Scottie Resources Announces Impressive Economics in Preliminary Economic Assessment for Scottie Gold Mine Project
Scottie Resources Announces Impressive
Economics in Preliminary Economic
Assessment for Scottie Gold Mine Project
Vancouver, British Columbia--(Newsfile Corp. - October 28, 2025) - Scottie Resources Corp. (TSXV:
SCOT) (OTCQB: SCTSF) (FSE: SR80) ("
Scottie
" or the "
Company
") is pleased to announce the
results of an independent Preliminary Economic Assessment ("PEA") completed by Tetra Tech Canada,
Inc. ("
Tetra Tech
") for the Scottie Gold Mine project in British Columbia, Canada.
The PEA outlines a robust
Direct-Ship Ore ("DSO")
development scenario for the Scottie Gold Mine
Project, with strong economics and leverage to the current gold price environment, and additional upside
potential through toll milling. All dollar ($) amounts in this news release are in Canadian dollars ($) unless
otherwise indicated. The base case DSO project delivers an after-tax NPV(5%) ranging from $215.8
million to $668.3 million at gold prices of US$2,600/oz and US$4,200/oz, respectively.
Importantly, the
PEA also presents the opportunity to utilize excess capacity at the nearby Premier mill through a toll-
milling arrangement, which could significantly enhance project economics. Under this scenario, the after-
tax NPV(5%) increases to $380.1 million at US$2,600/oz and $831.7 million at US$4,200/oz (note: no
toll-milling agreement is currently in place). The PEA contemplates an initial capital cost of $128.6 million
and average annual production of approximately 65,400 ounces of gold over a seven-year mine life. The
project demonstrates a compelling after-tax payback period of 1.7 years for the standalone DSO case,
and just 0.9 years under the toll-milling opportunity at a gold price of US$2,600/oz.
The Company will be hosting a webcast to review the PEA on Wednesday, October 29, 2025 at
8:00am PT.
To join the webcast, please follow this link:
https://www.gowebcasting.com/14523
Table 1:
Gold Price Sensitivity and Comparison table between DSO Base Case and Toll Milling
Options for the Scottie Gold Mine Project.
Gold Price
Description
DSO Base
Case
Toll Milling
Option*
$2600
US/oz
After-Tax NPV
5%
$215.8M
$380.1M
After-Tax IRR
60.3%
89.9%
After-Tax Payback
1.2 years
0.9 years
After-Tax NPV/CAPEX
1.7
3.0
$3400
US/oz
After-Tax NPV
5%
$442.0M
$606.0M
After-Tax IRR
107.9%
135.2%
After-Tax Payback
0.8 years
0.7 years
After-Tax NPV/CAPEX
3.4
4.7
$4200
US/oz
After-Tax NPV
5%
$668.3M
$831.7M
After-Tax IRR
153.2%
177.5%
After-Tax Payback
0.6 years
0.5 years
After-Tax NPV/CAPEX
5.2
6.5
Note: Scottie Gold Mine Preliminary Economic Assessment Base Case assumes a gold price of US$2600/troy ounce ("oz") and a US$/CAD$
exchange rate of 0.72:1.00. NPV/CAPEX is the ratio between NPV value versus Initial Capex *At this time there is no toll milling arrangement in place
with the nearby Premier mill.
"
The Direct Ship Ore ("DSO") PEA marks a major milestone for Scottie
," commented Brad Rourke,
CEO. "
It highlights a simple, low-capex project with robust economics and clear growth potential
through ongoing discovery. The DSO scenario eliminates the need for a mill or tailings facility,
streamlining both permitting and construction. In addition, the optionality of toll milling at a nearby
facility presents a clear, low-risk development pathway with meaningful upside. As we advance
engineering and permitting, our successful 2025 drilling campaign and planned 2026 program are
expected to convert a substantial portion of the current resource to the Indicated category and add new
ounces-extending mine life and further strengthening project economics
."
PEA Summary
The DSO project is planned to commence with open pit mining at the Blueberry Contact Zone, closely
followed by underground mining at the Blueberry Contact Zone, and subsequently the Scottie Gold Mine
(see Figure 1 for production schedule). The mined material will be then jaw crushed and sorted using an
XRF based ore sorting system. The upgraded product will be transported to the Stewart bulk shipping
facility located 40 km down an existing road to be shipped overseas. The material would be then sold to
Ocean Partners based on the negotiated terms in the existing offtake agreement (
see NR dated July 7,
2025
).
