 0.507 4.40 0.570

and 77.10 81.50 4.40 0.626 2.90 0.667

and 118.30 124.30 6.00 0.885 5.00 0.926

SCD-029 GUADALUPE

13.00 16.90 3.90 0.358 0.40 0.363

and 21.50 22.50 1.00 1.206 1.50 1.227

and 29.55 33.45 3.90 0.234 1.10 0.250

SCD-030 CABEZA BLANCA

25.75 29.10 3.35 0.348 1.00 0.362

and 38.30 40.50 2.20 1.173 0.30 1.177

includes 38.30 39.60 1.30 1.816 0.40 1.822

and 43.40 52.70 9.30 0.719 3.20 0.764

includes 44.60 46.40 1.80 1.891 5.80 1.974

SCD-031 CABEZA BLANCA

14.05 20.75 6.70 0.296 0.30 0.300

and 46.50 49.50 3.05 0.465 0.30 0.469

and 52.10 67.10 15.00 0.503 3.00 0.546

and 93.45 97.55 4.10 0.701 4.20 0.761

True widths in the El Colorado holes have yet to be established, while the Guadalupe intersections are considered

true widths. Cabeza Blanca drill holes true widths are considered to be about 90% of reported drill length intervals.

Table of Selected Core & RC Drill Results: Veta de Oro and Abejas

Cerro Caliche Project, holes composites with cutoff 0.15 Au g/t

Hole Target

From To Interval Au Ag AuEq

(meters) g/t g/t g/t

SCD-032 VETA DE ORO 106.00 112.50 6.50 0.510 6.00 0.595

includes 107.50 108.25 0.75 1.787 11.70 1.954

SCD-033 VETA DE ORO 66.10 79.10 13.00 0.663 3.80 0.718

and 81.60 85.30 3.70 0.421 1.50 0.442

SCD-034 VETA DE ORO

33.60 38.50 4.90 1.221 18.50 1.488

includes 36.50 38.50 2.00 2.352 24.40 2.701

and 47.70 54.50 6.80 0.717 17.00 0.960

and 63.40 66.50 3.10 0.602 0.40 0.607

SCD-035 VETA DE ORO and 62.55 75.30 12.75 0.545 1.30 0.564

SCR-156 ABEJAS 59.44 62.48 3.04 0.398 4.30 0.459

SCR-157 ABEJAS 76.20 80.77 4.57 0.603 16.00 0.833

Veta de Oro drill intersections are considered to be near true width drill intersections to reported drill length

intersection lengths.

Japoneses Zone Infill Drilling

The following assay results are the final six of 33 RC holes drilled during the 2020 drill program. A total of

70 holes have been drilled within the Japoneses zone (which now includes Boluditos and Chinos

NW zones) as the Company works to define the 1,300 meter long by 400 meter wide zone’s shallow oxide

gold mineralization. These holes are intended to infill gaps in the drill pattern. Selected RC drill hole

Intercepts from the Japoneses mineralized zone include SCR-151 with 27 meters averaging 0.694 g/t Au

which is a wide addition to the zone’s near surface mineralization. A high-grade vein with a width of 3.05

meters averaging 3.355 g/t Au, which was intercepted within the 27-meter interval, is interpreted to be a

section of the main Japoneses vein. Intersections in the Japoneses zone appear to have true widths

approximately 15 percent less than reported as drill length intersections.

