Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

RVG.V ·

Revival GOLD Marks Impressive Continued Growth IN Mineral Resource and Advances Open Pit Heap Leach Restart Plans with PFS

Metallurgy & Processing

1

REVIVAL GOLD MARKS IMPRESSIVE CONTINUED GROWTH IN

MINERAL RESOURCE AND ADVANCES

OPEN PIT HEAP LEACH RESTART PLANS WITH PFS

Toronto, ON – July 11th, 2023 – Revival Gold Inc. (TSXV: RVG, OTCQX: RVLGF) (“Revival Gold” or

the “Company”), is pleased to report impressive continued growth in the Company’s Mineral

Resources and the completion of a Preliminary Feasibility Study (“PFS”) on the potential open

pit heap leach restart of the Beartrack-Arnett Gold Project (“Beartrack-Arnett” or the “Project”)

located in the western United States.

Mineral Resource Update Highlights

• The updated Mineral Resource is based on 172,244 meters of drilling through the end of

2022 and contains:

• A Measured & Indicated Mineral Resource of 86.2 million tonnes at 0.87 g/T gold

containing 2. 42 million ounces of gold 1, an increase of 14% over the 2022

Measured & Indicated Mineral Resource2; and,

• An Inferred Mineral Resource of 50.7 million tonnes at 1. 34 g/T gold containing

2.19 million ounces of gold 1, an increase of 13% over the 2022 Inferred Mineral

Resource2;

• Contained gold in open pit heap leach Measured & Indicated Resources increased 142%2

to 42.3 million tonnes at 0.70 g/T gold containing 959,000 ounces of gold with additional

Inferred Resources of 6.3 million tonnes at 0.53 g/ T gold containing 108,000 ounces of

gold; and,

• Contained gold in underground mill Inferred Resources increased 180% to 6.7 million

tonnes at 4.0 g/ T gold containing 877,000 ounces of gold with a 33% increase in grade

over the 2022 Inferred Mineral Resource2.

Open Pit Heap Leach Restart PFS Highlights

• Inaugural Proven & Probable open pit heap leach Mineral Reserve of 36.2 million tonnes

at 0.74 g/T gold for 859,000 ounces of gold3;

• Average gold production of 65,300 ounces of gold per year, for a total of 529,100 ounces

of gold over an eight-year mine life;

1 Estimates based on a gold price of $1,900 per ounce. See Tables 1 and 2 for additional assumptions. All figures in this news

release are in Metric units and in $US unless stated otherwise.

2 See Revival Gold’s May 16th, 2022, news release and NI 43-101 Technical Report by Wood plc dated July 13th, 2022.

3 Proven and Probable Mineral Reserves were estimated at a gold price of $1,700 per ounce.

2

• Pre-production capital of $ 109 million, working capital of $5 million, and life -of-mine

(“LOM”) sustaining capital of $ 100 million, reflecting only a modest increase in capital

relative to the 2020 Preliminary Economic Assessment;

• Total cash cost of $986 per ounce and All-In Sustaining Cost (“AISC”) of $1,235 per ounce

of gold;

• After-tax NPV at a 5% discount rate (“NPV5%”) of $105 million and after-tax IRR of 24.3%

at $1,800 per ounce gold increasing to an NPV5% of $138 million and after-tax IRR of 29.5%

at $1,900 per ounce gold;

• After-tax payback period of 3.4 years at $1,800 per ounce gold decreasing to 3.1 years

at $1,900 per ounce gold;

• Low technical and execution risk of a brownfield project with existing infrastructure ,

minimal pre-production earthworks and mine pre-stripping, limited planned disturbance

outside the Project’s current footprint, and a high proportion of low-risk pre-production

capital expenditures on mechanical equipment;

• Excellent additional exploration potential with exploration drilling currently underway

on high grade open pit oxide opportunities at Roman’s Trench and Haidee that offer near

term opportunities to extend the open pit heap leach PFS mine life; and,

• Opportunity to pursue a potential second phase mill operation with Mineral Resources

that provide optionality to begin underground or with an open pit, or concurrently

develop both.

“Completion of this PFS marks a significant de-risking milestone for Revival Gold”, said Hugh Agro,

President & CEO. “Beartrack -Arnett presents a unique opportunity for meaningful US gold

production from a low-risk, low capital restart of an established domestic mine site. The project

features robust economics including an attractive 24% after -tax IRR at $1,800 gold which

increases to 30% at current prices”, added Agro.