The PEA is based on the mineral resource estimate, titled "NI 43-101 2025 Maiden Mineral Resource
Estimate for the Scottie Gold Mine Project" for the Scottie Gold Mine Property, British Columbia,
Canada, effective February 2, 2025 and announced on
May 7, 2025
(the "February 2025 Mineral
Resource Estimate").
Technical and Financial Details
Table 2:
Scottie Gold Mine DSO PEA Summary (Base Case), assumes a 5% discount rate and a gold
price of US$2600.
Throughput (tpd)
900
Mine Life
7 years
Milled Tonnage (Mt)
2.19
Average LOM Gold Head Grade (gpt)
6.86
Contained Gold oz
483,000
Gold Recovery
94.7%
Payable Gold oz (LOM)
457,600
Average Annual Production (LOM) - Gold oz
65,400
Average Annual Production (Years 1-4) - Gold oz
77,300
UG Mining Cost ($/t sorted)
$118.10
OP Mining Cost ($/t mined)
$6.95
Processing Cost ($/t sorted)
$17.96
G&A Cost ($/t sorted)
$31.23
Surface Services Cost ($/t sorted)
$16.76
Total Operating Cost ($/t sorted)
$185.30
Initial Capital Cost ($ million)
$128.6
LOM Sustaining Capital Cost ($ million)
$76.7
LOM AISC (US$/oz Au)
US$1452
Pre-Tax IRR
82.5%
Pre-Tax NPV (5%, $ million)
$326.1
Pre-Tax Undiscounted LOM net free cash flow ($ million)
$419.1
Pre-Tax Payback period
1 year
After-Tax IRR
60.3%
After-Tax NPV (5%, $ million)
$215.8
After-Tax Undiscounted LOM net free cash flow ($ million)
$283.5
After-Tax Payback period
1.2 years
The PEA presents a range of metal pricing scenarios on after-tax basis to evaluate the economics of the
project in both base case and alternate commodity price scenarios:
Additional sensitivities to the price of gold, recovery, exchange rate, Capex, and Opex will be presented
in the PEA Technical Report. The project economics are most sensitive to gold prices.
Diluted Resource Estimate
The resource estimate for the PEA is based on inferred resources as stated in the February 2025
Resource Estimate for the Scottie Gold Mine project. Certain mining factors have been applied to this
resource estimate, to generate diluted resources using a conceptual mine plan for the PEA. The
February 2025 Resource Estimate is summarized below:
Blueberry Pit Resource
Source
Cutoff Au
Tonnage
Au
NSR
Au Metal
(g/t)
(ktonnes)
(g/t)
($CDN)
(kOz)
Blueberry Pit (Inferred)
0.25
2,887
2.06
156.04
191
0.3
2,712
2.17
164.69
190
0.5
2,114
2.68
202.51
182
0.7
1,707
3.17
239.73
174
1
1,323
3.85
290.19
164
2.5
600
6.61
492.83
128
5
273
10.35
755
91
Total Underground Resource
Source
Cutoff Au
Tonnage
Au
NSR
Au Metal
(g/t)
(ktonnes)
(g/t)
($CDN)
(kOz)
Blueberry and Scottie Mine Underground (Inferred)
2.5
1,897
8.66
678.51
528
3
1,704
9.33
731
511
3.5
1,549
9.94
778.78
495
4
1,404
10.59
829.04
478
4.5
1,269
11.26
881.69
459
5
1,143
11.98
937.99
440
10
520
18.05
1,413.75
302
Inferred
varies
3,604
6.06
470.69
703
Notes to the 2025 Resource Table:
1
.
Resources are reported using the 2014 CIM Definition Standards and were estimated using the 2019 CIM Best Practices Guidelines, as
required National Instrument 43-101 - Standards of Disclosure for Mineral Projects ("NI 43-101")
2
.
The base case MRE has been confined by "reasonable prospects of eventual economic extraction" shape using the following assumptions:
Metal price of US$2000/oz gold
Metallurgical recovery of 90% gold
Payable metal of 99% gold in doré
Forex of 0.74 $US:$CDN
Processing costs of CDN$24 / tonne milled, which includes milling, transport, smelter treatment, refining and General &
Administrative (G&A) costs
Underground production cost of CDN$78 / tonne, and underground development costs to be CDN$90 / tonne, for a total underground
mining cost of CDN$168 / tonne
Open pit mining costs of CDN$3.00 / tonne for mineralized and waste material
45-degree pit slopes
The 130% price case pit shell is used for the confining shape with elevation adjustment of the main Blueberry pit for the
underground resource.
