Trigon Metals Announces Positive Feasibility for its Kombat Asis West Underground Mine

Corporate Updates

Trigon Metals Announces Positive Feasibility for its Kombat Asis West

Underground Mine

TORONTO--(BUSINESS WIRE)--March 4, 2024--Trigon Metals Inc. (TSX-V: TM, OTCQB:

PNZTF) ("Trigon" or the "Company") is pleased to announce the results of the feasibility study

undertaken on its Kombat Asis West underground mine in Namibia (the “Feasibility Study”).

The Feasibility Study was prepared by SRK Consulting South Africa (Pty) Ltd (“SRK”) in

accordance with Canadian Securities Administrators' National Instrument 43-101 Standards of

Disclosure for Mineral Projects ("NI 43-101").

The Feasibility Study incorporates both the currently operational open pit mine at Kombat as

well as the restart of the historic Asis West underground mine. Please note that all financial

figures in this press release are in United States dollars, unless otherwise noted.

Highlights

• Significant Mineral Reserves and production,

• Strong financial metrics,

• Defined Project Capital requirement, and

• Derisked operational and production profile.

Jed Richardson, Chairman, commented “I am pleased with the efforts of our team and the

collaboration with SRK on the completion of the study. The projected returns validate our efforts

and expectations for the Kombat Mine. We look forward to even stronger valuations as we

develop through the conversion of more of our Indicated Mineral Resources to Reserves, the

development of Asis Far West and exploration of the Copper King Extension."

A summary of operating and financial metrics from the Feasibility Study are presented in Table

1 below.

Table 1: Kombat Mine – Operating and Financial Metrics

Description Unit Total/average over LoM Asis West

underground Open pit

Copper price USD/lb 4.00

Silver price USD/oz 25.00

Life of mine Years 5.8 5.8 2.4

Run of mine kt 2 385 1 635 750

RoM grade - Copper % 2.46% 3.16% 0.93%

RoM grade - Silver g/t 17.5 22.9 5.7

Processing recovery - Copper % 92% 93% 88%

Processing recovery - Silver % 85% 86% 76%

Concentrate production kt 195 171 24

Recovered product - Copper Mlb 120 106 14

Recovered product - Silver kg 35 451 32 143 3 308

C1 cash cost/lb USD/lb 2.19

AISC/lb USD/lb 2.59

Project capex USDm 40.6

NPV10% (pre tax) (100%) USDm 116.0

IRR10%(pre tax) % 285%

NPV10% (after tax) (100%) USDm 77.8

IRR10%(after tax) % 235%

Note

Run of mine excludes 13.0 kt at 0.83% Cu sitting in stockpile.

C1 cost: direct costs, which include costs incurred in mining and processing (labour, power,

reagents, materials) plus local G&A, and freight, realization and selling costs, and mineral

royalties.

ASIC: All In Sustaining Costs, including sustaining capital.

Certain project capital has already been incurred and this is included in the assessed

loss/unredeemed capital reported by Trigon at February 2024.

Kombat Mine Overview

Trigon holds six active mineral licences related to the Kombat mine: the four mining licenses of

Asis West, Asis Far West, Asis Ost and Gross Otavi and two exclusive prospecting licenses. The

project areas are situated in the Otjozondjupa Region, Grootfontein Magisterial District of the

Otjozondjupa Region, Namibia, between the towns of Otavi, 37 km to the west and Grootfontein,

45 km to the east.

Trigon commenced with open pit mining in early 2023, and dewatering of the historic Asis West

underground complex (which comprises two vertical shafts, No. 1 shaft and No. 3 shaft, and a

decline ramp) in August 2023. In February 2024, Trigon announced the commencement of

operational training for the commencement of underground mining.

Mineral Resources and Mineral Reserve Estimates

Mineral Resources

The Mineral Resource Statement presented represents the third Mineral Resource evaluation

prepared for the Kombat Mine project in accordance with NI 43-101 by Minxcon (Pty) Ltd (an

independent consulting company) commissioned by Trigon to undertake this work. The Mineral

Resources have been independently reviewed by SRK and reported using updated techno-

economic factors.

