Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

SF.V ·

Trigon Metals Agrees Offtake and Project Finance Terms and Provides Update ON Project Restart Activities

Financings Mine Development & Operations Partnerships & JV

TRIGON METALS AGREES OFFTAKE AND PROJECT FINANCE TERMS AND PROVIDES UPDATE ON

PROJECT RESTART ACTIVITIES

HIGHLIGHTS

• Offtake for 100% of annual production from the Kombat mine for up to 20,000mt of

copper.

• Financing facility of up to US$7.7 million for the Kombat mine production start up.

• Project restart activities well underway to achieve commencement of production by mid -

2018.

• Infill drilling program complete as first step in updating current Mineral Resource estimate

that will be basis for feasibility study.

• Environmental permitting process on track for application in early 2018.

Toronto, Canada – October 26, 2017 – Trigon Metals Inc. (TSX-V: TM) (“Trigon” or the “Company”)

is pleased to announce that it , together with its 80% owned subsidiary, Manila Investments (Pty)

Ltd (“Manila”), has agreed terms with a major international trading house for copper concentrate

offtake from the Company’s Kombat mine in Namibia and a financing facility to fund operations

restart activities in order to commence with open pit mining.

Copper Concentrate Offtake

Trigon and Manila have agreed offtake terms with a major international trading house to buy

100% of the annual production from the Kombat mine up to a total of 20,000mt of contained

copper.

This represents the anticipated life of mine production from the open pit in the Kombat Central

and East areas, based on the Mineral Resource estimate as reported in the National Instrument

43-101 technical report entitled “NI 43 -101 Technical Report on th e Kombat Copper P roject,

Namibia” dated May 31, 2017 (the “Technical Report”) . The Technical Report constitutes a

preliminary economic assessment and is available under the Company’s profile on SEDAR at

www.sedar.com and on the Company’s website at www.trigonmetals.com.

The terms of the offtake are subject to various conditions precedent, including final due diligence

and approvals from the trader.

Financing Facility

In conjunction with the offtake , the trader will provide a financing facility to Manila of up to

US$7.7 million (the “Facility”) to refurbish the concentrator at the Kombat mine, to upgrade

infrastructures and for working capital purposes to bring the Kombat open pit mine into

production.

Trigon w ill act as guarantor for the Facility, and security will include first ranking charges and

security interest over all present and future property and assets of Manila.

The terms of the Facility are subject to various conditions precedent, including final due diligence

and approvals from the trader.

Stephan Theron, President and CEO of Trigon, commented: “ The financing and offtake

arrangements represent a major milestone for Trigon and Manila in re-starting the Kombat mine .

We are pleased to be partnering with a major international trader in this exciting venture , which

should ensure that we can meet our 2018 production restart goals.”

Restart Activities

The Company is concurrently progressing various workstreams regarding its strategy to bring the

Kombat mine back into production and is targeting the commencement of open pit mining by mid-

2018. The Company does not have a current feasibility study and is not basing its decision to

restart mining activities on any estimated mineral reserves or on a feasibility study regarding the

economic or technical feasibility of the Kombat project. Historically, projects that are

re-commenced prior to the mining company completing a feasibility study have a much higher risk

of economic or technical failure. Esti mates regarding production levels, development timetable

and economic feasibility in respect of the Kombat mine are based on internal management

forecasts and are inherently uncertain and subject to continued refinement.

Drilling Program

The drilling program focused on the Kombat Central and East areas targeted by the Company for

open pit mining is complete, with 48 holes or an aggregate of 2,200 meters having been drilled in

this first stage program, the primary aim of which is to upgrade the current Mineral Resource from

the Inferred category to Measured and Indicated Mineral Resources.

Final assay results are expected to be received by the end of November 2017 , following which the

information will be utilized to remodel and upgrade the current Mineral Resource as set out

above. The updated Mineral Resource is expected to be finalized by December 2017 and will form

the basis for the feasibility study on the surface mining areas as referred to below.

The Company further plans to undertake an additional drilling program to extend the current

Mineral Resource. This three phase program comprises an additional 34 holes, with an aggregate

of 1,437 meters to be drilled.

Feasibility Studies

The Company intends to initiate a feasibility study on the surface mining areas and a pre-feasibility

design on the Asis Far West underground mine during November 2017. The studies are anticipated

to take six months to complete, during which period refurbishment of the mill and concentrator

can commence to facilitate timelines for commencement of open pit mining and the processing of

ore therefrom. The Company does not currently have a feasibility study in respect o f the Kombat

mine and production restart activities are based on internal management forecasts.

Environmental Permitting

On September 25, 2017, the Company announced that it had received notification from the

Minister of Environment and Tourism in Namibia that it had been awarded an Environmental

Clearance Certificate for proposed exploration on the mining licences held by M anila. The

clearance is valid for a period of three years from September 18, 2017.

