FOR IMMEDIATE RELEASE

Atlas Salt Announces De-risked Development Schedule for Great Atlantic Salt

Project

St. John's, Newfoundland and Labrador – August 12, 2024 - Atlas Salt Inc. (“Atlas

Salt” or the “Company”) (TSXV: SALT; OTCQB: REMRF) is pleased to announce a de-

risked development schedule for the Great Atlantic Salt Project (the “Project”) with

3rd party review and verification by Tamkali Limited (“T amkali”), an independent

provider of Project Development and Control Services with a focus on the Mining

Industry.

The Company previously disclosed a schedule for the Project in a technical report,

supported by a feasibility study (“Feasibility Study”) prepared by SLR Consulting

(Canada) Ltd. (“SLR”), which was filed on SEDAR+ on October 12, 2023 , as amended

and refiled on May 1, 2024 . That feasibility schedule assumed a duration of 6 2

months, following project sanctioning that does not account for sourcing, timing and

preconditions for securing financing, all of which were not part of SLR’s scope of

work.

Over the past year, Atlas Salt has made key advances , such as obtaining provincial

environmental assessment (“EA”) release for the Project, addressing EA conditions,

acquiring surface rights, advancing permitting, advancing geotechnical studies ,

securing long-lead critical equipment and major components, sourcing off -take

partnerships and agreements, completing greenhouse gas intensity and economic

impact studies, and technical de-risking of the Project , which are all necessary

preconditions for securing financing packages.

Following a rigorous review and optimization process, the Company has reduced the

Project’s schedule duration to 59 months, a 5% improvement compared to the

Feasibility Study. As verified by Tam kali, this achievement reflects critical feedback

from regulators, vendors, and industry experts, resulting in a more detailed and

robust project execution plan.

2

TSXV: SALT

100 New Gower Street, Suite 910

St. John’s, NL A1C 6K3

Telephone: (709) 739-9545

AtlasSalt.com

[email protected]

The updated schedule includes a target date in the first half of 2025 for securing

project financing. While Atlas Salt is working towards meeting this target, the

Company acknowledges the inherent risks and uncertainties in achieving this date.

Should financing be delayed , the planned Project schedule will be adjusted

accordingly, with ongoing monitoring and management by the Company.

Richard LaBelle, CEO, noted, "Our ability to prudently manage our resources to

further build momentum while working within our current cash position is a

testament to our team's capabilities and determination to advanc e our world class

project."

Key Enhancements to the Project Schedule:

• Increased Detail: At this stage of the project, the level of detail in the schedule

has been doubled, ensuring a comprehensive representation of all project

activities. This enhancement supports more effective monitoring and control

of the Project’s progress.

• PERT Analysis and Monte Carlo Simulation: A full Program Evaluation and

Review Technique ( “PERT”) analysis has been conducted, accompanied by a

Monte Carlo simulation to address schedule risks and duration uncertainties.

This dual approach has provided a more realistic and resilient schedule that

anticipates potential challenges and mitigates associated risks.

• Oracle Primavera Cloud Software: The scheduling work was performed

using Oracle Primavera Cloud, a leading scheduling software. This platform

enhances the precision and flexibility of the schedule while ensuring a

seamless transition into the construction phase, supporting the Project’s long-

term success. Additionally, Atlas Salt is currently implementing Oracle Aconex

and Oracle Netsuite systems, which together will form an integrated

scheduling, construction management, costing, procurement and financial

controls system.

• Quality Assurance Review: The revised schedule underwent a quality

assurance review by Tamkali, an independent project services and controls

3

TSXV: SALT

100 New Gower Street, Suite 910

St. John’s, NL A1C 6K3

Telephone: (709) 739-9545

AtlasSalt.com

[email protected]

advisory firm. The review confirmed that the schedule serves as a robust

baseline for project execution, capable of accommodating future project

phases, including construction and commissioning.

