Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

SGML.V ·

Sigma Lithium Announces Exceptional PEA Results Supporting Doubling Planned Production Capacity to 440,000tpa (66,000 LCE) ______________________________________________________________________________________________________________

Economic Studies

SIGMA LITHIUM ANNOUNCES EXCEPTIONAL PEA RESULTS SUPPORTING

DOUBLING PLANNED PRODUCTION CAPACITY TO 440,000tpa (66,000 LCE)

______________________________________________________________________________________________________________

PHASE 2 PRODUCTION HIGHLIGHTS

 Project’s near-term production capacity of battery grade high-purity green lithium will be potentially

doubled:

o Production is planned to increase from 220,000 tpa (33,000 LCE) planned for 2022 in Phase 1, to

440,000 tpa (66,000 LCE), within approximately one year.

o Phase 2 production has a projected life of mine of approximately 13 years: vertically integrated to

Sigma’s second deposit, Barreiro with 20.5 Mt of measured & indicated high-grade and high-purity

lithium resources at 1.43% Li2O.

o Low-risk execution strategy: Phase 2 construction is planned to start once Phase 1 concludes

commissioning and ramps up production in 2022.

o The Company has significantly advanced multiple Project workstreams with the objective of

preparing for Phase 2 production after 2023.

PHASE 2 FINANCIAL HIGHLIGHTS

 Phase 2 has the potential to more than double total NPV of the Project to US$844 million:

o NPV of Phase 2 Production US$449 million.

o Low initial capital expenditures of US$44.5 million.

 Phase 2 after-tax cash flow generation during 13 years is projected as follows:

o Net revenue of US$2.1 billion (annualized US$165 million).

o After Tax Free Cash Flow of US$ 766 million (annualized US$60 million).

o EBITDA of US$1 billion (annualized US$83 million).

o IRR of 208%.

 Located close to Atlantic emerging supply chain for electric vehicles in North America and Europe, Phase 2

would enable Sigma to continue to be amongst the lowest cost producers in the industry.

o PEA projects Phase 2 average total cash cost to be US$256/t (FOB Plant, life of mine) and US$360/t

(CIF China Port, life of mine).

PHASE 1 CONSTRUCTION UPDATE

 All Detailed Engineering and Pre-Construction workstreams continued to advance to achieve production in

the third quarter of 2022. https://vimeo.com/554389108 to Video with 3D rendering of Production Plant

o Construction site early works are ongoing (clearing and grubbing, laydowns & topsoil removal).

o Concluded all field Pre-Construction activities for the Production Plant.

o Completed trade-off studies for the optimization and expandability/scalability of the overall plant

design, evaluating multiple design options, performing tests and analysis to select the preferred

option.

o Concluded the definition of the streamlined scope and design of the non-process, non-plant

infrastructure (building infrastructure).

o Completed several critical workstreams involved in the Pre-Construction of the Phase 1 Mine within

the scheduled and budgeted parameters, including all field-based activities required for the

geotechnical as well as hydrogeological validations.

____________________________________________________________________________________________________

VANCOUVER, British Columbia, June 2, 2021 (GLOBE NEWSWIRE) -- Sigma Lithium Resources Corporation (“ Sigma” or the

“Company”) ( TSX-V: SGMA ) ( OTC- QB: SGMLF ) is pleased to announce the exceptional results of a Preliminary Economic

Assessment (the “PEA”) for an expansion of its Grota do Cirilo Project (the “ Project”), doubling its annual production capacity

of battery-grade, high-purity, environmentally sustainable 6% lithium concentrate (“ Green Battery Grade Lithium

Concentrate”) to approximately 440,000 tpa (66,000 LCE).

The expansion of Project achieves significant operational economies of scale resulting from adding a second environmentally

friendly dense media separator processing line train to its digitally automated production plant (the “ Production Plant”). The

second line is expected to produce an average of 222,000 tpa (33,000 LCE) of Battery Grade Green Lithium Concentrate

(“Phase 2”), doubling the initial planned annual production capacity of 220,000tpa (33,000 LCE) (“ Phase 1”).