3
.
The resulting net smelter return is NSR = Au g/t* CDN$98.60 / g * 90% recovery rate
4
.
Numbers may not add due to rounding.
5
.
Mineral resources are not mineral reserves and do not have demonstrated economic viability. There is no certainty that all or any part of the
estimated mineral resources will be converted into mineral reserves.
It is noted that the prices and costs used for the resource estimate are not identical to the updated values
used for the mining and cash flow calculations. The costs and Au price used for the resource reflect
those considered reasonable at the effective date of the resource estimate. A check has been done on
these values compared to the current values and it is found that the resource is somewhat conservative
on price resulting in a similar cutoff for open pit mining and somewhat higher cutoff for underground than
that used for the mining study and cashflow.
The Qualified Person is of the opinion that issues relating to all relevant technical and economic factors
likely to influence the prospect of economic extraction can be resolved with further work. These factors
may include environmental permitting, infrastructure, sociopolitical, marketing, or other relevant factors.
Mining Method
The Project is planned as a combined open pit and underground mining operation utilizing contractor
mining. Open pit development is expected to utilize a conventional truck-and-shovel method, whereas
underground development will be based on longitudinal longhole stoping. A nominal average production
rate of approximately 900 tonnes per day (tpd) has been assumed for the combined operation.
For the base case scenario, resource material selected as run-of-mine (ROM) mill feed will be
stockpiled and subsequently processed using an ore sorter. The ore sorter concentrate will be shipped
directly to overseas markets. This mining and processing strategy has been applied to both the open pit
and underground components and forms the basis of the PEA.
Table 3:
Combined Resource Material for Ore Sorter Feed
Phase
Rock
(Mt)
Ore Sorter
Feed (Mt)
Waste
(Mt)
Au
(g/t)
Au contained
(kOz)
Au Recovered (kOz)
Total OP
5.86
0.32
5.54
7.71
79
76
Total UG
2.55
1.87
1.73
6.72
403
384
Total
8.41
2.19
7.27
6.87
482
460
Note: BB = Blueberry, OP = open pit, UG = underground, Au = gold grade (g/t), Mt = million tonnes, kOz = thousand ounces
The Blueberry deposit was assessed to a combination of open pit and underground mining.
The Scottie
deposit, which was previously mined utilizing shrinkage stoping approximately 50 years ago, was
assessed as underground only.
The combined Resource material selected as ore sorter feed is summarized in Table 3 and the base
case production schedule used in the preliminary cashflow analysis is shown in Figure 1.
Figure 1:
Base Case Production Schedule over LOM
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/11118/272131_17cdb15b94598a7a_001full.jpg
Note: BB UG = Blueberry underground, Scottie UG = Scottie underground, BB OP = Blueberry open pit, Au = gold grade (g/t), kt = thousand tonnes
Metallurgy
Since 1980, numerous phases of metallurgical testing have been conducted on Scottie samples to
investigate the gravity-recoverable gold content, the cyanide leaching performance of head composite
samples, and the response of gravity tailings to flotation and cyanidation processes. These early studies
laid the groundwork for understanding the mineralization's behavior under conventional recovery
methods.
Beginning in 2024, the focus of metallurgical work shifted toward mill feed pre-concentration using ore
sorting and dense media separation (DMS).
Scottie Resources launched a particle sorting test program involving 210 quarter-core samples - 70
each from the Blueberry Open Pit (BBOP), Blueberry Underground (BBUG), and Scottie Gold Mine
Underground (SGMUG) zones. These samples, roughly 3 inches in size, were derived from broken drill
core and represented a broad spectrum of gold grades from each zone.
The primary objective of the program was to evaluate the effectiveness of separating target
mineralization from waste using X-ray scanning technologies. The results were analyzed across several
operational metrics, including feed grade, mass pull to product, gold recovery, sorted product grade,
rejected waste grade, and upgrade ratio.
Overall, the test program (
see NR dated April 1, 2025
) demonstrated that particle sorting was highly
effective across all zones using both XRT and XRF technologies. Notably, XRF outperformed XRT in
terms of mass pull to recovery ratio, particularly within the 30-60% mass pull range. Additionally, XRF
offered the advantage of enabling a three-way sort, allowing for the creation of a low-grade stockpile in a
single stage using commercially available sorting equipment.