Mineral Resources are shown in Tables 2 to 4 below. Mineral Resources are reported inclusive

of any Mineral Reserves that may be derived from them.

Table 2: Open Pit Mineral Resource Statement for Kombat Mine as at 29 February 2024

Area

Mineral

Resource

Category

Tonnes

(Mt)

Density

(t/m3)

Grade Content

Cu (%) Pb (%) Ag (g/t) Cu (t) Pb (t) Ag (kg)

Kombat East

Indicated

2.26 2.79 0.92 0.36 6.01 20 760 8 064 1 593

Kombat Central 0.87 2.78 1.07 0.13 9.32 9 294 1 167 148

Kombat West 0.01 2.98 1.95 4.69 17.43 268 645 10

Total Indicated 3.14 2.79 0.97 0.31 6.98 30 322 9 876 1 751

Gross Otavi Inferred 0.54 2.85 0.74 2.27 1.15 3 943 12 186 615

Total Inferred 0.54 2.85 0.74 2.27 1.15 3 943 12 186 615h

Notes:

1. A Mineral Resource is not a Mineral Reserve, and there is no guarantee that all or part of

the Mineral Resource will be converted to a Mineral Reserve

2. The Mineral Resources have been depleted with historical mining pit shells and

underground voids

3. The Mineral Resources are reported within an optimised pit shell, based on the techno-

economic factors disclosed above

4. The Kombat Mineral Resources are reported above a 0.53% Cu cut-off, and the Gross

Otavi Mineral Resources above a 0.60% CuEq cut-off

5. Mineral Resources are reported as total Mineral Resources and not attributable to Trigon

6. Mineral Resources are reported inclusive of any Mineral Reserves that may be derived

from them

7. The Gross Otavi Mineral Resources include geological losses of 15%, depletion for

unknown historical development of 1% and reduced by a porosity factor by 7.5%

Table 3: Underground Mineral Resource Statement for Kombat Mine at 29 February 2024

Area

Mineral

Resource

Category

Tonnes

(Mt)

Density

(t/m3)

Grade Content

Cu (%) Pb (%) Ag (g/t) Cu (t) Pb (t) Ag (kg )

Kombat East

Indicated

0.36 2.81 1.44 1.23 9.23 5 219 4 443 3 346

Kombat Central 0.85 2.81 1.55 0.86 12.55 13 173 7 299 10 664

Kombat West 1.18 2.83 1.90 1.30 11.26 22 393 15 319 13 255

Asis West 7.53 2.82 2.38 0.80 18.02 179 213 60 603 135 707

Gap 0.50 2.79 1.89 0.16 9.90 9 529 822 4 990

Total Indicated 10.42 2.82 2.20 2.20 16.11 229 527 88 486 167 962

Kombat East

Inferred

0.00 2.83 1.45 1.79 13.64 0 0 0

Kombat Central 0.01 2.88 2.02 2.74 0.01 187 254 0

Kombat West 0.13 3.68 5.00 10.50 0.08 6 377 13 399 11

Asis West 0.12 2.82 2.49 0.71 13.74 2 946 846 1 628

Gap 0.01 2.79 1.64 0.17 32.79 229 24 458

Asis Far West 1.53 2.79 2.15 0.37 7.99 32 763 5 703 12 196

Total Inferred 1.80 2.84 2.37 1.13 7.96 42 503 20 226 14 293

Notes:

1. A Mineral Resource is not a Mineral Reserve, and there is no guarantee that all or part of

the Mineral Resource will be converted to a Mineral Reserve

2. The Mineral Resources have been depleted with historical mining underground voids

3. The Mineral Resources are reported above a 1.2% CuEq cut-off

4. Mineral Resources are reported as total Mineral Resources and not attributable to Trigon

5. Mineral Resources are reported inclusive of any Mineral Reserves that may be derived

from them

6. No geological losses are applied

Table 4: Total Mineral Resource statement for Kombat Mine as at 29 February 2024

Source

Mineral

Resource

Category

Tonnes

(Mt)