Phase 1 is described in the Sigma’s technical report titled “Grota do Cirilo Lithium Project, Ara çuaí and Itinga Regions, Minas

Gerais, Brazil, National Instrument 43-101 Technical Report on Feasibility Study Final Report” dated October 18, 2019 (the

“2019 Feasibility Study Report”).

The exceptional PEA results demonstrate the cost benefit of vertically integrating the second production line and utilizing as a

feedstock spodumene ore from the Project’s second deposit Barreiro (the “Second Deposit” or “Barreiro”), mining an average

of 1.68Mt per year during 12.7 years of mine life. Barreiro is a high-purity, high-grade lithium deposit, with 20.485Mt of

measured & indicated mineral resources at 1.43% Li 2O and 1.909Mt of inferred mineral resources and shallow, near surface

mineralization ideal for open pit mining. The Second Deposit’s mineral reserve is expected to be declared later this quarter

when the ongoing pre-feasibility study (“ PFS”) is completed.

The PEA projects capital expenditures of US$44.5 million (year 0) including plant and mine construction, based on an optimized

mine plan. Incremental expenditures of US$28.9 million (additional mine stripping on year 5) and US$9.6 million (additional

mine stripping on year 6) is expected to be covered by the Company’s internal cash flow generation. As Phase 2 construction

is planned sequentially to the commissioning and production ramp up of Phase 1, the Company is expected to be fully

operational with Phase 1 by the time Phase 2 is commissioned. Therefore, additional working capital for commissioning of the

second DMS line as well as certain deferred capital expenditures may potentially also be covered by the internal cash flow

generation of the business.

According to the PEA, Phase 2 could potentially double total estimated NPV of the Project to US$844 million:

o NPV of Phase 2 Production is estimated to be US$449 million by the PEA.

o NPV of Phase 1 Production is estimated to be US$395 million by the 2019 Feasibility Study Report ( calculated

with price curves starting from US$650/t in 2021, below current market prices at CIF China port, and operational

expenditures reductions limited by the sensitivity analysis in 2019 to be 20%, despite Brazilian currency

devaluation since 2019 of approximately 35% )

Barreiro, the Project’s second deposit, has a similar exceptional mineralization to the Project’s first deposit, Xuxa, with large

crystals of coarse spodumene. As a result, the lithium achieves outstanding recoveries in an environmentally friendly DMS

plant, with similar flowsheet (and capital costs) to the first production line, without requiring a significantly more capital-

intensive flotation process.

During Detailed Engineering for Phase 1, the Company evaluated operational and capital expenditure trade-offs to be achieved

in the expansion of the Production Plant capacity, including design features to allow for the seamless incorporation of a second

production line.

Metallurgical HLS tests performed on the spodumene ore for Phase 2 in sizes of 6.3mm and 10mm achieved excellent lithium

recoveries of 70.2% and 66.1%, respectively, producing a 6% Li 2O battery-grade spodumene concentrate within the highest

levels of specifications demanded by the chemical lithium market without the use of flotation or hazardous chemical reagents,

in the concentration process. This is consistent with Sigma’s intention to continue to process its lithium ore in a “green”

environmentally friendly and sustainable manner .

The Company has been working with SGS and Primero to prepare a PFS for the Phase 2 production, targeting its completion in

June 2021, further continuing towards feasibility analysis in the second half of 2021. The Company and Primero completed all

the metallurgical and variability DMS pre-feasibility test work at SGS laboratories.

The Project is located in one of the world’s largest mining provinces in southeast of Brazil: with full mining infrastructure and

highways linking the Project to a commodities shipment capable port. Site infrastructure has been mostly in place and is

currently being upgraded for Phase 1 production. The Project is powered by 100% clean energy: transmission towers and lines

on site link the Project to a hydroelectricity plant 50km away.

SIGMA PHASED PRODUCTION APPROACH FOR THE PROJECT AND COMMERCIAL STRATEGY

As a result of the substantial size of its mineral resources, the Company has sub-divided the development of the Project into

an incremental and phased build-out.

Sigma is working to advance Phase 2 to a construction ready status by the end of 2021 or early 2022. Phase 2 construction is

projected to commence once the commissioning and production ramp up of Phase 1 is completed, which is expected in the

third quarter of 2022.

