Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

ROCK.V ·

Eros Announces Results of Preliminary Economic Assessment for the Bell Mountain Gold Project

Economic Studies

NEWS RELEASE

NR: 17-11

October 11, 2017

Eros Announces Results of Preliminary Economic

Assessment for the Bell Mountain Gold Project

Vancouver, BC (October 11, 2017) Eros Resources Corp. (TSX.V: ERC) (“Eros” or the

“Company”) hereby provides the results of a Preliminary Economic Assessment (“ PEA”) on

its 100% owned Bell Mountain gold project (the “Bell Mountain Property” or the “Project”) in

Churchill County, Nevada. The PEA provides a base case assessment of the current st atus

of the Project notwithstanding the Bureau of Land Management ( “BLM”) September 1, 201 6

notice that the US Navy had applied to expand the Fallon Range Training Facility and

withdraw 604,789 acres of public land, an area that includes the entire Bell Mo untain

Property. As a result, the BLM has segregated the proposed expansion area for a two -year

period such that no entry or work can be conducted on existing mining claims therein

(including the Bell Mountain P roperty) while an environmental impact statement (“EIS”)

respecting the expansion proposal is completed by the US Navy. The withdrawal will require

ratification by the US Congress, who are expected to make a final decision following the

completion of the EIS and upon receiv ing a recommendation from the Secretary of the

Interior.

“The PEA was compiled to provide an assessment of the Project as it stands today. The

restriction placed on Eros to explore and advance the Project has prevented us from

attempting to expand and upgrade the resource base and further enhance the potential

economics of the Project. Nonetheless, t he results of the study clearly indicate continued

investment into the Bell Mountain Property is justified,” stated Ron Stewart, President and

CEO of Eros.

PEA Highlights

The base case PEA economics assumed a gold price of $1,300/oz and a silver price of

$17.50/oz. All currencies are stated in US dollars.

• Pre-Tax Net Present Value (“NPV”) @ 5% and Internal Rate of Return (“IRR”) of $17.6

million and 41.4%, respectively with a payback period of ~1.7 years;

• After-Tax Net Present Value @ 5% and IRR of $9.3 million and 24.7%, respectively

with a payback period of ~2.7 years;

• Pre-production capital cost estimated at $18.5 million including a $1.7 million

contingency;

• Life of Mine (“LOM”) production of 60,056 ounces of gold and 408,498 ounces of silver

over a 4.0 year mine-life; and

• LOM cash cost of US$759/oz , net of by -product silver credits and including royalty

payments totalling $2.56 million.

The PEA was prepared by Welsh Hagen Associates (“WHA”) of Reno, Nevada in accordance

with National Instrument 43 -101 Standards of Disclosure for Mineral Projects (“NI 43 -101”).

The study is being summarized into a technical report entitled "NI 43-101 Technical Report on

the Bell Mountain Project Preliminary Economic Assessment, Churchill County, Nevada,

USA" (the “Technical Report”), to be filed on SEDAR in accordance with NI 43-101 within 45

days.

The reader is caut ioned that the PEA is preliminary in nature and includes some inferred

mineral resources that are considered too speculative geologically to have the economic

considerations applied to them that would enable them to be categorized as mineral reserves.

There is no certainty that the PEA will be realized. There is no certainty that the inferred

mineral resources will be converted to the indicated or measured categories, or that the

potential measured or indicated resources would be converted to the proven or probable

mineral reserve categories. Mineral resources that are not mineral reserves do not have

demonstrated economic viability.

The estimates of mineral resources in the PEA and the mineral resource statement may be

materially affected by environmental, permitting, legal, title, taxation, socio -political,

marketing, or other relevant issues. The PEA recommends that the Project be advanced to a

feasibility level for a total estimated cost of $1,787,500 . The scope of work recommended

includes additional exploration and infill drilling, water well maintenance, metallurgical testing,

engineering and environmental studies.

Mineral Resource

The mineral resource estimate was prepared by Zachary J. Black, SME -RM, with Hard Rock

Consulting (“HRC”). The Project is subdivided into four (4) individual areas known as Spurr,

Varga, Sphinx and East Ridge. Each modelled area was divided into three domains: country

rock, stockwork and vein. HRC estimated the mineral resource using an ordinary krige

algorithm. In order to meet the test of ‘reasonable prospects for economic extraction,’ HRC

constructed a Lerchs -Grossmann pit shell based on $ 1,300/oz gold and $ 17.50/oz silver.

Resources were assigned measured, indicated and inferred classifications based on the

confidence of the estimate, domain of the geologic model and proximity to drill holes.

