Goondicum Processing Facility Commences Wet Commissioning
NEWS RELEASE
GOONDICUM PROCESSING FACILITY COMMENCES WET COMMISSIONING
Toronto, Ontario, October 22, 2018 – Melior Resources Inc. (TSXV: “MLR”) (“Melior” or the “Company”) today updated the market a bout
the progress being made at its Goondicum Ilmenite Project towards the commencement of production.
Progress as at 19th October
The Goondicum construction project remains on budget and on schedule for start of ilmenite and apatite production in November 2018.
This week the construction team was joined on site by the newly assembled operations team as they started to take over control of the processing
facility and commenced wet commissioning. Wet commissioning involve s running water through the plant in order to test all pumps , pipelines
and installed processing equipment for leaks, correct installa tion and any equipment manufacturing defects. Dry commissioning o f the newly
installed ROM drive over hopper facility was also successfully completed this week.
The construction team will begin to be decommissioned from site this coming week and training for the operational team has commenced and will
be an on-going part of the wet commissioning period.
Mark McCauley, Melior CEO, said, “We are now entering a very ex citing phase of the project restart and everything is currently proceeding to
plan. I would like to thank our Construction Manager, Gerry Finch, for the effort he has put in over the last six months and the exceptional job he
and his team have done throughout construction. Gerry and his team have provided a ready to commission plant on time and on bud get with no
lost time safety incidents to date. This sets a very positive scene for the next phase of the operation and I am sure the quality of the work done to
date will be reflected in a smooth commissioning.”
Construction Photos Below
Photo 1 – ROM Drive Over
Unit and Scrubbers
Photo 2 ‐ Thickeners and
Clarified water reticulation
Photo 3 ‐ Floc and watershed
reagents unloading, mixing
and dosing
Photo 4 ‐ Ilmenite drying
and storage area
Photo 5 ‐ Ilmenite drying
circuit
Photo 6 ‐ Ilmenite dePhos
circuit
About Melior
Melior is the owner and operator of the Goondicum ilmenite and apatite mine strategically located in Queensland Australia. Further details on
Melior and the Goondicum mine can be found at www.meliorresources.com and regulatory filings are available on SEDAR.
Melior is incorporated under the provisions of the Business Corporations Act (British Columbia) and has a registered office in Toronto, Ontario.
Melior is classified as a Tier 1 Mining Issuer under the policies of the TSX-V.
Photo 7 ‐ Wet
commissioning WCP