This phased approach to development of the Project increases financial flexibility and reflects the Company’s ethos and

discipline in managing construction risk, while seeking to create substantial shareholder value. It also reduces commercial risk

by aligning commercial integration of the Project’s production growth profile with the demand of its customers in the lithium-

ion battery supply chain.

As a result of the high quality and low impurities of its lithium products, the Company has experienced significant commercial

success with various customers in the electric vehicle supply chain. As a result, the Company made a decision to accelerate the

required studies for the development of Phase 2, to potentially respond to a significant increase in demand from its customers,

following the significant improvement in the outlook of global demand for ESG-sustainable lithium products.

By demonstrating its ability to expand production in the near term, the Company seeks to take advantage of the current strong

demand, and solidify its unique commercial advantage in delivering environmentally, socially sustainable and low carbon high

purity lithium products to like-minded cathode and battery producers.

The technical report for the PEA will be filled on SEDAR (and will also be available at www.sigmalithiumresources.com within

45 days of this news release. Readers are encouraged to read the technical report in its entirety, including all qualifications

and assumptions related to the PEA results announced in the news release.

FIRST QUARTER 2021 RESULTS: PHASE 1 CONSTRUCTION & PROJECT DEVELOPMENT UPDATE

The Company has reported unaudited financial and operating results for the first quarter ended March 31, 2021 (“ 1Q 2021”).

Overall, the Company made significant progress towards construction, despite the circumstances created by the COVID-19

pandemic.

Highlights of Phase 1 construction update include:

 All Detailed Engineering and Pre-Construction workstreams continued to advance to achieve production in the third

quarter of 2022.

o At the end of Detailed Engineering, the Project will move to the Implementation/Deployment Stage (FEL 3 /

Class 3) in the third quarter of 2021, with increased accuracy from the capital estimates included in the

Feasibility Study Report.

o Strict COVID-19 health and safety protocols are in place. Without any cases of COVID-19 reported at site

since April 30, 2021.

 Construction site early works are ongoing (clearing and grubbing, laydowns & topsoil removal):

o Followed by additional topsoil removal and foundation preparations, once results and geotechnical

modelling of Production Plant foundation are concluded.

 Concluded all field Pre-Construction activities for the Production Plant.

o Primero conducted a review of the current designs, assessing the impact on the foundation design and

earthwork quantities, based on the geotechnical assessment for the civil engineering and concluded that the

soil condition does not create any risk for construction of the foundations of the Production Plant.

 Completed trade-off studies for the optimization and expandability/scalability of the overall plant design, evaluating

multiple design options, performing tests and analysis to select the preferred option.

o Expansion design features are being determined in order to allow for the incorporation of a second

production line for Production Phase 2.

 Concluded the definition of the streamlined scope and design of the non-process, non-plant infrastructure (building

infrastructure).

 Completed several critical workstreams involved in the Pre-Construction of the Phase 1 Mine within the scheduled

and budgeted parameters.

o This includes all field-based activities required for the geotechnical validation at detailed engineering level,

as well as critical field work of hydrogeological validation.

 All remaining state permits required to commence construction are forecasted to be issued by the third quarter of

2021.

Highlights of ESG:

 Significantly advanced the life cycle analysis and carbon credits audit workstreams, planning to publish results in the

third quarter of 2021, including more information on its carbon in-setting and offsetting strategy.

 Continued to progress on the creation and structuring of an independent agency for private investment promotion

and economic diversification of the region (“ Investment Agency”), with institutional support from the development

bank of the state of Minas Gerais (“ BDMG”), from the secretary of special development projects (“ INDI”) and from

the Mayors of the two municipalities.

 Expanded humanitarian relief during the months of COVID-19 pandemic for the population living in extreme

vulnerability in the region, as follows:

o Distributed 1,200 basic food baskets in two months, feeding approximately 2,400 people per month.

o Agreed to extend the initiative in a collaboration with Rotary Club, distributing an additional 1,000 food

baskets (feeding an additional 4,000 people).

o Repeated COVID-19 prevention initiatives from March 2020, and distributed 12,000 units of hospital

disinfectant, as well as 2,400 hand sanitizers “family size”, totaling 840 kg of the product.

o Initiatives funded at cost as a result of financial sponsorship from Sigma’s key shareholders and stakeholders.

