Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

SGD.TO ·

Snowline Gold Drills 617.6 m at 1.7 Grams per Tonne Gold From Surface, Including 3.24 Grams per Tonne Gold Over 202.0 M, Showcasing Strong Consistency of Valley Deposit, Rogue Project, Yukon

Drill Results

Snowline Gold Drills 617.6 m at 1.7 Grams per Tonne Gold From

Surface, Including 3.24 Grams per Tonne Gold Over 202.0 M,

Showcasing Strong Consistency of Valley Deposit, Rogue Project,

Yukon

• Key Infill Holes Deliver: Hole V-24-119 intersects 617.6 m at 1.68 g/t Au from

bedrock surface at 2.4 m downhole, including 202.0 m at 3.24 g/t Au, highlighting

along with other holes consistency of strong, near-surface mineralization across largest

gaps in previous drilling

• Updated Mineral Resource Estimate Forthcoming:Valley MRE to be updated in first

half of 2025, following a 90% increase in total drilling (53 km vs 28 km in 2024)

• Rapid Project Advancement: Work underway on first-ever Preliminary Economic

Assessment for Valley deposit, set to highlight potential economics of large, low strip,

front-heavy gold system.

V ANCOUVER, BC / ACCESS Newswire / March 4, 2025 / SNOWLINE GOLD CORP

(TSXV:SGD)(OTCQB:SNWGF) (the "Company" or "Snowline") is pleased to announce

additional drill results from its 2024 drill campaign on the Valley deposit, Rogue Project, Yukon.

At Valley, holes V-24-119 through V-24-122 returned intervals of strong gold mineralization

from key drill coverage gaps at Valley, showcasing continuity of Valley's high-grade, near-

surface core zone and further derisking the deposit. Additional holes V-24-123 and V-24-124

returned zones of low-grade mineralization in large step-outs to the southeast of the existing

Mineral Resource Estimate (MRE). Together, these results and previous 2024 drill results will

help to inform an updated MRE for Valley anticipated in the coming months. The Company has

also initiated work on a Preliminary Economic Assessment (PEA) of Valley based on all drilling

to date, engaging SRK Consulting (Canada) Inc and additional independent contractors to

conduct the study.

Table 1 - Highlight summary of Snowline's latest assay results; see Table 2 for details. Note

that the interval reported in V-24-119 comprises two closely spaced mineralized intervals along

with the low-grade 12.0 m interval in between. *Interval widths reported.

"Today's excellent drill results come on the heels of Snowline's fourth anniversary as a company-

we commenced trading on March 1, 2021," said Scott Berdahl, CEO & Director of Snowline.

"At that time, what is now the Valley deposit was a grassroots, greenfield target: an outcrop chip

sample of 4.2 grams per tonne gold over 4.7 m[i]. Snowline drilled the first ever holes at Valley in

September 2021. The speed and efficiency with which we have advanced Valley from that

outcrop sample to a significant gold deposit since is a testament to many of the same qualities

that we feel would make for a robust future gold mine, namely the three-dimensional consistency

of high-grade, non-refractory gold mineralization beginning at surface. We are excited to

continue our rapid advancement of Valley with an updated MRE along with a PEA to quantify

the compound effects of these positive attributes on potential future economics.

"We are also looking forward to another big season in 2025, with five drills currently on site and

ready to commence a program of district-scale exploration alongside advancement and potential

expansion of Valley, commencing in mid-May. The details of this program will be outlined in a

future release."

V ALLEY DRILLING, ROGUE PROJECT

Figure 1 - Plan map of drill results on the Rogue Project's Valley deposit, highlighting

current results in drill holes V-24-119 through V-24-124. Past analytical results are faded.

Roughly 53 km of drilling to date has revealed a large, continuous and relatively high-grade near

surface ore body at Valley. The Company is working on an updated MRE for the Valley deposit

as well as its first-ever PEA.

The six holes reported herein from Valley primarily target gaps in previous drilling, with V-24-

119 and 120 collared in the largest gaps remaining in the grid covering the high-grade core of the

Valley deposit. V-24-123 and 124 are drilled as step-outs to the southeast. The results continue to

build on the Company's understanding of the Valley deposit through de-risking and potential

expansion.

