Scottie Resources Announces 15,000 M Drill and Exploration Program ON Its Scottie GOLD MINE Project
SCOTTIE RESOURCES ANNOUNCES 15,000 M DRILL AND EXPLORATION
PROGRAM ON ITS SCOTTIE GOLD MINE PROJECT
VANCOUVER, BC
,
June 9, 2022
/CNW/ - Scottie Resources Corp. ("
Scottie
" or the "
Company
") (TSXV: SCOT) (OTCQB: SCTSF) (FSE: SR8) is pleased to
announce plans for a 15,000 metre drill program on the Company's flagship asset, the Scottie Gold Mine Project, located in BC's Golden Triangle. The drill
program is planned to commence in late June and continue into the fall using three diamond drill rigs. Approximately 12,000 metres will test the Blueberry Contact
Zone, with the remaining metres allocated to the Scottie Gold Mine as well as ancillary early stage targets. The Blueberry Contact Zone is located 2 km north-
northeast of the 100% owned past-producing high-grade Scottie Gold Mine, 35 km north of the town of
Stewart, BC
along the Granduc Road.
"Since delivering the outstanding drill results from 2021 which unlocked the clear potential of the Blueberry Contact Zone, our geological team has been diligently
planning an ambitious follow-up drill program." comments President and CEO,
Brad Rourke
: "The focus of drilling at Blueberry will be shared between extending
the strike length of the zone, infill between established zones of mineralization, and testing continuity of the structures to depth. We've also developed a number of
other high-priority targets at the Scottie Gold Mine Project that have the potential to significantly enhance the scale of the existing discoveries. We are excited to
return to site and get the drills turning again."
2022 Drill Program Overview
The drill program will commence in late-June to early-July (snow melt dependant) with three skid-based drills, two on the Blueberry Contact Zone, and one testing
other local high-priority targets. In early August two of the drills will transition to fly-drills and test targets around the Scottie Gold Mine, as well as other helicopter
accessible sites. In September the fly-drills will transition back to being skid-based in order to follow-up on results generated at the beginning of the season.
Blueberry Drilling
After making the Blueberry Contact Zone discovery in 2019 the geology team at Scottie developed a new geological model which transformed the Blueberry
target from a single vein to a property scale structural feature. This model which was tested throughout the 2021 field season has helped define the architecture
of the system, which links several widely spaced high-quality targets along a common structure. Testing during 2022 of well-developed targets will double the
existing strike length of the system, potentially extending the zone to >1,400 metres. Combining multiple geophysical data sets, extensive mapping and surficial
sample data has allowed the team to extrapolate the structure beneath the historic lakebed, in order to generate high-confidence drill targets. Drilling during 2019-
2021 focused on drill testing beneath high-grade mineralization outcropping at surface. Due to overburden coverage along the contact zone, multiple areas have
no surficial expression, creating gaps in the drill density along the known structure. Short infill holes during 2022 will test these areas in order to connect the
already established high-grade zones. One of the deepest holes of 2021 (SR21-138) intersected 15.3 g/t gold over 13.49 metres at a depth of 225 metres, and
additional drilling will prioritize further extending mineralization at depth.
2022 Exploration Fieldwork
In addition to drilling, the company will be carrying out a high-resolution LiDAR survey, as well as ground-based EM surveys on the Scottie Gold Mine Project, with
the aim of further extending the Blueberry Contact Zone to the south beneath the historic lakebed. Detailed geological mapping and sampling will be conducted on
a variety of gold and polymetallic targets on the Company's >25,000 ha Cambria Project located adjacent to the town of
Stewart, BC
. The Cambria Project hosts
multiple small past-producing silver-rich polymetallic mines. and this season's exploration work will be focused on developing drill targets to test and advance the
property's potential.
Figure 1: Plan map outlining the proposed 2022 drill plan on the Blueberry Contact Zone. (CNW Group/Scottie Resources Corp.)
Figure 2: Grade thickness interpolated contour model of the Blueberry Zone. The contours are based on the drill holes intercepts and do not represent true
thicknesses. Drilled pierce points are displayed to provide some context relating to the drill hole density and the impact of interpolation in areas of little to no
drilling. The model has an average thickness of ~15 metres and the viewed window is ±50 metres. (CNW Group/Scottie Resources Corp.)