Corporate:

 As at the date of this MD&A, the Company has $41.3 million (US$33.6 million) in cash and cash equivalents, out of

which approximately $33.8 million (US$28 million) is held in a construction segregated savings account.

o Additionally, it has an undrawn credit line balance of US$4,037,150 under the US$5,000,000 unsecured

revolving credit facility (the “A10 Credit Facility”)

 The Company has announced that it is considering a potential listing of the Common Shares in a major U.S. stock

exchange market with a view to increasing access to U.S. capital markets and enhancing overall shareholder value.

 Consistent with its retention policies to manage human capital as well as with its ethos of aligning incentives amongst

all stakeholders and shareholders, most of the compensation of the Company’s key personnel is equity based.

o To that regard, the Company grated an aggregate of 996,333 Restricted Share Units to officers and an

aggregate of 385,000 Restricted Share Units to key employees and consultants. As per the ESOP, Ana Cabral-

Gardner and Calvyn Gardner were not awarded equity compensation.

Calvyn Gardner, Sigma CEO said that “ We continue to progress updating the current Feasibility Study Report with the pre-

feasibility for the Phase 2, which would be fully integrated into the production complex for the Phase 1, currently in pre-

construction. The previous work undertaken when completing our 2019 Feasibility Study Report, as well as detailed engineering

phase of pre-construction for Phase 1, means that substantial plant engineering design as well as mining cost databases are

available to support the technical studies required for this update, expediting and de-risking its execution.”

Ana Cabral-Gardner, Sigma President and Chief Operating Officer stated that “The doubling of Sigma’s near-term planned

capacity to 66,000 LCE, with low additional capex has the potential to significantly transform our scale and relevance. It further

increases our uniqueness as a global supplier of environmentally sustainable green lithium concentrate, while consolidating

our strategic importance upstream as a source of high-purity green lithium products for our current and new customers, as

they advance their plans for cathodes and battery cell production facilities in Europe and the United States, effectively building

a sizable Atlantic lithium supply chain”.

Figure 1a: Plant 3D layout of the industrial complex and production facility for Phase 1 and Phase 2

Figure 1b: Plant 3D layout of the industrial complex and production facility for Phase 1 and Phase 2

1 - SUMMARY OF PROJECT FINANCIAL PERFORMANCE RESULTS

1.1 Project Economics

An economic analysis for Phase 2 was developed using the discounted cash flow method and was based on the data and

assumptions for capital and operating costs for mining, processing and associated infrastructure. The basis for forecasted

spodumene concentrate lithium pricing was provided by Roskill’s arm’s length price curve with an internal adjustment starting

with 2022 price of US$750/t (below current 2021 spot market). Although approximately 70% of the Company’s operational

costs are incurred in Brazilian reais, the assumptions were fixed in USD, the base currency for the financial model. Key

assumptions and results of the economic evaluation are displayed in the tables 1 and 2 below .

Table 1.1.1: Financial Results Summary for Phase 2 During the Estimated Life of Mine

Financial Summary Unit Total

Net Present Value (NPV 8%) After-Tax US$ M $ 449

Internal Rate of Return (IRR) After-Tax % 208%

After-Tax Payback Period Years 0.4

Capital Intensity (Initial Capex/ Annual Production) US$ per tonne $200 per tonne

NPV: Capex (ratio) Ratio X:1 10:1

Table 1.1.2: Key Assumptions Utilized in the Project Economics

Assumptions Unit Total

Annual Lithium Concentrate Production at 6% tonnes 222,147

Project Estimated Life (Integrated Mine/Plant) years 12.7

Discount Rate % 8

Total Royalty (1) % 3

Average Corporate Tax (2) % 15.3

CAPEX

Year 0 (plant construction and starter mining pit) US$ M 44.5

Year 5 (pit expansion) US$ M 28.9

Year 6 (pit expansion) US$ M 9.7

OPEX

Average total cash cost (FOB Plant) US$/t 256

All-in sustaining cost (“AISC”) CIF China US$/t 360

Average Selling Price US$/t 750

(1) CFEM and NSR#1 Royalties

(2) Sudene Corporate Tax Benefit During 8 first years. 34% for the following years