Density

(t/m3)

Grade Content

Cu (%) Pb (%) Ag (g/t) Cu (t) Pb (t) Ag (kg)

Open Pit Indicated 3.14 2.79 0.97 0.31 6.98 30 322 9 876 1 751

Underground 10.42 2.82 2.20 2.20 16.11 229 527 88 486 167 962

Total Indicated 13.56 2.81 1.92 1.76 14.00 259 849 98 362 169 713

Open Pit Inferred 0.54 2.85 0.74 2.27 1.15 3 943 12 186 615

Underground 1.80 2.84 2.37 1.13 7.96 42 503 20 226 14 293

Total Inferred 2.33 2.85 1.99 1.39 6.39 46 446 32 412 14 908

Notes:

1. A Mineral Resource is not a Mineral Reserve, and there is no guarantee that all or part of

the Mineral Resource will be converted to a Mineral Reserve

2. The Mineral Resources have been depleted with historical mining underground voids

3. The underground Mineral Resources are reported above a 1.2% CuEq cut-off. The

Kombat open Pit Mineral Resources (All indicated) are reported above a 0.53% Cu cut-

off, and the Gross Otavi open Pit Mineral Resources (All Inferred) above a 0.60% CuEq

cut-off

4. Mineral Resources are reported as total Mineral Resources and not attributable to Trigon

5. Mineral Resources are reported inclusive of any Mineral Reserves that may be derived

from them

6. No geological losses are applied at Kombat. The Gross Otavi Mineral Resources include

geological losses of 15%, depletion for unknown historical development of 1% and

reduced by a porosity factor by 7.5%

Mineral Reserves

The open pit Mineral Reserves as set out in Table 5 are limited to the Ore Capping open pits,

which are situated in the Kombat East and Central areas. The LoM pit has been excluded due to

interference with current underground infrastructure. The open pit Mineral Reserve is declared at

the RoM stockpile as a reference point.

Table 5: Open Pit Mineral Reserve Statement for Kombat Mine as at 29 February 2024

Area

Mineral

Reserve

Category

Tonnes

(Mt)

Grade Content

Cu

(%)

Ag

(g/t)

Cu

(t)

Ag

(kg)

Kombat East Probable 0.75 0.93% 5.7 6 953 4 299

Total Probable 0.75 0.93% 5.7 6 953 4 299

Notes:

1. The Mineral Reserves have been depleted with historical mining pit shells and

underground voids.

2. The Mineral Reserves are reported within pit designs and scheduled.

3. The Kombat Mineral Reserves are reported above a 0.56% Cu cut off.

4. Mineral Reserves are reported as total Mineral Reserves and not attributable to Trigon.

5. The Mineral Reserve statement excludes 13.0 kt at 0.83% Cu sitting in stockpile.

The Mineral Reserves for the underground mining schedule are set out in Table 6 below. The

Mineral Reserves are reported at the point where the ore is fed into the processing plant.

Table 6: Kombat Asis West Underground Mineral Reserve as at 29 February 2024

Area

Mineral

Reserve

Category

Tonnes

(Mt)

Grade Content

Cu Ag Cu Ag

(%) (g/t) (t) (kg)

Asis West Probable 1.64 3.16% 22.8 51 643 37 393

Total Probable 1.64 3.16% 22.8 51 643 37 393

Notes:

1. Applied a dilution factor 0.5 m envelope of ore below cut-off in the stopes.

2. Applied an overbreak of 5% in waste development.

3. Lashing or mucking loss of blasted material in the stopes at 2%.

4. Applied a cut-off of 1.5% Cu ore.

5. The Mineral Reserve estimates are declared at the shaft head.

6. Cu metallurgical recovery applied is 93%.

7. The declaration is according to CIM Standards.

The combined Mineral Reserves for the Kombat mine are set out in Table 7 below.