About the Blueberry Contact Zone
The Blueberry Zone is located just 2 km northeast of the 100% owned, past-producing Scottie Gold Mine located in
British Columbia, Canada's
Golden Triangle
region. Historic trenching and channel sampling of the Blueberry Vein include results of 103.94 g/t gold over 1.43 metres, and 203.75 g/t gold over 1.90 metres.
Despite high-grade surficial samples and easy road access, the Blueberry Vein had only limited reported drilling prior to the Company's exploration work. The
target was significantly advanced during Scottie's 2019 drill program when an interval grading 7.44 g/t gold over 34.78 metres was intersected in a new splay off
zone of the main Blueberry Vein. The drill results received in 2020 and 2021, coupled with surficial mapping and sampling suggest that this splay is in fact a major
N-S mineralized structure, of which the Blueberry Vein was only a secondary structure. This zone is much wider than pursued in previous exploration models and
drilling in 2021 expanded its strike length to 720 meters and its depth to 225 meters. The zone is steeply dipping, and there is no current restraint on its potential
depth; the mineralization at the adjacent Scottie Gold Mine has a vertical extent greater than
450 m
. The Blueberry Zone is located on the Granduc Road, 20 km
north of the Ascot Resources' Premier Project, which is in the process of refurbishing their mill in anticipation of production in 2022 (
August 10, 2021
). Newcrest's
Brucejack Mine is located 25 km to the north.
Thomas Mumford
, Ph.D., P.Geo and VP Exploration of Scottie, a qualified person under National Instrument 43-101, has reviewed the technical information
contained in this news release on behalf of the Company.
ABOUT SCOTTIE RESOURCES CORP.
Scottie owns a 100% interest in the high-grade, past-producing Scottie Gold Mine and Bow properties and has the option to purchase a 100% interest in
Summit
Lake
claims which are contiguous with the Scottie Gold Mine property. Scottie also owns 100% interest in the Georgia Project which contains the high-grade
past-producing
Georgia River Mine
, as well as the Cambria Project properties and the Sulu property. Altogether Scottie Resources holds more than 52,000 ha of
mineral claims in the Stewart Mining Camp in the Golden Triangle.
The Company's focus is on expanding the known mineralization around the past-producing mines while advancing near mine high-grade gold targets, with the
purpose of delivering a potential resource. The Company's focus is on expanding the known mineralization around the past-producing mine while advancing near
mine high-grade gold targets, with the purpose of delivering a potential resource.
All of the Company's properties are located in the area known as the Golden Triangle of
British Columbia
which is among the world's most prolific mineralized
districts.
Forward Looking Statements
This news release may contain forward–looking statements. Forward looking statements are statements that are not historical facts and are generally, but not
always, identified by the words "expects", "plans", "anticipates", "believes", "intends", "estimates", "projects", "potential" and similar expressions, or that events or
conditions "will", "would", "may", "could" or "should" occur. Although the Company believes the expectations expressed in such forward–looking statements are
based on reasonable assumptions, such statements are not guarantees of future performance and actual results may differ materially from those in forward
looking statements. Forward–looking statements are based on the beliefs, estimates and opinions of the Company's management on the date such statements
were made. The Company expressly disclaims any intention or obligation to update or revise any forward–looking statements whether as a result of new
information, future events or otherwise.
Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of TSX Venture Exchange) accepts
responsibility for the adequacy of accuracy of this release.
View original content to download multimedia:
https://www.prnewswire.com/news-releases/scottie-resources-announces-15-000-m-drill-and-exploration-program-on-its-scottie-gold-mine-project-301564885.html
SOURCE
Scottie Resources Corp.
View original content to download multimedia:
http://www.newswire.ca/en/releases/archive/June2022/09/c5469.html
%SEDAR: 00031828E
For further information:
Brad Rourke, President and CEO, +1 250 877 9902, [email protected]; Gordon Robb, Business Development, +1 250 217
2321, [email protected]