Table 1.1.3: Phase 2 Estimated Revenue, Operating Costs and EBITDA

Production: Total tonnes of lithium concentrate 2,870,444 tonnes

Average Price for project life $750/t

Annualized

US$ M

Total

US$ M

Gross Revenue $ 170 US$ 2,153

Less: Total Royalties ($5) ($61)

(-) CFEM ($3) ($43)

(-) Net Smelter Royalties ($1) ($18)

Net Revenues $165 $2,092

Less: Site Operating Costs ($84) ($1,066)

(-) Mining ($45) ($571)

(-) Processing ($12) ($156)

(-) Selling, General & Administration ($1) ($8)

(-) Transportation Costs ($24) ($299)

(-) Depreciation ($2) ($32)

EBIT $81 $1,026

% EBIT Margin 49% 49%

(+) Depreciation $2 $32

EBITDA $83 $1,058

% EBITDA Margin 51% 51%

(-) Taxes ($16) ($203)

(+/-) WC ($0) ($3)

(-) Capex ($7) ($85)

After-Tax Free Cash Flow $60 $767

% Margin 37% 37%

1.2 - Capital and Operating Costs

SGS and GE-21 completed the Class 5 estimate (+/- 30%) of the capital and operating costs, incorporating engineering from

the ongoing detailed engineering and FEED (front end engineering design) of Sigma’s Phase 1 Production Plant. The Capex has

been prepared to reflect optimized site layouts, mine scheduling, plant and equipment design and installation. Phase 2

development significantly leverages the Production Plant infrastructure that will be constructed for Phase 1. Site infrastructure

has been mostly in place (Sigma’s assets are from a brownfield project) and is currently being upgraded for Phase 1.

Operating cost estimates were provided by GE-21 and are based on an owner-operated model and have an accuracy of +/-30

%. The crushing contracting, substation rental, mobile equipment rental and product transport operating costs were

incorporated in the overall operating cost.

The cash operating costs were developed based on third party contract mining and outsourced crushing, as well as on the

Phase 2 Plant processing cost. The Phase 2 Production is forecasted to have very low operating costs at US$256 per tonne of

concentrate as a result of its high grade, high DMS recoveries, low levels of impurities, low cost of electricity and general low

country costs. Table 1.2.1 shows the anticipated average operating costs over the LOM. Table 1.1.3 presents the forecast

revenue and costs on both a total and average LOM basis.

Table 1.2.1: Operating Cost Estimate

Cost Category

LOM Average

US$/t

Mining $ 199

Processing 54

SG&A 3

Sub-Total $ 256

Transportation by Truck Mine to Port 34

Shipping to China Port (average) 70

Sub-Total 104

Total $ 360

The CAPEX has been prepared to reflect optimized site layouts, mine scheduling, plant and equipment design, supply and

installation. Phase 2 development significantly leverages the plant infrastructure that will be constructed for Phase 1. Site

infrastructure has been mostly in place (Sigma’s assets are from a brownfield project) and is currently being upgraded for

Phase 1.

The Company has evaluated operational and capital expenditure trade-offs to be achieved as a result of possible design

alternatives for the crushing circuit to be installed at the Production Plant. These trade-offs aim to further de-risk and optimize

the construction of the Production Plant. The scalability of the Production Plant was also studied to determine expansion

design features to allow for the incorporation of a second production line for Phase 2 high-grade green lithium production.

The total initial development CAPEX for Phase 2 is estimated to be US$ 44.5 million. The estimate is detailed in Table 1.2.2 and

includes processing, mine equipment purchases, infrastructures, contingency and other direct and indirect costs. Incremental

expenditures of US$28.9 million (additional waste mine stripping in year 5) and US$9.6 million (additional waste mine stripping

in year 6) can be funded by internal cash flow generation.