Seabridge Drilling Confirms Promising Gold Target at Iskut Project Evidence of a gold-bearing epithermal system found at Quartz Rise
Seabridge Drilling Confirms Promising Gold Target at Iskut Project
Evidence of a gold-bearing epithermal system found at Quartz Rise
TORONTO, Nov. 20, 2017 -- Seabridge Gold (TSX:SEA) (NYSE:SA) announced today that its first exploration program on the
Quartz Rise target at its 100%-owned Iskut Project in northwestern British Columbia has been completed and all assay
results are in hand. Ten core holes were completed this year totaling 4,459 meters.
This year’s drilling found evidence of a gold-bearing intermediate sulfidation epithermal system beneath the Quartz Rise
lithocap as anticipated. Intercepts included 1.5 meters grading 8.26 g/T gold in QR-17-01 and 1.5 meters grading 74.1 g/T gold
in QR-17-07. Sampling of a cliff face north of Quartz Rise returned very high grades ranging from 1.49 to 125.3 g/T gold. An
economic source for these gold concentrations was not found in the 2017 drilling but the data acquired in this year’s program
has defined a target (see below) which could account for these high grade results. A second exploration program is being
planned for next year to pursue this target.
This year’s drilling was designed to test a graben feature discovered during surface work on the Quartz Rise lithocap. This
graben appears to have constrained the most intense hydrothermal alteration in the area of the lithocap. Drilling focused on the
southeastern portion of the graben. Next year’s work will include additional geophysical surveys and drilling along strike of this
graben to the northwest. Drill tests will be orientated to optimize intersections with northeast structures and stratigraphic
intervals which this year’s program has determined to be the most favorable for higher gold concentrations.
Rudi Fronk, Seabridge Chairman and CEO, commented that “in our first program at Quartz Rise, our exploration team has
successfully found the right environment for a high-grade epithermal gold deposit. The system at Quartz Rise has all the
earmarks we were looking for and we think we have enhanced the potential for a significant discovery. Further geophysical
work completed at the end of this year’s program suggests which part of the system should be targeted next year. Iskut’s
similarities with KSM are persuasive and this knowledge should help us zero in on the potential at Quartz Rise.”
Program Description
The program at Quartz Rise began with geological mapping which featured a shallow northeast dipping sequence of Jurassic
felsic volcanic rocks deposited unconformably on Triassic marine sedimentary rocks. This is the geological time break that
has proved to be productive elsewhere in the region. The entire section of volcanic rocks shows leaching and textural
destruction consistent with acidic alteration within an extensive lithocap emanating from an intrusive center. Similar lithocaps
host rich epithermal gold systems in some of the world’s best mining districts. A pair of graben-forming faults (labeled #6 and
#9) identified in the Jurassic volcanic rocks was mapped in detail, surface sampled and surveyed using short-wave infrared
(SWIR) instrumentation to define the areas of most intense alteration. This work led to three specific questions to be answered
by drilling:
• Did the graben faults act as conduits for mineralizing fluids?
• Can receptive units be identified within the volcanic stratigraphy?
• Is there a preferred direction within the graben and lithocap with potential to host an intermediate sulfidation epithermal
occurrence?
Graben Faults
The graben-forming faults were suspected to be significant precious-metal fluid pathways; they were traceable over several
kilometers and they projected into the historical Johnny Mountain Mine where they are recognized as controlling gold
distribution within the mine. The best indication that these faults helped to focus gold came from an intersection in QR-17-06;
here the #6 fault returned a 3.8 meter interval of 6.52g/ T gold. Elsewhere in hole QR-17-04, a silica breccia zone adjacent to
the #9 fault contained anomalous gold concentrations. We have concluded from these results that the graben-forming faults
are likely an integral part of the mineralizing system but are not the primary depositional sites for precious metals at Quartz
Rise.
Receptive Volcanic Units
The volcanic stratigraphy established from surface mapping and drill holes shows a series of coarse lithic tuff flows intercalated
with densely welded flows, incestuous porphyritic sills and tuffaceous sedimentary rocks. In Quartz Rise, the coarse lithic tuff
tends to show much more intense leaching and acid alteration then do the densely welded tuff, sills or sedimentary rocks. In
several drill intersections, the tuffs directly below the densely welded units or sills contain intervals of anomalous gold,
specifically holes QR-17-2 and QR-17-7. These results indicate that the coarse lithic tuff units were permeable to hydrothermal
fluids and could represent permissive units for deposition of precious metals.
Vectoring Towards a New Target within the Quartz Rise Graben
Compilation of surface mapping and drill hole geology shows a clear trend of decreased hydrothermal alteration toward the
south and east. This is defined by the intensity of acid alteration, better preservation of original volcanic textures and
diminishing pathfinder geochemistry. The opportunity for discovery therefore appears to improve to the north and west of the
Quartz Rise area, toward historical mining. Furthermore, it has become evident that the northwest trending graben structural
pattern does not account for the best gold values found in this year’s program including holes QR-17-01 (1.5 meters grading
8.26 g/T gold) and QR-17-07 (1.5 meters grading 74.1 g/T gold) as well as sampling of a cliff face north of Quartz Rise which
returned very high grades ranging from 1.49 to 125.3 g/T gold.