Table 7: Kombat Combined Mineral Reserve as at 29 February 2024

Area

Mineral

Resource

Category

Tonnes

(Mt)

Grade Content

Cu Ag Cu Ag

(%) (g/t) (t) (kg)

Asis West Underground Probable 1.64 3.16% 22.8 51 643 37 393

Open pit Probable 0.75 0.93% 5.7 6 953 4 299

Stockpile Probable 0.01 0.83% 2.5 108 33

Total Probable 2.40 2.40% 17.4 58 704 41 726

Open Pit Mining Notes:

1. The Mineral Reserves have been depleted with historical mining pit shells and

underground voids.

2. The Mineral Reserves are reported within pit designs and scheduled.

3. The Kombat Mineral Reserves are reported above a 0.56% Cu cut-off.

4. Mineral Reserves are reported as total Mineral Reserves and not attributable to Trigon

Underground Notes:

1. Applied a dilution factor 0.5m envelope of ore below cut-off in the stopes.

2. Applied an overbreak of 5% in waste development.

3. Lashing or mucking loss of blasted material in the stopes at 2%.

4. Applied a cut-off of 1.5% Cu ore.

5. The Mineral Reserve estimates are declared at the point where the ore if fed into the

plant.

6. Cu metallurgical recovery applied is 93%.

7. The declaration is according to CIM Standards.

8. Mineral Reserves are reported as total Mineral Reserves and not attributable to Trigon

Qualified Person

The technical information presented in this press release has been reviewed and approved for

disclosure by [Andrew McDonald CEng MIMMM FSAIMM, SRK Principal Engineer and

Competent Valuator, Jaco van Graan, Pr Eng MSAIMM, SRK Associate Partner and Principal

Mining Engineer, Mark Wanless Pr.Sci.Nat FGSSA MGASA, SRK Partner and Principal

Geologist and Joseph Mainama PrEng MSAIMM, SRK Partner and Principal Mining Engineer]

who are Qualified Persons as defined by NI 43-101.

Trigon Metals Inc.

Trigon is a publicly traded Canadian exploration and development company with its core

business focused on copper and silver holdings in mine-friendly African jurisdictions. Currently,

the company has operations in Namibia and Morocco. In Namibia, the Company holds an 80%

interest in five mining licences in the Otavi Mountainlands, an area of Namibia widely

recognized for its high-grade copper deposits, where the Company is focused on exploration and

re-development of the previously producing Kombat Mine. In Morocco, the Company is the

holder of the Silver Hill project, a highly prospective copper and silver exploration project.

The complete NI 43-101 technical report associated with the Feasibility Study and updated

mineral resources and reserves estimates (the “Technical Report”) will be available on SEDAR+

at www.sedarplus.ca under the Company’s issuer profile, as well as the Company’s website at

www.trigonmetals.com within 45 calendar days.

Cautionary Notes

This news release may contain forward-looking statements. These statements include statements

regarding the Kombat Mine, the mineralization of the Kombat Mine, the timing and results of

economic studies including the Feasibility Study, the economic viability of the Kombat Mine,

mineral resources and mineral reserves estimates, ability to realize on projected economic

estimates, timing of receipts of permits and approvals, future exploration and development plans

and results and the Company’s future plans and objectives. These statements are based on

current expectations and assumptions that are subject to risks and uncertainties. Actual results

could differ materially because of factors discussed in the management discussion and analysis

section of our interim and most recent annual financial statements or other reports and filings

with the TSX Venture Exchange and applicable Canadian securities regulations. We do not

assume any obligation to update any forward-looking statements, except as required by

applicable laws.

Non-IFRS measures

The Company has included certain non-IFRS measures in this press release. The Company

believes that these measures provide investors an improved ability to evaluate the underlying

performance of the Company’s projects. The non-IFRS measures are intended to provide

additional information and should not be considered in isolation or as a substitute for measures

of performance prepared in accordance with IFRS. These measures do not have any

standardized meaning prescribed under IFRS, and therefore may not be comparable to other

issuers.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in

the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy

of this release.