REVIVAL GOLD PROVIDES UPDATE

ON BEARTRACK-ARNETT PREFEASIBILITY STUDY

Toronto, ON – February 27th, 2023 – Revival Gold Inc. (TSXV: RVG, OTCQX: RVLGF) (“Revival Gold”

or the “Company”), is pleased to provide an update on the Company’s first phase heap leach

restart Prefeasibility Study (“PFS”) underway on the Beartrack-Arnett Gold Project (“Beartrack -

Arnett” or the “Project”) located in Lemhi County, Idaho, USA.

The PFS is being led by industry leaders Kappes Cassiday & Associates (“KCA”) and Independent

Mining Consultants Inc. (“IMC”) . The PFS remains on track for completion by mid -2023. Key

developments are as follows:

• IMC has developed draft updated heap leach mineral resource models and mine plans for

both the main deposit (Beartrack) and the satellite deposit (Haidee) at Beartrack-Arnett that

incorporate 2022 drilling results. These items are under review; however, the draft leach

resource models and mine plans are in-line with Revival Gold’s objective to see average

production in the PFS at 65,000 to 70,000 ounces gold per year over a 7 to 9 year mine life;

• Mill resource models that include the high -grade Joss area will be updated once the leach

models are complete. Undated resource models for both heap leach and mill material will

be incorporated into a new Mineral Resource estimate for Beartrack-Arnett, which will be

released with the PFS;

• KCA and IMC have completed trade-off studies to optimize heap leach mine sequencing,

waste rock management, cell layouts and sequencing, haul road alignments, and crusher

locations. These studies were key to moving forward with earthworks calculations, water

balance modeling, bid package preparation, and drawing package development;

• PFS drawing packages are progressing on schedule and include process flowsheets (100%

complete), piping & instrumentation diagrams (100% complete), general arrangement

drawings (75% complete), overall site layout drawings (65% complete), electrical drawings

(15% complete), and leach pad details & stacking plans (10% complete);

• Idaho Power Company (“IPCo”) has completed a power study to assess upgrades required

to the existing 69 kV service to site to support the PFS. The IPCo upgrades include substation

and other electrical system infrastructure improvements to increase the reliability and

availability of power to the Project;

• An assessment of existing site fa cilities and infrastructure has been completed and all

required plant and mobile equipment requirements have been determined . KCA has

developed eleven bid packages in support of cost estimating for the PFS , and quotes are

actively being received, reviewed, and incorporated into a draft PFS financial model;

2

• Process and sitewide water balance models have been developed and are being updated

iteratively with the overall PFS designs. Meteorological modeling was completed in early

2023 to support the PFS water balance models; and,

• Synthetic Precipitation Leaching Procedure geochemical testing on representative Haidee

waste rock samples was completed in February 2023. These results will be compared with

Acid Base Accounting testing completed in 2022 to develop predictions for operational and

post-operational geochemical behavior of Haidee waste rock in support of the PFS closure

plan.

“We are encouraged by the progress KCA and IMC are making on the PFS for the first phase re-start

of gold production at Beartrack -Arnett. Under the direction of Revival Gold’s VP, Engineering &

Development, John Meyer, the PFS and updated Mineral Resource estimate remains on track for

delivery by mid -2023. Meanwhile, Revival Gold’s exploration team, led by VP, Exploration, Steve

Priesmeyer, is continuing to advance preparations for this summer’s field season. Key target areas

for 2023 in support of Revival Gold’s fi rst phase re -start plans include open pit oxide resource

expansion opportunities at Haidee and other new open pit oxide targets across the western side of

Beartrack-Arnett,” said Hugh Agro, President and CEO.

Qualified Persons

John P.W. Meyer, P.Eng., Vice President Engineering and Development is the Company’s designated

Qualified Person for this news release within the meaning of National Instrument 43-101 Standards

of Disclosure for Mineral Projects and ha s reviewed and approved its scientific and technical

content.

About Revival Gold Inc.

Revival Gold Inc. is a growth-focused gold exploration and development company. The Company is

advancing the Beartrack-Arnett Gold Project located in Idaho, USA.