A secondary and subordinate northeast structural orientation has subsequently been defined which is orthogonal to the graben
faults and preferentially localizes intervals of high-grade gold. The 2017 Quartz Rise drilling plan was not designed to evaluate
this northeast orientation. An IP survey was conducted late in the 2017 program to pursue this idea and its chargeability
features provide indirect confirmation of favorable northeast structures which will be targeted in next year’s program.
Selected 2017 Assay Data
Table of selected drill hole intersections and cliff face samples from 2017 Quartz Rise Program
Drill Hole
Total Depth
(m) From (m) To (m) Width (m) Au g/T Ag g/T
Intersection on Graben Faults
QR-17-06 753.0 340.5 344.3 3.8 6.52 1.3
QR-17-04 540.0 271.0 280.0 9.0 0.48 4.4
Intersection in Permissive Stratigraphy
QR-17-02 504.0
160.6 166.5 5.9 0.59 3.4
237.0 246.0 9.0 0.95 1.2
277.5 283.6 6.1 1.74 1.4
306.0 313.0 7.0 0.56 1.4
QR-17-07 501.0 202.5 210.0 7.5 0.71 0.2
Drill Intersection and Surface Samples on North East Structures
QR-17-01 329.5 218.5 220.0 1.5 8.26 6.5
QR-17-07 501.0 25.0 26.5 1.5 74.10 6.3
CS-1 Sample weight 1.54kg 1.49 0.4
CS-2A Sample weight 0.72kg 125.3 31.6
CS-2C Sample weight 0.55kg 10.5 3.9
CS-2D Sample weight 4.23kg 4.05 3.1
The results provided in the table above are early-stage and insufficient to establish a true thickness of the mineralized zones.
These intervals are provided as an illustration of specific environments encountered in the program and do not represent all the
precious metal intervals from the drilling program. Additional drilling will be required to determine the relevance of the widths of
drill hole intervals reported here.
Exploration activities by Seabridge at the Iskut Project are being conducted under the supervision of William E. Threlkeld,
Registered Professional Geologist, Senior Vice President of the Company and a Qualified Person as defined by National
Instrument 43-101. Mr. Threlkeld has reviewed and approved this news release. An ongoing and rigorous quality control/quality
assurance protocol is employed in all Seabridge drilling campaigns. This program includes blank and reference standards.
Cross-check analyses are conducted at a second external laboratory on at least 10% of the drill samples.
Seabridge holds a 100% interest in several North American gold projects. The Company's principal assets are the KSM and
Iskut Projects located near Stewart, British Columbia, Canada and the Courageous Lake gold project located in Canada's
Northwest Territories. For a full breakdown of Seabridge's mineral reserves and mineral resources by category please visit the
Company's website at http://www.seabridgegold.net/resources.php.
None of the Toronto Stock Exchange, New York Stock Exchange, or their Regulation Services Providers accepts
responsibility for the adequacy or accuracy of this release.
This document contains "forward-looking information" within the meaning of Canadian securities legislation and
"forward-looking statements" within the meaning of the United States Private Securities Litigation Reform Act of
1995. This information and these statements, referred to herein as "forward-looking statements" are made as of the
date of this document. Forward-looking statements relate to future events or future performance and reflect current
estimates, predictions, interpretations, expectations or beliefs regarding future events and include, but are not
limited to, statements with respect to: (i) the graben feature constraining the most intense hydrothermal alteration
in the area of the lithocap; (ii) the belief that the exploration team has successfully found the right environment for
a high-grade epithermal gold deposit and that Quartz Rise has the potential for a significant discovery; (iii) the
graben-forming faults likely being an integral part of the mineralizing system but not the primary depositional sites
for precious metals at Quartz Rise; (iv) the coarse lithic tuffs possibly representing permissive units for deposition of
precious metals; and (v) the opportunity for discovery improving to the north and west of the Quartz Rise area.
All forward-looking statements are based on Seabridge's or its consultants' current beliefs as well as various
assumptions made by them and information currently available to them. Although management considers these
assumptions to be reasonable based on information currently available to it, they may prove to be incorrect. Many
forward-looking statements are made assuming the correctness of other forward looking statements.
Forward-looking statements involve various risks and uncertainties. There can be no assurance that such
statements will prove to be accurate and actual results and future events could differ materially from those
anticipated in such statements. Important factors that could cause actual results to differ materially from the
Company's plans or expectations include the risk that the interpretations of the geologic formations at the Quartz
Rise area do not conform to the geologic models that are the foundations for such hypotheses and other risks
outlined in statements made by the Company from time to time in the filings made by the Company with securities
regulators. A detailed cautionary statement outlining the forward looking statements in the mineral reserves and
mineral resources reported by the Company, as well as assumptions and risks relating to them appears on its
website. The Company disclaims any intention or obligation to update or revise any forward-looking statements
whether as a result of new information, future events or otherwise, except as otherwise required by applicable
securities legislation.
We caution readers not to place undue reliance on these forward-looking statements as a number of important
factors could cause the actual outcomes to differ materially from the beliefs, plans, objectives, expectations,
anticipations, estimates assumptions and intentions expressed in such forward-looking statements.
ON BEHALF OF THE BOARD
"Rudi Fronk"
Chairman & C.E.O.
For further information please contact:
Rudi P. Fronk, Chairman and C.E.O.
Tel: (416) 367-9292 · Fax: (416) 367-2711
Email: [email protected]