A graphic illustrating the high -level project schedule reflecting the 3-month

improvement and estimated ranges, is included below.

Figure 1 - Updated Overall Project Schedule

Tamkali’s President, Will van Niekerk , highlighted, "Our Independent peer review of

the de-risked Project schedule found that it is representative of the execution

strategy and can effectively be used to establish an initial baseline for the Project's

timeline, ensuring that the key milestones for management, engineering,

procurement, construction and commissioning are defined and achievable. This

foundation will support a baseline upon which permitting, engineering, and

associated activities can be built to ensure transparent progression of the Project as

it advances through its subsequent phases."

Richard LaBelle, CEO, commented: "This schedule improvement is a testament to our

commitment to building the Great Atlantic Salt Project. By integrating expert insights

from Tamkali and advanced risk analysis, we have strengthened our confidence in

the Project’s successful execution. We are excited about the progress made and are

fully dedicated to advancing the Project with a focus on operational excellence and

stakeholder value."

4

TSXV: SALT

100 New Gower Street, Suite 910

St. John’s, NL A1C 6K3

Telephone: (709) 739-9545

AtlasSalt.com

[email protected]

For further information and ongoing updates, please visit https://atlassalt.com/.

For further information about Tamkali, please visit https://tamkali.ca/.

Scientific and Technical Information

The scientific and technical information contained in this news release has been

approved by Andrew Smith, P.Eng., Mine Project Manager, who is a "Qualified

Person" for the purposes of NI 43-101.

About Atlas Salt Inc.

Atlas Salt Inc. is developing Canada’s next salt mine and is committed to responsible

and sustainable mining practices. With a focus on innovation and efficiency, the

company is poised to make significant contributions to the North American salt

market while upholding its values of environmental stewardship and community

engagement.

For information, please contact:

Richard LaBelle, CEO

[email protected]

We seek safe harbor.

Cautionary Statement

Neither the TSX Venture Exchange nor its Regulation Services Provider, (as the term is

defined in the Policies of the TSX Venture Exchange) accepts responsibility for the adequacy

or accuracy of this release. This press release includes certain “forward -looking

information” and “forward-looking statements” (collectively “forward-looking statements”)

within the meaning of applicable Canadian securities legislation. All statements, other

than statements of historical fact, included herein, without limitation, statements relating

to the future operating or financial performance of the Company, are forward -looking

statements. Forward -looking statements are frequently, but not always, identified by

words such as “expects”, “anticipates”, “believes”, “intends”, “e stimates”, “potential”,

5

TSXV: SALT

100 New Gower Street, Suite 910

St. John’s, NL A1C 6K3

Telephone: (709) 739-9545

AtlasSalt.com

[email protected]

“possible”, and similar expressions, or statements that events, conditions, or results “will”,

“may”, “could”, or “should” occur or be achieved. Forward-looking statements in this press

release relate to, among other things: obtaining financing, completion, delivery and timing

of project components and requirements, and analysis and assumptions related thereto.

Actual future results may differ materially. There can be no assurance that such

statements will prove to be accurate, and actual results and future events could differ

materially from those anticipated in such statements. Forward-looking statements reflect

the beliefs, opinions and projections on the date the statements are made and are based

upon a number of assumptions and estimates that , while considered reasonable by the

respective parties, are inherently subject to significant business, technical, economic, and

competitive uncertainties and contingencies. Many factors, both known and unknown,

could cause actual results, performance or achievements to be materially different from

the results, performance or achievements that are or may be expressed or implied by such

forward-looking statements and the parties have made assumptions and estimates based

on or related to many of these factors. Such factors include, without limitation: the timing,

completion and delivery of required permits, supply arrangements and financing. Readers

should not place undue reliance on the forward -looking statements and information

contained in this news releas e concerning these times. Except as required by law, the

Company does not assume any obligation to update the forward -looking statements of

beliefs, opinions, projections, or other factors, should they change, except as required by

law.