Resource Statement for the Bell Mountain Project, Churchill County, Nevada

Note: Open pit optimization was used to determine potentially mineable tonnage. Measured, Indicated and Inferred mineral

classification was determined according to CIM Standards. Mineral resources, which are not mineral reserves, do not have

demonstrated economic viability. The 2017 Measured, Indicated and Inferred resource is constrained within a $1, 300/oz Au

and $17.50/oz Ag Lerchs-Grossman Pit shell. The base case estimate applies a AuEq cutoff grade of 0.005 oz/t for Varga

and 0.004 oz /t for all other areas based on the estimated operating costs. Metallurgical recoveries used for the cutoff

calculations were 83.7% on gold and 29.6% on silver for Spurr, 68.6% on gold and 12.8% on silver for Varga and 80% on

gold and 10% on silver for Sphinx and East Ridge.

Tons

(x1000) (opt) (oz) (opt) (oz) (opt) (oz)

Measured 362.4 0.024 8,720 0.87 316,121 0.028 10,225

Indicated 494.5 0.019 9,546 0.73 360,301 0.023 11,261

M&I 856.9 0.021 18,266 0.79 676,421 0.025 21,486

Inferred 395.9 0.008 3,131 0.40 158,100 0.010 3,884

Tons

(x1000) (opt) (oz) (opt) (oz) (opt) (oz)

Measured 769.7 0.016 12,316 0.34 258,904 0.017 12,966

Indicated 1,373.3 0.016 21,424 0.31 430,519 0.016 22,505

M&I 2,143.0 0.016 33,740 0.32 689,423 0.017 35,472

Inferred 1,140.7 0.013 14,711 0.31 355,618 0.014 15,604

Tons

(x1000) (opt) (oz) (opt) (oz) (opt) (oz)

Measured 15.5 0.032 496 0.95 14,821 0.034 521

Indicated 13.6 0.017 227 0.51 6,884 0.018 239

M&I 29.1 0.025 723 0.74 21,705 0.026 760

Inferred 254.4 0.019 4,892 0.53 134,915 0.020 5,119

Tons

(x1000) (opt) (oz) (opt) (oz) (opt) (oz)

Measured 0 0.000 - 0.00 - 0.000 -

Indicated 36.1 0.028 1,016 0.85 30,598 0.030 1,067

M&I 36.1 0.028 1,016 0.85 30,598 0.030 1,067

Inferred 268.4 0.023 6,150 0.77 205,928 0.024 6,496

East Ridge at 0.004 AuEq cutoff

Classification

Gold Silver Gold Equivalent

Classification Gold Silver Gold Equivalent

Spurr at 0.004 AuEq cutoff

Classification

Gold Silver Gold Equivalent

Varga at 0.005 AuEq cutoff

Classification

Gold Silver Gold Equivalent

Sphinx at 0.004 AuEq cutoff

Capital Costs

Capital costs were developed based on scaling costs from similar facilities for p roduction

rates and from design assumptions including a contractor operated mining fleet. The

estimated life of mine capital cost for the base case is summarized below.

Estimated Life of Mine Capital Costs

Cost in US$

Mining

Haul Roads

$ 97,380

Process

Mobilization and Site

Preparation

$ 273,708

Earthworks

$ 661,388

Heap Leach Pad

$ 3,912,475

Solution Collection / Distribution

System

$ 191,194

Process Ponds

$ 611,450

Crushing Circuit

$ 3,706,642

Carbon Plant

$ 779,698

Buildings (Shop, warehouse,

lab, offices)

$ 460,000

Concrete

$ 150,000

Miscellaneous Facility Elements

$ 1,110,400

Mine Site Mobile Fleet

$ 1,950,000

Indirect

Engineering, Procurement,

Construction Management

$ 250,000

Owner Costs

$ 2,667,000

Contingency 10% $ 1,682,133

Total $ 18,503,468

Operating and Reclamation Costs

Operating cost assumptions were based on similar scale surface mining operations using

heap leach processing in northern Nevada. Reclamation cost is consistent with the projected

scale of the mining operation. Operating and reclamation cost assumptions per ton of material

processed are summarized as follows:

Estimated Operating and Reclamation Costs

Category US$ per Ton Processed

Mining Cost $ 2.30

Processing Cost $ 4.15

G&A Cost $ 0.80

Reclamation Cost $ 0.25

Total $ 7.50

Processing and Metallurgical Recovery

The deposits of the Bell Mountain Property (Spurr, Varga, Sphinx and East Ridge) generally

are quite amenable to processing by heap leaching. Metallurgical recoveries used were

83.7% on gold and 29.6% on silver for Sp urr, 68.6% on gold and 12.8% on silver for Varga

and 80% on gold and 10% on silver for Sphinx and East Ridge. Additional metallurgical

testing will be required to confirm the leaching characterization of the mineralization and will

provide information for the heap design, project operation plans and insight into leach cycles.

Mine Plan

The PEA assumed a contractor operated, conventional open pit mine, with drill and blast rock

breakage and truck and loader materials handling. The mine production schedule w as based

on an average of 5,000 tons / day delivered to the crusher and then placed on the heap leach

pad as crushed mineralized material.