“Beyond the first phase of open pit heap leach production addressed in the PFS, potential exists

for Revival Gold to pursue a second phase of underground and open pit mill operations. The more

than doubling in Measured & Indicated open pit heap leach resources and near tripling of

underground Inferred resources reflected in today’s update speaks to the impressive ongoing

exploration and development potential at Beartrack-Arnett. With completion of the PFS, Revival

Gold is now positioned to progress environmental and permitting preparations, fine tune

engineering and design plans and advance the proposed Beartrack-Arnett project schedule .

Meanwhile, exploration continues with drilling having resumed this month”, said Agro.

The Mineral Resource estimate, Mineral Reserve estimate, and PFS were prepared in accordance

with National Instrument 43 -101 (“NI 43 -101”) by Kappes, Cassiday & Associates (“KCA”),

3

Independent Mining Consultants, Inc. (“IMC”), KC Harvey Environmental (“KC Harvey”) and WSP

USA Environmental & Infrastructure Inc. ( “WSP”), collectively the “Study Authors”, with an

effective date of June 30th, 2023. The Company will file a technical report summarizing the PFS

on www.revival-gold.com and on SEDAR at www.sedar.com in accordance with NI 43-101 within

45 days.

Conference Call

Management will host a conference call later this morning to discuss the results of the Mineral

Resource update and PFS. Call-in information below:

Scheduled Start: Tuesday, July 11th, 2023, 10:00 am EST

Call-In Number: 416-764-8658

Toll Free in North America: 888-886-7786

A replay of the conference call will be available for one week at 416-764-8691 or toll free in North

America at 877-674-6060. Playback passcode 416972#.

Further Details

Mineral Resource Estimate

The Mineral Resource estimate has been reported in accordance with NI 43 -101 and was

prepared by IMC with an effective date of June 30th, 2023. Table 1 provides the pit-constrained

and underground Beartrack-Arnett Gold Project Mineral Resource estimate, which include s

oxide, transition, and sulphide material.

Table 2 summarizes the Mineral Resource definition parameters used to develop the Mineral

Resource estimate . The Measured and Indicated Mineral Resources were estimated at a gold

price of $1,900 per ounce.

4

Table 1: Beartrack-Arnett Gold Project

Mineral Resources by Material Type and Location

Resource Type Location Resource Category

Mineral Resources

Resource Grade Contained

(kT) (g/T) (koz)

Heap Leach

Mineral Resource

Open Pit

Beartrack

Measured 6,743 1.03 224

Indicated 18,781 0.77 466

Inferred 2,694 0.51 45

Haidee

Measured 5,932 0.48 92

Indicated 10,880 0.51 177

Inferred 3,624 0.55 64

Open Pit Beartrack

& Haidee

Measured 12,675 0.78 316

Indicated 29,661 0.67 643

Measured + Indicated 42,336 0.70 959

Inferred 6,318 0.53 108

Mill

Mineral Resource Open Pit Beartrack

Measured 6,557 1.10 231

Indicated 37,290 1.03 1,233

Inferred 37,666 0.99 1,204

Underground Beartrack Inferred 6,745 4.05 877

Open Pit &

Underground Beartrack

Measured 6,557 1.10 231

Indicated 37,290 1.03 1,233

Measured + Indicated 43,847 1.04 1,464

Inferred 44,411 1.46 2,082

Total

Mineral

Resource

Open Pit &

Underground

Beartrack

& Haidee

Measured 19,232 0.88 547

Indicated 66,951 0.87 1,876

Measured + Indicated 86,184 0.87 2,423

Inferred 50,728 1.34 2,190

Notes:

1) Gold price used for Mineral Resources: $1,900/oz.

2) Gold grades are reported in grams per metric tonne (g/T).

3) Economic cutoff is based on Income Net of Process = $0.01/tonne. Income Net of Process = (Grade x Recovery x ($1,900 - $5)) - (Process

Cost + G&A). Beartrack heap leach process cost and process recovery varies with CN/FA ratio.

4) Beartrack average heap leach gold recovery = 51% of FA, which excludes secondary leach recovery that is included in the PFS recovery

calculations. Beartrack heap leach ore types are: CN/FA > 0.7 = Oxide, 0.2 to 0.7 CN/FA = Transition, CN/FA < 0.2 = Sulphide. Beartrack

base heap leach mining cost and average processing cost including G&A = $2.04/T and $6.88/T, respectively. Beartrack heap leach

throughput = 12,000 T/d. Beartrack approximate FA cutoff grades for heap leach resource = Oxide = 0.15 g/T, Transition = 0.29 g/T,

Sulphide = 0.96 g/T.