Beartrack-Arnett is the largest past -producing gold mine in Idaho. Engineering work has been

initiated on a Preliminary Feasibility Study (“PFS”) for the potential restart of heap leach operations.

Meanwhile, exploration continues, focused on expanding the 2022 Indicated Mineral Resource of

65.0 million tonnes at 1.01 g/t gold containing 2.11 million ounces of gold and Inferred Mineral

Resource of 46.2 million tonnes at 1.31 g/t gold containing 1.94 million ounces of gold (see Revival

Gold NI -43-101 Technical Report by Wood plc dated July 13th, 2022, for further details). The

mineralized trend at Beartrack extends for over five kilometers and is open on strike and at depth.

Mineralization at Arnett is open in all directions.

Revival Gold has approximately 91.9 million shares outstanding and a cash balance of C$3.2 million

as of December 31 st, 2022. All figures in this news release are in metric units and in $US unless

3

stated otherwise. Additional disclosure including the Company’s financial statements, technical

reports, news releases and other information can be obtained at www.revival-gold.com or on

SEDAR at www.sedar.com.

For further information, please contact:

Hugh Agro, President & CEO or Melisa Armand, Investor Relations

Telephone: (416) 366-4100 or Email: [email protected]

Cautionary Statement

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX

Venture Exchange) accepts responsibility for the adequacy or accuracy of this news release.

This news release includes certain “forward-looking information” within the meaning of Canadian securities legislation

and “forward -looking statements” within the meaning of U.S. securities legislation (collectively “forward -looking

statements”. Forward -looking statements are not comprised of historical facts. Forward -looking statements include

estimates and statements that describe the Comp any’s future plans, objectives or goals, including words to the effect

that the Company or management expects a stated condition or result to occur. Forward -looking statements may be

identified by such terms as “believes”, “anticipates”, “expects”, “estimates”, “may”, “could”, “would”, “will”, or “plan”.

Since forward-looking statements are based on assumptions and address future events and conditions, by their very

nature they involve inherent risks and uncertainties. Although these statements are based on information currently

available to the Company, the Company provides no assurance that actual results will meet management’s

expectations. Risks, uncertainties, and other factors involved with forward -looking statements could cause actual

events, results, performance, prospects, and opportunities to differ materially from those expressed or implied by such

forward-looking statements. Forward looking statements in this news release includes, but is not limited to, the size of

the Financing, the completion, terms and expected closing date of the Financing, the Company’s objectives, goals or

future plans, statements, exploration results, potential mineralization, the estimation of mineral resources, exploration

and mine development plans, timing of the commencement of operations and estimates of market conditions. Factors

that could cause actual results to differ materially from such forward-looking statements include, but are not limited to

failure to identify mineral resources, failure to convert estimated mi neral resources to reserves, the inability to

complete a feasibility study which recommends a production decision, the preliminary nature of metallurgical test

results, delays in obtaining or failures to obtain required governmental, environmental or other project approvals,

political risks, uncertainties relating to the availability and costs of financing needed in the future, changes in equity

markets, inflation, changes in exchange rates, fluctuations in commodity prices, delays in the development of projects,

capital, operating and reclamation costs varying significantly from estimates and the other risks involved in the mineral

exploration and development industry, an inability to raise additional funding, the manner the Company uses its cash

or the proceeds of an offering of the Company’s securities, an inability to predict and counteract the effects of COVID -

19 on the business of the Company, including but not limited to the effects of COVID -19 on the price of commodities,

capital market conditions, restriction on labour and international travel and supply chains, and those risks set out in the

Company’s public documents filed on SEDAR. Although the Company believes that the assumptions and factors used in

preparing the forward-looking statements in this news release are reasonable, undue reliance should not be placed on

such information, which only applies as of the date of this news release, and no assurance can be given that such events

will occur in the disclosed time frames or at all. The Company di sclaims any intention or obligation to update or revise

any forward-looking statements, whether as a result of new information, future events or otherwise, other than as

required by law.