Mineral resources within the pits volumes were evaluated and scheduled. The average cutoff

grade for the mine life of the conceptual mining project is 0.004 Au opt for the Spurr, Sphinx

and East Ridge deposits, and 0.005 Au opt for the Varga. A detailed conceptual mine

schedule is summarized by year as follows.

Conceptual Mine Schedule

Item Units Year 1 Year 2 Year 3 Year 4 Totals

Total Mineralized Material Tons 000's 1,500.0 1,500.0 1,500.0 406.6 4,906.6

Au Equivalent Grade AuEq opt 0.020 0.017 0.015 0.024 0.018

Contained oz Au Equivalent1 Oz AuEq 000's 29.3 25.6 22.5 9.6 87.0

Waste Rock Tons 000's 966.9 564.1 1,236.7 990.8 3,758.6

Total Mined Tons 000's 2,466.9 2,064.1 2,736.7 1,397.5 8,665.2

1 Gold Equivalent (AuEq) = Au + (Ag/AuEq Factor) where AuEq Factor = (Au Rec/Ag Rec) x ($1,250/oz gold/$15.00/oz silver)

Project Economics

A gold price of $1,300/oz and a silver price of $17.50/oz were chosen for the base case

economic evaluation based roughly on the 3 -year trailing London Gold Fix prices in

combination with the current gold and silver prices at the effective date of the PEA . The

economic evaluation base case is considered realistic and meets the test of reasonable

prospect for eventual economic extraction. The base case economic results for the metal

price assumptions are shown as follows

Cash Flow Summary

Pre-tax After Tax

IRR 41.4% 24.7%

NPV @ 5% Discount Rate (US$m) $17.64 $9.31

Average Annual Cash Flow (US$m) $10.22 $7.87

Average Operating Margin $170.11/oz Au $131.09/oz Au

Payback Period ~1.7 years ~2.7 years

Qualified Persons and NI 43-101 Disclosure

John Welsh, P.E., Douglas Willis (CPG) and Carl Nesbitt (SME -RM) representing Welsh Hagen

Associates, Zachary Black (SME -RM) representing Hard Rock Consulting, LLC, and Walter

Martin (CPG) representing Stantec Consulting Services Inc., the Qualified Persons, as defined

under NI 43 -101, responsible for the preparation of the Technical Report , have reviewed the

contents of this press release for accuracy of the technical and economic information presented.

The Technical Report, with an anticipated effective date of October 9, 2017 will be prepared by

Welsh Hagen Associates, an independent geological consulting firm located in Reno, Nevada,

USA. This report will be available on SEDAR (www.sedar.com) within 45 days.

The technical contents of this news release have also been reviewed and approved by Ronald

Stewart, P.Geo. a Qualified Person as defined by NI 43-101.

About Eros

Eros Resources Corp. is a Canadian public company focused on the exploration and

development of resource projects in North America. Eros has as its prime business objective the

identification, acquisition and exploration of advanced resource projects with a Nor th American

focus. A secondary focus of the Company is to make strategic investments with a global focus

and a diverse commodity base. The Company’s expertise in the resource sector supports the

selection of these strategic investments.

On behalf of the Board of Directors of

Eros Resources Corp.,

Ron Stewart

President & CEO

Cautionary note regarding forward-looking statements

Certain statements made and information contained herein may constitute “forward looking information” and

“forward looking statements” within the meaning of applicable Canadian and United States securities legislation,

including, among other things, t his press release includes references to mineral resources and future potential

forecast economics of extracting those resources . These statements and information are based on facts

currently available to the Company and there is no assurance that actual results will meet management's

expectations. Forward -looking statements and information may be identified by such terms as "antic ipates",

"believes", "targets", "estimates", "plans", "expects", "may", "will", "could" or "would". Forward -looking

statements and information contained herein are based on certain factors and assumptions regarding, among

other things, there is no certainty that any portion of the resources will be confirmed with greater certainty , if

confirmed, there is no certainty that it will be commercially viable to extract any portion of the resource , there is

no certainty th at access to the resour ce area will be re -established, and if access to the resource area is

blocked for an extended period of time, or permanently, there is no certainty that any compensation will be

received by the Company. Forward-looking information involves known and unknow n risks, uncertainties and

other factors that may cause actual results or events to differ materially from those expressed or implied by such

forward-looking information, including the re-establishment of physical access to the property, the availability o f

adequate and secure sources of funding to construct the extraction facilities required to extract the mineral

resources, prevailing commodity prices, the receipt of regulatory approvals, environmental risks and the

performance of personnel. While the Co mpany considers its assumptions to be reasonable as of the date

hereof, forward -looking statements and information are not guarantees of future performance and readers

should not place undue importance on such statements as actual events and results may di ffer materially from

those described herein. The Company does not undertake to update any forward -looking statements or

information except as may be required by applicable securities laws.

Neither TSX Venture Exchange nor the Investment Industry Regulatory Organization of Canada accepts

responsibility for the adequacy or accuracy of this release.