Process Plant
Based on the results of the test work, a cost-effective processing flowsheet was developed to recover
and upgrade the mill feed into a saleable concentrate using ore sorting technique. The processing plant
includes the following components:
A primary crusher operates in closed-circuit with a triple-deck dry screen.
Coarse product from the dry screen is washed using a double-deck wet screen to prepare the feed
for ore sorter. Fine product from the dry screen is stockpiled and later blended with sorter
concentrate.
The two fractions (coarse & fine) from the wet screen are sorted separately using two X-ray
fluorescence (XRF) sorters to produce final concentrate, which is shipped directly overseas for
sale.
Wash water from the wet screen is recycled using a belt filter.
All the associated utilities required for plant operation are included.
Initial and Sustaining Capital Cost Estimates
The PEA estimates initial capital requirements of $128.6 million and cumulative sustaining capital of
$76.7 million (Table 4).
Table 4:
Initial and Sustaining Capital Costs
Initial Capital Item
Initial Capital
($ million)
Mining Infrastructure
$6.8
Site Access & Pads
$5.0
Site Services Mobile Equipment
$7.8
Process Plant
$26.2
Surface Infrastructure
$38.8
Project Indirects
$23.7
Owners Costs
$3.4
Contingency
$16.9
Total
$128.6
OP Mining - Preproduction
$4.5
Sustaining Capital Item
Sustaining Capital ($ million)
Mining
$73.1
Others
$3.6
Total Sustaining Capital
$76.7
Reclamation/Closure Costs
$15.0
All capital incurred up to the end of construction period, except pre-production mining ($4.5M), is
included in the Initial Capital. The PEA is based on contractor open pit and underground mining model.
Any capital required from operation commencement is included in Sustaining Capital. A total of $16.9
million in contingencies have been included in the Initial Capital which is approximately 20% of the Initial
Directs Costs.
Operating Cost Estimates
LOM operating costs for the Scottie Gold Mine DSO project are estimated to average $185.38 per
tonne sorted. During the start-up period, processing and general and administrative ("G&A") costs per
tonne are slightly higher until sorting throughput ramps up to design capacity. The PEA is based on
contractor open pit and underground mining, which has an estimated UG LOM cost of $118.1 per tonne
sorted and OP LOM cost of $6.95 per tonne mined. Processing costs are estimated at $17.96 per tonne
sorted, G&A and site services costs are estimated at $31.23 and $16.76 per tonne sorted, respectively.
The processing, G&A, and site services costs per tonne sorted are based on an estimated plant
operating time of 50% over the LOM with potential to improve these unit costs with potential utilization of
a leaching plant nearby (see section entitled Scottie Gold Mine Opportunities to Enhance Value below).
All-In Sustaining Cash Costs per Ounce of Gold Equivalent
AISC are estimated to be US$1,452/oz Au produced, based on LOM production of 457,600 recoverable
ounces Au.
Scottie Gold Mine Opportunities to Enhance Value
Of the studied project design components, the PEA demonstrates that the most profound improvement
to the project economics is toll milling the product at the nearby Premier mill (i.e. Table 1). No toll milling
arrangement is currently in place with the Premier mill, it is considered in the PEA as a recommendation
for further study work. The Premier mill is located halfway along the trucking route to the Stewart
Terminal. The model assumes appropriate operating costs derived from Ascot's 2020 Feasibility Study,
with an additional toll milling premium applied, similar to comparable toll milling projects. At US$2600/oz
gold the AISC for the toll milling model is calculated to be US$935 (versus US$1452 in the base-case
DSO model).
Several opportunities have been identified that may significantly enhance the economic return outlined in
the PEA, including but not limited to the following:
Toll milling: Additional opportunities of refinement on this concept include: (1) optimizing mine plan
and resource for reduced shipping costs (i.e. include more lower grade ounces), (2) removal of the
crushing/ore sorting plant, and (3) further metallurgical test work on the mineralization to maximize
recovery in a toll milling scenario. The results from our preliminary metallurgical test-work
suggested intensive leaching recoveries of up to 97% for both gold and gold gravity concentrates.
In the PEA, the cyanide leaching recoveries is set at 89.1%. Historic production and recent test
work suggests potential for improved gold recoveries of approximately 91-95% for gold. Scottie
intends to follow up these promising results with further test work to be completed and incorporated
into the Feasibility (FS).