Table of Selected RC Drill Results: Japoneses

Cerro Caliche Project, holes composites with cutoff 0.15 Au g/t

Hole Target

From To Interval Au Ag AuEq

(meters) g/t g/t g/t

SCR-150 JAPONESES

0.00 6.10 6.10 0.319 2.30 0.353

and 51.82 56.39 4.57 0.311 0.20 0.313

and 64.01 67.06 3.05 0.222 0.30 0.227

SCR-151 JAPONESES

6.10 33.53 27.43 0.694 1.40 0.714

includes 27.43 30.48 3.05 3.355 7.60 3.464

and 48.77 51.82 3.05 0.321 0.40 0.327

SCR-152 JAPONESES 38.10 41.15 3.05 0.283 0.80 0.294

and 47.24 50.29 3.05 0.428 1.90 0.456

SCR-153 BUENA VISTA

13.72 21.34 7.62 0.229 0.40 0.234

and 32.00 50.29 18.29 0.372 0.70 0.382

includes 42.67 44.20 1.53 1.609 2.40 1.643

Cerro Caliche Project, holes composites with cutoff 0.15 Au g/t

Hole Target

From To Interval Au Ag AuEq

(meters) g/t g/t g/t

SCR-154 JAPONESES 54.86 62.48 7.62 0.187 0.30 0.192

and 88.39 94.49 6.10 0.507 0.40 0.513

SCR-155 JAPONESES

0.00 3.05 3.05 0.195 1.40 0.214

and 70.10 74.68 4.58 0.632 1.50 0.653

includes 70.10 71.63 1.53 1.576 2.80 1.616

and 99.06 105.16 6.10 0.462 2.10 0.491

Drill collar locations, azimuths and dips for the drill holes included in this release are provided in the table

below and have been posted to the Company’s website for all drill holes.

Drill Collar Locations (NAD 1927 UTM Zone 12N)

Drill Hole Zone Easting Northing Elevation Depth (m) Dip Azimuth

SCR-150 JAPONESES 536812 3365017 1370 82.30 -45 233

SCR-151 JAPONESES 536840 3365036 1355 106.68 -45 234

SCR-152 JAPONESES 536858 3365067 1347 131.06 -45 234

SCR-153 BUENA VISTA 536582 3365441 1262 97.54 -45 234

SCR-154 BUENA VISTA 536646 3365471 1260 94.49 -45 233

SCR-155 JAPONESES 536886 3365103 1345 121.92 -45 235

SCR-156 ABEJAS 537198 3365552 1393 100.58 -50 237

SCR-157 ABEJAS 537178 3365631 1407 131.06 -45 233

SCD-025 EL COLORADO 536198 3364517 1245 100.15 -62 194

SCD-026 EL COLORADO 536174 3364466 1241 89.85 -73 225

SCD-027 EL COLORADO 536171 3364449 1240 103.10 -60 188

SCD-028 EL COLORADO 536142 3364584 1304 143.40 -77 218

SCD-029 GUADALUPE 535983 3365201 1348 90.50 -45 260

SCD-030 CABEZA BLANCA 536102 3365255 1352 90.20 -45 240

SCD-031 CABEZA BLANCA 536109 3365304 1326 109.95 -45 295

SCD-032 VETA DE ORO 537095 3365742 1413 149.10 -60 235

SCD-033 VETA DE ORO 536982 3365838 1413 85.00 -65 235

SCD-034 VETA DE ORO 537026 3365754 1410 87.90 -55 235

SCD-035 VETA DE ORO 536899 3365898 1406 101.10 -70 241

Mel Herdrick, Sonoro’s VP of Exploration, commented, “The focused drill program of 2020 was very

successful in further outlining additional gold mineralization, part of which contains significantly higher

gold grades. We have a substantial amount of additional drilling planned to fully define the project’s

considerable potential. Our plan is to drill up to 50 more holes as part of this effort by the end of March

of this year, which we expect will be in time to contribute further to the updated resource estimate to be

prepared by Micon International.”

Kenneth MacLeod, Sonoro’s President and CEO, added, “I am very happy to report at the conclusion of the

2020 drilling program that the program’s goals, as they relate to the overall development of production

at Cerro Caliche, have been achieved and that the entire campaign to begin gold production at Cerro

Caliche remains on track.”

John Darch, Sonoro’s Chairman, stated, “From the outset, our pledge to shareholders has been to begin

producing gold at Cerro Caliche as quickly as was reasonably achievable. Our overall objective was, and

continues to be, to generate free cash flow to be used to explore and define Cerro Caliche’s considerably

larger mineralized potential, thereby shaping the Company’s future growth plans. This way we hope to

minimize the need to issue additional shares and, thereby, avoid diluting our existing shareholders’

interests in the Company, as we fund future exploration and development.”

Quality Assurance/Quality Control (“QA/QC”) Measures and Analytical Procedures

Drill samples are collected with an airstream cyclone and passed into a splitter that divides each sample

into quarters. The quartered samples are then bagged and sealed with identification. The sample group

has blanks, standards and duplicates inserted into the sample stream.

Bureau Veritas (BV) collects the samples and transports them directly to the preparation laboratory in

Hermosillo, Sonora. At the laboratory, part of each sample is reduced through crushing, splitting and

pulverization. About 200 grams are sent by BV to their Vancouver, Canada laboratory and dissolved in

aqua regia for multi-element ICP analysis, including silver. Of these samples, 30 grams undergo fire assay

in Hermosillo for gold by reducing the fire assay to a concentrated button of material that is dissolved in

acids and the gold content determined by atomic absorption.