5) Haidee heap leach recovery = 86% of FA. Haidee base heap leach open pit mining cost and average processing cost including G&A =

$2.04/T and $6.78/T, respectively. Haidee heap leach throughput = 12,000 T/d. Haidee heap leach resource cutoff grade = 0.17 g/T.

6) Beartrack mill sulphide recovery = 94%. Beartrack base mill open pit mining cost and processing cost including G&A = $2.14/T and

$24.83/T, respectively. Beartrack average mill underground mining cost and processing cost including G&A = $100.00/T and $35.52/T,

respectively. Beartrack mill open pit throughput = 12,000 T/d. Standalone underground throughput = 2,500 T/d. Beartrack open pit mill

sulphide resource cutoff = 0.43 g/T. Beartrack underground mill resource cutoff = 2.37 g/T.

7) Total surface mine material moved: 449,504 kT.

8) Mineral Resources include Mineral Reserves.

9) Numbers may not add exactly due to rounding.

5

Table 2: Beartrack-Arnett Gold Project

Mineral Resource Estimate Definition Parameters

Mineral Resource

Definition Parameters Units

Mill Parameters Heap Leach Parameters

Beartrack

Underground

Beartrack

Open Pit

Beartrack

Open Pit

Haidee

Open Pit

General

Mineral Resource Gold Price $/oz $1,900

Mining / Processing Rate T/d 2,500 12,000 12,000

Average Process Recovery % 94% 51%1 86%

Mining OPEX

Base Mining $/T $100.00 $2.14 $2.04 $2.04

Incremental Bench Mining $/T - - $0.04 $0.02

per bench below listed elevation ft - - 7,075 7,340

Processing OPEX including G&A

Oxide (CN/FA > 0.7) $/T - - $6.62 $6.78

Transition (CN/FA > 0.2 < 0.7) $/T - - $7.31 -

Sulphide (CN/FA < 0.2) $/T $35.52 $24.83 $8.02 -

Incremental Ore Haul $/T - - - $2.19

Other Costs

Refining & Freight $/oz $5.00 $5.00

Open Pit Slope Angles

Tertiary, Dykes, Till, Fill degrees - 38 38

Rapakivi Granite degrees - 45 45

Yellowjacket degrees - 45 45

Economic Cutoff Values

Net of Process Revenue $/T $100.00 $0.01 $0.01 $0.01

Approximate Contained Gold Cutoff Grades

Heap Leach Oxide g/T - - 0.15 0.17

Heap Leach Transition g/T - - 0.29 -

Heap Leach Sulphide g/T - - 0.96 -

Mill Sulphide g/T 2.37 0.43 - -

Note:

1) This value represents the average metallurgical recovery of the Beartrack heap leach Mineral Resource inside the PFS pit;

however, the recoveries used to define the PFS Mineral Resource were calculated on a block-by-block basis using the

following equation: 0.8852 * CN/FA - 0.0612, where CN is the cyanide soluble gold estimate for a given block and FA is the

contained gold estimated for a given block. This value excludes secondary leach recovery, which is included in the KCA PFS

recovery calculations.

Table 3 illustrates the sensitivity of the total Mineral Resource to changes in gold price from

$1,800 per ounce up to $2,000 per ounce.

6

Table 3: Beartrack-Arnett Gold Project

Mineral Resources Sensitivity to Gold Price

Mineral Resource Category

and Gold Price

Resource

Tonnage

(kT)

Contained

Gold Grade

(g/T)

Contained

Gold

(koz)

Mineral Resource Sensitivity at $1,800/oz Gold

Total Measured + Indicated 83,017 0.88 2,360

Total Inferred 44,674 1.39 2,003

Base Case Mineral Resource at $1,900/oz Gold

Total Measured + Indicated 86,184 0.87 2,423

Total Inferred 50,728 1.34 2,190

Mineral Resource Sensitivity at $2,000/oz Gold

Total Measured + Indicated 97,295 0.81 2,525

Total Inferred 63,597 1.19 2,441

Inferred Mineral Resources include 6.7 million tonnes of underground material at 4.0 g/T gold

containing 877,000 ounces of gold. The increase in underground Inferred Mineral R esources

since 2022 is, in part, derived from a more focused approach to mining and the elimination of an

open pit in the Joss Target areas. The pit elimination would reduce the environmental footprint

of the potential mill phase and accelerate the expected permitting and development timelines

for the potential mill production phase to commence.

