Black Butte Copper Project Update
Black Butte Copper Project Update
WHITE SULPHUR SPRINGS, Mont., Aug. 17, 2020 -- Sandfire Resources America Inc. (“Sandfire America” or the
“Company” TSX.V: SFR and OTCQB: SRAFF ) provides the following update on its Black Butte Copper underground mining
project in Montana, USA.
Final Mine Operating Permit Granted
The Company is pleased to announce that on August 14, 2020, the Montana Department of Environmental Quality (“MT DEQ”)
issued a final approval for the Phase I Bonding for the underground Black Butte Copper project (the “Project). The Company
has posted a US$4.65 million surety bond for the Project, the MT DEQ has approved the bond posting and has issued a Final
Mine Operating Permit allowing the Company the right to commence Phase I Development surface construction at the mine
site.
The issuance of the Final Mine Operating Permit is the result of the Company meeting all the requirements of the Project
Record of Decision as published by the MT DEQ on April 9, 2020.
Commencement of Phase I Development Surface Earthworks
The Company has signed a construction contract for the commencement of surface earthworks with MK Weeden, a
Lewistown, Montana company. In addition, it has signed a fencing contract with a local Meagher County business, Menard
Construction Inc. These two contractors will employ up to 30 Montanans on the early earthworks project this year.
Commenting on the achievement of this milestone, Sandfire America’s CEO and VP of Project Development, Rob Scargill,
said: “Putting local Montana companies to work has always been an important company goal and now, more than ever, it will
help with the economic recovery as we continue to deal with COVID-19 pandemic. Strength in the natural resources sector is
crucial to creating lasting opportunities for the people of Montana.”
Hard Rock Mining Impact Plan Account Fully Funded
The Montana Hard Rock Mining Impact Act, a law unique to Montana and of great importance for local governments, requires a
large-scale mineral development to prepare a Hard Rock Mining Impact Plan (“HRMIP”) which describes the social and
economic impacts the mineral development will have on affected units of local government. The Company must then provide
the local governmental units funding to address identified financial impacts. The units of local government affected by the Black
Butte Copper Project are Meagher County, the City of White Sulphur Springs, and the White Sulphur Springs Public School
District #8. The agreed Black Butte Copper HRMIP requires the Company to place $437,000 in an escrow account available for
access by the local government entities as needed during mine construction. The account undergoes an annual review
ensuring it adequately covers impacts.
VP of Communication Nancy Schlepp stated, “This law is a fabulous monetary bridge for our community ensuring no lag time
is felt as our community infrastructure needs change as the tax base expands- ultimately benefitting everyone. This brilliant
law should be considered by other areas of Montana business”.
Feasibility Study Reaching Finalization
Work on the Feasibility Study for the Project is being finalized, using the agreed bonding amounts and with updated market
inputs after COVID-19. The Feasibility Study is expected to be published in the September Quarter, 2020.
Financing
Following a review of financing options by the Non-Executive Independent Directors, the Company entered into to an
unsecured loan with our majority shareholder, Sandfire Resources Limited, to provide US$5 million to cover anticipated
expenditures for early earthworks and to defend the Mine Operating Permit from legal challenges. This brings the Company’s
total debt to US$10 million. On release of the Feasibility Study, the Board will consider the Company’s mid-term and long-term
financing options.
QUALIFIED PERSON
Jerry Zieg, Vice President of Exploration for the Company, is a Qualified Person for the purposes of NI 43-101 and has
reviewed, verified, and approved the data disclosed and information of a scientific or technical nature contained in this news
release.
Contact Information:
Sandfire Resources America Inc.
Nancy Schlepp, VP of Communications
Mobile: 406-224-8180
Office: 406-547-3466
Email: [email protected]
CAUTIONARY NOTE
Cautionary Note Regarding Forward-Looking Statements: Certain disclosures in this document constitute “forward looking
information” within the meaning of Canadian securities legislation, including statements regarding the Company’s plans for
advancing the Black Butte Copper Project including commencement of contracted surface work and expected outcomes. In
making these forward-looking statements, the Company has applied certain factors and assumptions that the Company
believes are reasonable, including that the Company will receive required regulatory approvals, that the Company will continue
to be able to access sufficient funding to execute its plans, that the Company's exploration and development activities on the
Black Butte Copper Project will not be materially affected by actions of environmental activists or other special interest
groups, and that the results of exploration and development activities are consistent with management’s expectations, and
assumptions regarding the impact of the global health and financial crisis caused by COVID-19 on the Company. However,
the forward-looking statements in this document are subject to numerous risks, uncertainties and other factors, including
factors relating to the Company’s operation as a mineral exploration and development company and the Black Butte Copper
Project, that may cause future results to differ materially from those expressed or implied in such forward-looking statements,
including that results of exploration and development activities will not be consistent with management’s expectations, delays
in obtaining or inability to obtain required government or other regulatory approvals or financing, interference with the
Company's exploration or development activities by environmental activists or other special interest groups, the risk that the
Company will be materially and adversely impacted by the global health and financial crisis caused by COVID-19, failure of
plant, equipment or processes to operate as anticipated, the risk of accidents, labor disputes, inclement or hazardous
weather conditions, unusual or unexpected geological conditions, ground control problems, earthquakes, flooding and all of
the other risks generally associated with the development of mining facilities. There can be no assurance that such
statements will prove to be accurate, and actual results and future events could differ materially from those anticipated in
such statements. Readers are cautioned not to place undue reliance on forward-looking statements. The Company does not
intend, and expressly disclaims any intention or obligation to, update or revise any forward-looking statements whether as a
result of new information, future events or otherwise, except as required by law.
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX
Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.