Santacruz Reports Progress on Veta Grande Mill Expansion and Additional Drilling Campaign at Armados Vein
TSX.V: SCZ
FSE: 1SZ
February 28th, 2018
Santacruz Reports Progress on Veta Grande Mill Expansion and Additional Drilling Campaign at
Armados Vein
Vancouver, B.C. – Santacruz Silver Mining Ltd. (TSX.V:SCZ) (the “Company” or “Santacruz”) reports that
construction works to expand the Veta Grande mill capacity to 750 tpd are 85% advanced. Commissioning of
this expansion is expected to start in late March. The mill expansion is being funded by Carrizal Mining, S.A.
de C.V. (“Carrizal”) pursuant to the Carrizal LOI (see press release dated December 14th, 2017).
In addition, Santacruz advises that the previously announced drill campaign (see press release dated January
9th, 2018) at the Veta Grande Project has been e xpanded to include an initial 3,000-metre undergorund
diamond drill program on the Armados vein. In order to complete the program in a timely manner Carrizal is
mobilizing a second drill rig to the Veta Grande mine with drilling expected to commence by mid-March.
Carlos Silva, COO of Santacruz, stated " The expansion of the Veta Grande Project diamond drill program to
include the Armados vein will allow us to better delineate a mine plan on this vein in anticipation of the
inminent expansion of the Veta Grande mill capacity.” Mr. Silva continued “ The mill expansion activities are in
line with our budget and commissioning of the new ball mill is scheduled to start by the end of th e first quarter
aiming to achieve designed efficiencies during the month of April."
About Santacruz Silver Mining Ltd.
Santacruz is a Mexican focused silver company with two producing silver projects (Rosario, including the
Cinco Estrellas property and Membrillo Prospect, and the Veta Grande project and milling facility) and tw o
exploration properties including the Minillas property and Zacatecas properties. The Company is managed by
a technical team of professionals with proven track records in developing, operating and discovering silver
mines in Mexico. Our corporate objective is to become a mid-tier silver producer.
About Carrizal Mining, S.A. de C.V.
Carrizal Mining is a Mexican privately owned Company which operates the Zimapan mine in Zimapan Hidalgo
Mexico. The Company operates a 3,200 tpd mill and produces approximately 5.5 million silver equivalent
ounces a year.
‘signed’
Arturo Préstamo Elizondo,
President, Chief Executive Officer and Director
For further information please contact:
Arturo Prestamo
Santacruz Silver Mining Ltd.
Email: [email protected]
Telephone: (604) 569-1609
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies
of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.
Forward looking information
Certain statements contained in this news release constitute "forward -looking information" as such term is
used in applicable Canadian securities laws. Forward -looking information is based on plans, expectations and
estimates of management at the date the information is provided and is subject to certain factors and
assumptions. In making the forward -looking statements included in this news release, the Company has
applied several material ass umptions, that the Company's financial condition and development plans do not
change as a result of unforeseen events, that third party mineralized material to be milled by the Company will
have properties consistent with management's expectations, that th e Company will receive all required
regulatory approvals, and that future metal prices and the demand and market outlook for metals will remain
stable or improve. Forward -looking information is subject to a variety of risks and uncertainties and other
factors that could cause plans, estimates and actual results to vary materially from those projected in such
forward-looking information. Factors that could cause the forward -looking information in this news release to
change or to be inaccurate include, but are not limited to, the risk that any of the assumptions referred to prove
not to be valid or reliable, which could result in lower revenue, higher cost, or lower production levels; delays
and/or cessation in planned work; changes in the Company's financi al condition and development plans;
delays in regulatory approval; risks associated with the interpretation of data (including in respect of the third
party mineralized material) regarding the geology, grade and continuity of mineral deposits; the possibil ity that
results will not be consistent with the Company's expectations, as well as the other risks and uncertainties
applicable to mineral exploration and development activities and to the Company as set forth in the Company's
continuous disclosure filings filed under the Company's profile at www.sedar.com. There can be no assurance
that any forward -looking information will prove to be accurate, as actual results and future events could differ
materially from those ant icipated in such statements. Accordingly, the reader should not place any undue
reliance on forward -looking information or statements. The Company undertakes no obligation to update
forward-looking information or statements, other than as required by applicable law.
Rosario Project
The decisions to commence production at the Rosario Mine , Cinco Estrellas Property and Membrillo Prospect
were not based on a feasibility study of mineral reserves demonstrating economic and technical viability, but
rather on a m ore preliminary estimate of inferred mineral resources. Accordingly, there is increased
uncertainty and economic and technical risks of failure associated with this production decision. Production
and economic variables may vary considerably, due to the ab sence of a complete and detailed site analysis
according to and in accordance with NI 43-101.
Veta Grande Project
The decision to commence production at Veta Grande Project was not based on a feasibility study on mineral
reserves demonstrating economic and technical viability. Accordingly, there is increased uncertainty and
economic and technical risks of failure associated with this production decision. Production and economic
variables may vary considerably due to the absence of a complete and detailed site analysis according to and
in accordance with NI 43-101.