Roughly 25,000 m were drilled at Valley in 55 holes in 2024 - nearly double the amount of

drilling (27,911 m) used to inform the Company's initial MRE for Valley. The results of this

drilling will be used to produce an updated MRE on the Valley deposit in H1 of 2025, as well as

to inform a PEA for Valley that is currently underway.

Figure 2 - Cross-section A-A', showing V-24-119 & 120 in the context of the initial Valley

MRE block model and MRE-constraining revenue factor 0.72 pit shell. The underlying Valley

block model has not been updated to reflect the current results, nor any results to date from 2024.

Blocks shown outside of the current pit shell constraint are not included in the initial MRE for

Valley. Areas without blocks have not been modelled and were assumed as nil for the initial

Valley MRE.

Hole V-24-119

V-24-119 infills a 130 m gap along section between previous holes V-24-071 and V-22-029. It

intersected primarily coarse-grained granodiorite. From bedrock surface at 2.4 m downhole, the

hole returned an interval of 543.1 m averaging 1.80 g/t Au, including 202.0 m at 3.24 g/t Au

from 96.5 m downhole. A 19.5 m section from 210.0 m downhole averages 5.68 g/t Au (Table 2).

Twelve metres below this interval, a second mineralized interval averaged 1.03 g/t Au over 53.0

m from 557.5 m downhole.

Including two short (12.0 m and 6.0 m) weakly mineralized intervals, V-24-119 averages 1.68 g/t

Au over the entire 617.6 m downhole from bedrock surface at 2.4 m, ending in low grade

mineralization (0.3 g/t Au over the final 3.5 m from 616.5 m downhole). These results and those

of subsequent holes V-24-120 through V-24-122 significantly de-risk the core of the Valley

deposit, reducing uncertainty and efficiently helping to constrain deposit grades throughout a

broad volume.

Hole V-24-120

Collared in the same section as V-24-119 located within a 170 m gap, V-24-120 encountered

strong mineralization from bedrock surface at 7.6 m downhole, averaging 1.88 g/t Au over 200.9

m, including 2.90 g/t Au over 104.5 m from 11.5 m downhole. The hole exits the intrusion at

248.5 m downhole and was terminated shortly thereafter.

Figure 3 - Cross-section B-B', showing V-24-121 in the context of the initial Valley MRE

block model and MRE-constraining revenue factor 0.72 pit shell. The hole encountered an

unexpected zone of >1 g/t Au gold grades near the top of the hole. The underlying Valley block

model has not been updated to reflect the current results, nor any results to date from 2024.

Blocks shown outside of the current pit shell constraint are not included in the initial MRE for

Valley. Areas without blocks have not been modelled and were assumed as nil for the initial

Valley MRE.

Hole V-24-121

V-24-121 is collared in a 150 m gap along section between previous holes V-23-050 and V-24-

090, near the northeastern edge of the Valley deposit (Figures 1 & 3). The hole averaged 0.80 g/t

Au-double the 0.4 g/t Au cutoff grade used in the initial MRE at Valley-over its first 486.5 m

from bedrock surface at 6.0 m downhole, including a slightly higher-grade section of 1.06 g/t Au

over 243.0 m from 41.0 m downhole. Notably, the top of this subinterval averages 1.80 g/t Au

over 21.0 m, expanding the breadth of near-surface, relatively high-grade mineralization at

Valley to the northeast (Figure 3).

Hole V-24-122

V-24-122 reports a consistent interval of 352.0 m averaging 1.05 g/t Au from bedrock surface at

6.5 m downhole. The hole fills a gap in previous coverage in the southeastern part of the Valley

deposit, with the nearest hole V-23-052 collared roughly 50 m to the east. Highlighting this

consistency, capping the mineralization at 10.0 g/t Au has no effect on the resultant interval

grades (Table 2).

Figure 4 - Cross-section C-C', showing V-24-122 in the context of the initial Valley MRE

block model and MRE-constraining revenue factor 0.72 pit shell. The underlying Valley block

model has not been updated to reflect the current results, nor any results to date from 2024.

Blocks shown outside of the current pit shell constraint are not included in the initial MRE for

Valley. Areas without blocks have not been modelled and were assumed as nil for the initial

Valley MRE.

Holes V-24-123 & V-24-124

V-24-123 & 124 are among the southeasternmost holes drilled at Valley (Figure 1), each a step-

out of roughly 50 m from previous drilling. Both holes encountered anomalous (>1 g/t Au) gold

mineralization, with V-24-123 encountering multiple broad intervals throughout its length

averaging from 0.2 to 0.9 g/t Au (Table 2) and extending the envelope of known mineralization

at Valley to the southeast.