Exploration Potential: The resource estimated for the PEA is based on the February 2025 Mineral
Resource Estimate, which includes the Blueberry Zone, Scottie Gold Mine, and Bend vein. With
success on further drilling, there are several ways that expanded resources could improve the
economics of the project, including higher throughput, extended mine life, and bringing in additional
isolated stopes left off the PEA mine plan due to development costs.
Throughput Expansion: The mine plan for the PEA is based on a 900 tpd throughput scenario,
which results in a 7-year mine life. Expanded resources have the potential to justify increased mine
and mill throughput. As part of the upcoming Feasibility Study (FS), Scottie will evaluate the
potential costs to expand the process plant capacity to 1,500-2,000 tpd with potential benefits to
unit costs for processing and G&A with respect to economies of scale.
Reduced Development Cost per Ounce: Blueberry and Scottie Gold Mine underground deposits
have relatively high development costs per ounce of mineral resource. Expanding the resource for
these areas would spread the relatively high development capital over more ounces, improving
economics and reducing the AISC per ounce.
Power Line: The PEA assumes the use of onsite generated power using conventional fuel at
$0.26/KWH or higher and exposes the operation to fluctuations in the price of fuel. The FS will
investigate the contemplation of the connection of the site to the BC Hydro grid via power available
at an estimated cost of $0.07/KWH.
Feasibility Study
With the PEA completed, Scottie is moving forward with a Feasibility Study for the Scottie Gold Mine
project. The Company is targeting completion of the FS in H1, 2027 and making a production decision
following the release of a positive study. The on-going FS data collections and engineering will allow us
to conduct detailed feasibility work including further metallurgy, assess geotechnical conditions,
reconcile underground grades with the resource model, complete test mining to define the optimum
mining method, and determine more accurate development costs.
The recommended budget for the FS, field support for the study, ongoing exploration work,
environmental work, infill drilling, upgrading mineral resources to mineral reserves and construction
planning over the next 12 months is estimated at $25 million.
Tetra Tech's work to complete the PEA, demonstrates that the Scottie Gold Mine project has robust
economic potential and recommends that Scottie continue developing the project with emphasis on the
exploration work required to improve confidence in inferred resources.
Qualified Persons
The Independent Qualified Persons, as defined in NI 43-101 for the PEA and who have reviewed and
approved the contents of this news release are Hassan Ghaffari, P. Eng., M.A.Sc., Jianhui (John) Huang,
PhD, P. Eng. from Tetra Tech, and Damian Gregory, P. Eng. from Snowden Optiro, and Sue Bird, P.
Eng. from Moose Mountain Technical Services.
The Technical Report, "NI 43-101 2025 Maiden Mineral Resource Estimate for the Scottie Gold Mine
Project" for the Scottie Gold Mine Property, British Columbia, Canada, effective February 2, 2025 and
announced on June 24, 2025, has been filed on SEDAR+.
Dr. Thomas Mumford, P.Geo., President of the Company and a non-independent qualified person under
National Instrument 43-101, has reviewed and approved the technical information contained in this news
release on behalf of the Company.
ABOUT SCOTTIE RESOURCES CORP.
Scottie Resources holds 100% interest in the Scottie Gold Mine Property, which includes the high-grade,
past-producing Scottie Gold Mine and the adjacent Blueberry Contact Zone. The Company also owns a
100% interest in the Georgia Project, host to the past-producing Georgia River Mine, as well as the
Cambria, Sulu, and Tide North properties. In total, Scottie controls approximately 58,500 hectares of
highly prospective mineral claims within the Stewart Mining Camp in British Columbia's Golden Triangle-
one of the world's most prolific mineralized districts.
Scottie's current resource estimate on the Scottie Gold Mine Project includes a total of 703,000 gold
ounces at an average grade of 6.1 g/t (Inferred category), highlighting the potential for a significant near-
surface, high-grade deposit. The Company's strategy is to continue expanding this resource and to
define additional mineralization around past-producing mines through systematic drilling and surface
exploration.
In parallel, Scottie is evaluating a potential Direct Shipping Ore (DSO) scenario at the Scottie Gold Mine.
With permits in hand, a 10,000-tonne bulk sample is underway. This initiative provides an opportunity to
collect key geotechnical and metallurgical data while assessing a low-capex path to potential near-term
revenue through toll milling or third-party processing. This DSO concept does not imply a production
decision but reflects the optionality embedded in Scottie's portfolio.
Additional Information
Brad Rourke
Chief Executive Officer