The Company is currently engaged with its environmental consultant, SLR Environmental

Consulting (Namibia) (Pty) Ltd, to secure the Environmental Clearance Certificate req uired for

open pit mining and associated activities , as well as those needed for exploration activit ies for

underground mining. The required specialist studies are planned to be completed by the end of

November 2017, and application for the necessary permitting will be made in early 2018 after the

relevant Environmental Impact Assessment (“EIA”) reports have been reviewed by stakeholders.

Metallurgical Testwork

The results of m etallurgical testwork commissioned on historic drill cores from the targeted open

pit mining areas to evaluate ore grades and achievable recoveries used for the purposes of the

preliminary economic assessment (“PEA”) have been positive . Further testing to optimize future

comminution and flotation parameters is expected to be completed by January 2018 and will be

used in the DFS referred to above.

Power

An application has been made to Namibian Power Corporation (Proprietary) Limited to increase

the current power supply by 4.5MVA, in order to meet the requ irements for the targeted mining

and processing operations.

Highlights of the PEA

The PEA , highlights of which were published in the Technical Report, confirms that the Kombat

operations, including both open pit and underground mining operations, have a best-estimated

net present value (“NPV”) of US$72 million, and a robust internal rate of return of 45.5% , using a

long term copper price of US$2.95/lb. The current copper price at US$3.17/lb is higher than these

long term forecasts.

The PEA is based on Inferred Mineral Resources of 6.905 million tonnes at a grade of 2.78%

copper, 1.14% lead and 19.11 g/t silver, and results in a c ombined open pit and underground life

of mine of nine years at an average mined grade of 2.83% copper, pro ducing 122,106 CuEq tons ,

at a C1 cash cost of US$1.33/lb.

The PEA was prepared by Minxcon (Pty) Ltd (“Minxcon”) and issued on May 26, 2017.

The PEA is preliminary in nature and includes Inferred Mineral Resources that are considered

too speculative geologically to have the economic considerations applied to them that would

enable them to be categorized as Mineral Reserves, and there is no certainty that the PEA will

be realized. Mineral Resources that are not Mineral Reserves do not have demonstrated

economic viability.

The Company’s phase 1 strategy of open pit mining to facilitate early cas h flow generation is

estimated to only require start-up capital of US$7.73 million.

Stephan Theron further commented: “The restart activities are in many instan ces proving better

results than the assumptions used in the PEA, and in the current copper price environment we are

extremely bullish about getting this project off the ground and back into production. We look

forward to reporting further positive news to the market as we achieve our targets.”

Qualified Person

Mr. Uwe Engelmann (BSc (Zoo. & Bot.), BSc Hons (Geol.), Pr.Sci.Nat. No. 400058/08, MGSSA) of

Minxcon, is a “qualified person” as such term is defined in NI 43 - 101 and has reviewed and

approved the technical information and data included in this press release. As a director of

Minxcon, Mr. Engelmann is considered independent.

Trigon Metals Inc.

Trigon is a publicly traded Canadian exploration and development company with its core business

focused on copper operations in Namibia, one of the world’s most prospective copper regions,

where it has substantial assets in place with significant upside. The C ompany continues to hold an

80% interest in five mining licenses in the Otavi Mountain lands, an area of Namibia widely

recognized for its high -grade copper deposits. Within these licenses are three past producing

mines including the Company’s flagship property, the Kombat Mine.

For further information, contact:

Blake Hylands

Investor Relations +1 (416) 216 5445

Email: [email protected]

Website: www.trigonmetals.com

Cautionary Notes

This news release may contain forward- looking statements. These statements i nclude statements

regarding the offtake and financing facility terms, the drilling program and Mineral Resource

estimate, the feasibility studies and permitting requirements, the results of metallurgical testwork,

the Company’s strategies and the Company’s abilities to execute such strategies, the

mineralization of the Kombat mine, the realization of the PEA for the Kombat mine, potential

expansion of Mineral R esources, expectations of future cash flow, refurbishment of plant and

equipment, the updating of the Mineral Resources, the ability to complete a drilling program, the

ability to complete a DFS, the ability to obtain financing, the ability to enter into binding offtake

agreements, the value and rate of return of the Kombat mine and operations, the ability to

generate cashflow, the trader’s ability to purchase the production from the Kombat mine, the

granting of applicable permitting, the Company’s ability to restart the Kombat operations, the

results of the Technical Report and PEA, the Company’s expectations for the Kombat operations

and the Company’s future plans and objectives . These statements are based on current

expectations and assumptions that are subject to risks and uncertainties. Actual results could differ

materially because of factors discussed in the management discussion and analysis section of our

interim and most recent annual financial statements or other reports and filings with the TSX

Venture Exchange and applicable C anadian securities regulations. We do not assume any

obligation to update any forward-looking statements, except as required by applicable laws.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the

policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this

release.