Underground mining is assumed to utilize an overhand cut and fill approach on a “stand-alone”

basis with a cut -off grade of 2.37 g/T gold. The underground Mineral Resource occurs in both

the South Pit and Joss areas and vertically over an elevation of approximately 580 meters. The

underground Inferred Mineral Resource dips at approximately 80 -90 degrees and ranges in

thickness from about 3 to 25 meters.

Table 4 summarizes the sensitivity of the Beartrack underground Mineral Resource to changes in

cutoff gold grade. All underground scenarios in Table 4 are for Mineral Resources that sit below

mill open pit Mineral Resource.

7

Table 4: Beartrack-Arnett Gold Project

Underground Mineral Resources Sensitivity to Cutoff Gold Grade

Cutoff

Gold Grade

(g/T)

Gold

Price

($/oz)

Inferred Mineral

Resource Tonnage

(kT)

Contained

Gold Grade

(g/T)

Contained

Gold

(koz)

2.00 2,250 12,470 3.22 1,292

2.26 2,000 8,194 3.77 994

2.37 1,900 6,746 4.05 877

2.50 1,800 5,517 4.39 778

2.64 1,700 4,295 4.87 672

2.74 1,640 3,385 5.38 586

Note: A cutoff gold grade of 2.37 g/T defines the Base Case underground mineral resource.

Figure 1 presents an overview of the Beartrack -Arnett Project area and the location of Mineral

Resources on the property.

Figure 1: Beartrack-Arnett Gold Project

Mineral Resource Areas1 and Land Position

Note:

1) See Revival Gold news release dated July 11 th, 2023, for additional details on Mineral Resources and press releases dated

October 2nd, 2017, March 15th, 2022, and September 22nd, 2022, for additional details on drill results depicted here.

8

Mineral Reserve Estimate

The PFS and associated Mineral Reserve estimate was developed based on the open pit heap

leach Measured and Indicated portion of the Beartrack and Haidee Mineral Resource estimates.

The Proven and Probable Mineral Reserves for the Project were estimated a t a gold price of

$1,700 per ounce and are summarized in Table 5.

Table 5: Beartrack-Arnett Gold Project

Mineral Reserve Estimate by Location and Category

Deposit Mineral Reserve Category

Mineral Reserves

Tonnage Gold Grade Contained Gold

(kT) (g/T) (koz)

Beartrack Proven 6,420 1.06 219

Probable 15,600 0.82 413

Proven + Probable 22,020 0.89 632

Haidee Proven 5,933 0.48 92

Probable 8,244 0.51 136

Proven + Probable 14,177 0.51 228

Total Proven 12,353 0.78 311

Total Probable 23,844 0.72 549

Total Proven + Probable 36,197 0.74 859

Notes:

1) Gold price used for Mineral Reserves: $1,700/oz.

2) Gold grades are reported in grams per metric tonne, g/T.

3) Cutoff gold grade is based on Net of Process Revenue = $0.01/tonne.

Net of Process Revenue = (Grade x Recovery x ($1,700 - $5)) - (Process Cost + G&A).

Process cost varies with CN/FA ratio. Process recovery varies by CN/FA ratio.

4) Typical FA gold cutoff grades are: 0.17 g/T oxide, 0.33 g/T transition, 1.07 g/T sulphide.

5) Total open pit material: 124,413 kT.

6) Numbers may not add exactly due to rounding.

Open Pit Heap Leach PFS

The PFS was developed as an initial phase of open pit mining with approximately 36.2 million

tonnes of heap leachable ore from the Beartrack and Haidee deposits at an average rate of

12,000 tonnes/day for a period of 8.1 years . The PFS mine fleet is conventional with loading

accomplished by three 11 m3 front loaders matched to up to thirteen 90-tonne class haul trucks.

Run-of mine ore from the open pits would be processed in a conventional, mobile crushing circuit

to achieve a particle size of 100% passing 38 mm (1.5 inch). Crushed ore w ould be conveyor

stacked onto heap leach pads and leached with a low concentration cyanide solution. The

resulting pregnant leach solution w ould be processed in an existing, refurbished, adsorption -