Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

RNCH.V ·

Goondicum Processing Facility Commences Wet Commissioning

Mine Development & Operations Metallurgy & Processing

NEWS RELEASE

GOONDICUM PROCESSING FACILITY COMMENCES WET COMMISSIONING

Toronto, Ontario, October 22, 2018 – Melior Resources Inc. (TSXV: “MLR”) (“Melior” or the “Company”) today updated the market a bout

the progress being made at its Goondicum Ilmenite Project towards the commencement of production.

Progress as at 19th October

The Goondicum construction project remains on budget and on schedule for start of ilmenite and apatite production in November 2018.

This week the construction team was joined on site by the newly assembled operations team as they started to take over control of the processing

facility and commenced wet commissioning. Wet commissioning involve s running water through the plant in order to test all pumps , pipelines

and installed processing equipment for leaks, correct installa tion and any equipment manufacturing defects. Dry commissioning o f the newly

installed ROM drive over hopper facility was also successfully completed this week.

The construction team will begin to be decommissioned from site this coming week and training for the operational team has commenced and will

be an on-going part of the wet commissioning period.

Mark McCauley, Melior CEO, said, “We are now entering a very ex citing phase of the project restart and everything is currently proceeding to

plan. I would like to thank our Construction Manager, Gerry Finch, for the effort he has put in over the last six months and the exceptional job he

and his team have done throughout construction. Gerry and his team have provided a ready to commission plant on time and on bud get with no

lost time safety incidents to date. This sets a very positive scene for the next phase of the operation and I am sure the quality of the work done to

date will be reflected in a smooth commissioning.”

Construction Photos Below

Photo 1 – ROM Drive Over 

Unit and Scrubbers 

Photo 2 ‐ Thickeners and 

Clarified water reticulation  

Photo 3 ‐ Floc and watershed 

reagents unloading, mixing 

and dosing  

Photo 4 ‐ Ilmenite drying 

and storage area  

Photo 5 ‐ Ilmenite drying 

circuit 

Photo 6 ‐ Ilmenite dePhos 

circuit 

About Melior

Melior is the owner and operator of the Goondicum ilmenite and apatite mine strategically located in Queensland Australia. Further details on

Melior and the Goondicum mine can be found at www.meliorresources.com and regulatory filings are available on SEDAR.

Melior is incorporated under the provisions of the Business Corporations Act (British Columbia) and has a registered office in Toronto, Ontario.

Melior is classified as a Tier 1 Mining Issuer under the policies of the TSX-V.

Photo 7 ‐ Wet 

commissioning WCP