No QA/QC issues were noted with the results received from the laboratory.

Geologic Description

Cerro Caliche is located 45 kilometers east southeast of Magdalena de Kino in the Cucurpe-Sonora Mega-

district of Sonora, Mexico. Multiple historic underground mines were developed in the concession

including Cabeza Blanca, Los Cuervos, Japoneses, Las Abejas, Boluditos, El Colorado, Veta de Oro and

Espanola. Mineralization types of the Cucurpe-Sonora Mega-district include variants of epithermal low

sulfidation veins and related mineralized dikes and associated volcanic domes. Local altered felsic dikes

cut the mineralized meta-sedimentary rock units and may be associated with mineralization both in the

dikes and meta-sedimentary rocks.

Host rocks include Jurassic-Cretaceous meta-sedimentary rock units including argillite, shale, quartzite,

limestone, quartz pebble conglomerate and andesite. Younger intrusive rock consisting of medium

coarse-grained granodiorite-granite is present in the westerly parts of the concessions near the historic

Cabeza Blanca Mine. It is apparent that veining cuts and pervasively alters the intrusive stock. Rhyolite

occurs in irregular bodies distributed in higher elevations in the northerly part of the concession, including

the Rincon area, where it occurs as flows, sills, dikes and rhyolite domes. Part of the rhyolite is mineralized

and appears to be related to epithermal gold mineralization throughout the property.

Qualified Person Statement

Stephen Kenwood, P.Geo., a Director of Sonoro, is a Qualified Person within the context of National

Instrument 43-101 (NI 43-101) and has read and approved this news release. Readers are cautioned that

the presence of mineralization on historic mines adjacent to or on Cerro Caliche is not necessarily

indicative of gold mineralization in the concessions held by the Company.

About Sonoro Gold Corp.

Sonoro Gold Corp. is a publicly listed exploration and development company with a portfolio of

exploration-stage precious metal properties in Sonora State, Mexico. The Company has highly

experienced operational and management teams with proven track records for the discovery and

development of natural resource deposits.

On behalf of the Board of Sonoro Gold Corp.

Per: “Kenneth MacLeod”

Kenneth MacLeod

President & CEO

For further information, please contact:

Sonoro Gold Corp. - Tel: (604) 632-1764

Email: [email protected]

Forward-Looking Statement Cautions: This press release contains certain "forward-looking statements" within the meaning of Canadian

securities legislation, relating to, among other things, the Company's plans for the exploration, development and operations at the above-

described Cerro Caliche Concessions, located in the municipality of Cucurpe, Sonora, Mexico, including statements regarding the

Company’s plans for additional drilling, an anticipated update of the current resource estimate for Cerro Caliche, the Company’s plans for

a proposed 20,000 tonne per day HLMO, including the potential for revenue-positive operations, the hope for results of continued

exploration drilling, including to test high-grade targets, and other material conditions set out above on which the Company’s

development plans are dependent. Although the Company believes that such statements are reasonable based on current circumstances,

it can give no assurance that such expectations will prove to be correct. Forward-looking statements are statements that are not historical

facts; they are generally, but not always, identified by the words "expects", "plans", "anticipates", "believes", "intends", "estimates",

"projects", "aims", "potential", "goal", "objective", "prospective" and similar expressions, or that events or conditions "will", "would",

"may", "can”, "could" or "should" occur, or are those statements, which, by their nature, refer to future events. The Company cautions

that forward-looking statements are based on the beliefs, estimates and opinions of the Company's management on the date the

statements are made and they involve a number of risks and uncertainties, including the possibility of unfavourable exploration and test

results, unfavourable results of the contemplated PEA of the Cerro Caliche project, the lack of sufficient future financing to carry out

exploration and development plans and unanticipated changes in the legal, regulatory and permitting requirements for the Company’s

exploration programs. There can be no assurance that such statements will prove to be accurate, as actual results and future events

could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-

looking statements. The Company disclaims any intention or obligation to update or revise any forward-looking statements, whether as

a result of new information, future events or otherwise, except as required by law or the policies of the TSX Venture Exchange. Readers

are encouraged to review the Company’s complete public disclosure record on SEDAR at www.sedar.com.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture

Exchange) accept responsibility for the adequacy or accuracy of this release.