Table 2 - Summary of significant mineralization returned from current holes from Valley.

The consistency of strong mineralization in the Valley deposit is reinforced by the capped values

in the rightmost column, wherein any assay result >10 g/t Au is replaced by 10.0 g/t Au to

calculate the average interval grades. Rounding errors may be present in interval lengths.

*Interval widths reported; true widths of the Valley system are complex, with different vein

generations, orientations, and grade distributions present within various intervals through the

bulk tonnage gold target at Valley.

QA/QC

On receipt from the drill site NQ2-sized drill core was systematically logged for geological

attributes, photographed and sampled at Snowline's "Forks" Camp. Sample lengths as small as

0.5 m were used to isolate features of interest, but most samples within moderate to strong

mineralization were 1.0 m in length; otherwise, a default 1.5 m downhole sample length was

used. Core was cut in half lengthwise along a pre-determined line, with one half (same half,

consistently, dictated by orientation line where present or by dominant vein orientation where

absent) collected for analysis and one half stored as a record. Field duplicates were collected at

regular intervals as ¼ core samples by splitting the ½ core sent for sampling, leaving a consistent

record of half core material from duplicate and non-duplicate samples alike. Standard reference

materials and blanks were inserted by Snowline personnel at regular intervals into the sample

stream. Bagged samples were sealed with security tags to ensure integrity during transport. They

were delivered by expeditor to Bureau Veritas' preparatory facility in Whitehorse, Yukon. Sample

preparation was completed in Whitehorse, with analyses completed in Vancouver.

Bureau Veritas is accredited to ISO/IEC 17025 and ISO9001 for quality management. Samples

were crushed by BV to >85% passing below 2 mm and split using a riffle splitter. 250 g splits

were pulverized to >85% passing below 75 microns. A four-acid digest with an inductively

coupled plasma mass spectroscopy (ICP-MS) finish was used for 59-element analysis on 0.25 g

sample pulps (BV code: MA250). All samples were analysed for gold content by fire assay with

an atomic absorption spectroscopy (AAS) finish on 30 g samples (BV code: FA430). Any sample

returning >10 g/t Au was reanalysed by fire assay with a gravimetric finish on a 30 g sample (BV

code: FA530).

For the purposes of this release, contiguous mineralized intervals at Valley are defined as runs of

mineralization with no break >5.0 m assaying <0.1 g/t Au and may include any highlight

subsections thereof.

ABOUT ROGUE

Snowline Gold's 100%-owned, flagship Rogue Project, in Canada's Yukon Territory, covers a 60

x 30 km cluster of intrusions in the eastern Tombstone Gold Belt known as the Rogue Plutonic

Complex.

Since its launch in 2021, Snowline has progressed the Rogue Project's Valley deposit from a

greenfield prospecting discovery to a significant bulk tonnage gold resource, with 4.05 Moz gold

Indicated mineral resource at 1.66 g/t Au and an additional 3.26 Moz Inferred mineral resource at

1.25 g/t Au within a pit-shell constraint. The resource estimate numbers are supported by the

recent technical report for Rogue, prepared in accordance with NI 43-101 standards, entitled

"Rogue Gold Project: NI 43-101 Technical Report and Mineral Resource Estimate," authored by

Heather Burrell, P. Geo., Daniel J. Redmond, P. Geo., and Steven C. Haggarty, P. Eng., with an

effective date of May 15, 2024.

Exploration of the open Valley deposit is ongoing. Valley is a reduced intrusion-related gold

system (RIRGS), geologically similar to multi-million-ounce RIRGS deposits currently in

production, like Kinross's Fort Knox Mine in Alaska, but with substantially higher gold grades.

Gold is associated with bismuthinite and telluride minerals hosted in sheeted quartz vein arrays

within and along the margins of a one-kilometer-scale, mid-Cretaceous aged Mayo-series

intrusion.

The Rogue Project area hosts multiple intrusions similar to Valley along with widespread gold

anomalism in stream sediment, soil and rock samples. Elsewhere, RIRGS deposits are known to

occur in clusters. For these reasons, Snowline considers the Rogue Project to have district-scale

potential to host additional reduced intrusion-related gold systems.