Melior Moves Closer to Full Production - Goondicum Commissioning and Production RAMP-up Update

Mine Development & Operations

NEWS RELEASE

MELIOR MOVES CLOSER TO FULL PRODUCTION -

GOONDICUM COMMISSIONING AND PRODUCTION RAMP-UP UPDATE

Toronto, Ontario, February 14, 2019 – Melior Resources Inc. (TSXV: “MLR”) (“Melior” or the

“Company”) today updated the market about progress at its Goondicum Ilmenite Project.

Commissioning and production ramp-up at Goondicum successfully continues to advance on schedule.

Ilmenite production was 5,238 tonnes in January exceeding our budget forecast. Production of our

secondary product apatite, of 317 tonnes was below forecast. Apatite sales represent around 15% of

forecasted revenue and provides useful margin expansion. Modifications for the apatite circuit are being

implemented and management is confident that apatite production will be brought up to budgeted levels

over the next few months.

Notable to highlight is that initiation of product offtake is on track. The first ilmenite shipment remains

scheduled for Q1 CY2019 and ilmenite haulage to the port from the mine has now commenced.

No Lost Time Incidents were recorded during January and the project has been LTI free since the start

of construction.

Mark McCauley, Melior’s CEO, said, “January saw further welcome progress with production rates of

over 400 tonnes per day of ilmenite which is getting close to levels of our pr ojected steady state of

production. Management remains confident that our clear target for Goondicum to produce 14,000

tonnes of ilmenite and 3,500 tonnes of apatite per month in the second half of CY2019 will be

achieved”.

Project Photos

Photo 1. First load of ilmenite from mine

Photo 2. First load of ilmenite into port storage facility

Photo 3. Aerial shot of processing facility

About Melior

Melior is the owner and operator of the Goondicum ilmenite and apatite mine located in Queensland

Australia. Further details on Melior and the Goondicum mine can be found at

www.meliorresources.com and regulatory filings are available on SEDAR. Melior is incorporated under

the provisions of the Business Corporations Act (British Columbia) and has a registered office in

Vancouver, British Columbia. Melior is classified as a Tier 1 Mining Issuer under the policies of the

TSX Venture Exchange.

The expectations outlined in this press release regarding the Goondicum mine represent the information

contained in the PEA prepared independently by TZ Minerals International Pty Ltd. for the purposes of

National Instrument 43-101 (“NI 43-101”) and relies in part on inferred resources. As a result, the PEA

is subject to increased uncertainty and technical and economic risks of mine failure and there can be no

assurance that the report’s expectations will be achieved.

The PEA is preliminary in nature and includes Inferred Resources that are considered too speculative

geologically to have the economic considerations applied to them that would enable them to be

categorized as Mineral Reserves, and there is no ce rtainty the PEA will be realized. Shareholders are

strongly encouraged to refer to the complete updated Technical Report prepared in accordance with NI

43-101 in respect of the Goondicum mine, which includes the results of the PEA described in this news

release, which has been filed on SEDAR at www.sedar.com under the Company’s profile on August

30, 2018.

Forward Looking Statements Disclaimer

This press release contains forw ard-looking information within the meaning of applicable securities

laws that reflects the current expectations of management of Melior regarding the production ramp up

of the Goondicum mine. The words “may”, “w ould”, “could”, “should”, “will”, “anticipate”,

“believe”, “plan”, “expect”, “int end”, “estimate”, “aim”, “endeav our”, “project”, “continue”,

“predict”, “potential”, or the negative of these term s or other similar expressions have been used to

identify these forward-looking stat ements and include, but are not limited to statements regarding

anticipated production, timing for first ilmenite shipment and haulage and target production rates.

Forward-looking statements are based upon a number of assumptions and are subject to a number of

known and unknown risks and uncertainties, many of which are beyond management’s control, and

that could cause actual results to differ materially fr om those that are disclosed in or implied by such

forward-looking statements. There can be no assurance that forward-looking information will prove to

be accurate, as actual results and future events could differ materially from those expected or estimated

in such statements. Accordingly, readers should not place undue reliance on forward-looking

information. Risks, assumptions and uncertain ties regarding Melior and the forward looking

information herein are described in its publicly available disclosure documents including the Technical

Report, as filed by Melior on SEDAR (www.sedar.com) except as updated herein. This forward-looking

information represents management’s views as of the date of this press release. While subsequent events

and developments may cause such views to change, Melior does not intend to update this forward-

looking information, except as required by applicable securities laws.

For further information please contact:

MELIOR RESOURCES INC.

Mark McCauley

Chief Executive Officer

+61 7 3233 6300

[email protected]

Investor Relations

Andreas Curkovic Proconsul Capital

+1-416-577-9927

Neither the TSX Venture Exchange nor its Regulation Serv ices Provider (as that term is defined in the

policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this

release.