Atlas Salt Submits Early Works Development Plan for Great Atlantic Salt Project

St. John's, Newfoundland and Labrador – February 28, 2025 - Atlas Salt Inc. (“Atlas

Salt” or the “Company”) (TSXV: SALT; OTCQB: REMRF) is pleased to announce the

formal submission of the Early Works Mine Development and Rehabilitation and

Closure Plan (the “Early Works Development Plan”) to the Department of Industry,

Energy and Technology for the Government of Newfoundland and Labrador, for the

Great Atlantic Salt Project (the “Project”) in Newfoundland and Labrador, Canada.

The submission of the Early Works Development Plan marks a critical milestone in

advancing the Project toward construction. This plan outlines the phased approach

for site preparation and early-stage infrastructure development, ensuring regulatory

compliance while de-risking key project components ahead of full-scale mine

construction.

Key Components of the Early Works Development Plan

 Site Preparation: Clearing and grubbing activities, stockpile pad grading, and

initial earthworks to establish the mine site footprint.

 Primary and Secondary Access Roads: Construction of a 1.3 km primary

access road from Steel Mountain Road and a 300 m secondary access route

along the planned conveyor corridor.

 Surface Infrastructure: Development of laydown areas, temporary

construction facilities, and essential utilities to support subsequent project

phases.

 Sediment and Erosion Control Measures: Implementation of stormwater

management systems, catchment ditches, and a temporary settling basin to

mitigate environmental impacts.

 Regulatory Compliance and Permitting: Submission of required approvals for

road access, site disturbance, and water management infrastructure, ensuring

alignment with provincial environmental guidelines.

2

TSXV: SALT

100 New Gower Street, Suite 910

St. John’s, NL A1C 6K3

Telephone: (709) 739-9545

AtlasSalt.com

[email protected]

The Early Works Development Plan enables Atlas Salt to initiate critical site activities

ahead of full project execution, accelerating timelines for major construction phases.

By proactively addressing key infrastructure and environmental management

requirements, the Company aims to optimize the transition into mine development

while maintaining a rigorous approach to regulatory compliance.

Richard LaBelle, CEO of Atlas Salt, commented: “The submission of the Early Works

Development Plan represents another significant step in de-risking the Great Atlantic

Salt Project and positioning Atlas Salt as a leading low-cost producer in the North

American salt market. This milestone ensures we remain on track for the timely

development of critical project infrastructure, paving the way for commercial

production.”

Pending governmental review and approval, Early Works construction is expected to

commence in 2025, with subsequent phases progressing in alignment with the

overall project schedule.

For further information and ongoing updates, please visit https://atlassalt.com.

About Atlas Salt Inc.

Atlas Salt Inc. is developing Canada’s next salt mine and is committed to responsible

and sustainable mining practices. With a focus on innovation and efficiency, the

company is poised to make significant contributions to the North American salt

market while upholding its values of environmental stewardship and community

engagement.

For information, please contact:

Richard LaBelle, CEO

[email protected]

(709) 739-9545

We seek safe harbor.

Cautionary Statement

3

TSXV: SALT

100 New Gower Street, Suite 910

St. John’s, NL A1C 6K3

Telephone: (709) 739-9545

AtlasSalt.com

[email protected]

Neither the TSX Venture Exchange nor its Regulation Services Provider, (as the term is

defined in the Policies of the TSX Venture Exchange) accepts responsibility for the adequacy

or accuracy of this release. This press release includes certain “forward-looking

information” and “forward-looking statements” (collectively “forward-looking statements”)

within the meaning of applicable Canadian securities legislation. All statements, other

than statements of historical fact, included herein, without limitation, statements relating

to the future operating or financial performance of the Company, are forward-looking

statements. Forward-looking statements are frequently, but not always, identified by

words such as “expects”, “anticipates”, “believes”, “intends”, “estimates”, “potential”,

“possible”, and similar expressions, or statements that events, conditions, or results “will”,

“may”, “could”, or “should” occur or be achieved. Forward-looking statements in this press

release relate to, among other things: obtaining financing, completion, delivery and timing

of project components and requirements, and analysis and assumptions related thereto.

Actual future results may differ materially. There can be no assurance that such

statements will prove to be accurate, and actual results and future events could differ

materially from those anticipated in such statements. Forward-looking statements reflect

the beliefs, opinions and projections on the date the statements are made and are based

upon a number of assumptions and estimates that, while considered reasonable by the

respective parties, are inherently subject to significant business, technical, economic, and

competitive uncertainties and contingencies. Many factors, both known and unknown,

could cause actual results, performance or achievements to be materially different from

the results, performance or achievements that are or may be expressed or implied by such

forward-looking statements and the parties have made assumptions and estimates based

on or related to many of these factors. Such factors include, without limitation: the timing,

completion and delivery of required permits, supply arrangements and financing. Readers

should not place undue reliance on the forward-looking statements and information

contained in this news release concerning these times. Except as required by law, the

Company does not assume any obligation to update the forward-looking statements of

beliefs, opinions, projections, or other factors, should they change, except as required by

law.