Robust Project Economics for Revel Ridge: After-Tax NPV5.0% of C$454M, 21% IRR and 3.2 Year Payback
PEA Delivers Rokmaster Resources Corp
Robust Project Economics for Revel Ridge:
After-Tax NPV5.0% of C$454M, 21% IRR and
3.2 Year Payback
VANCOUVER, BC
,
Dec. 29, 2023
/CNW/ -
Rokmaster Resources Corp.
(TSXV: RKR) (OTCQB:
RKMSF) (FSE: 1RR1) ("Rokmaster" or the "Company") is pleased to announce positive results from
the Preliminary Economic Assessment ("PEA") completed by Ausenco Engineering Canada ULC
("Ausenco"), supported by Mining Plus Canada Consulting Ltd.("Mining Plus"), Knight Piésold Ltd.
("KP"), P&E Mining Consultants Inc. ("P&E"), and Canenco Consulting Corp.("Canenco"), for the
Revel Ridge polymetallic gold-silver Project ("Revel Ridge" or the "Project") located in the
Revelstoke
area of southeastern
British Columbia
.
The PEA demonstrates the Revel Ridge Project's ability to become a long life and robust
polymetallic gold-silver mine with strong project economics at
US$1,850
/ounce gold, while today's
spot price is over
US$2,000
per ounce. In addition to the PEA, Revel Ridge has upside potential to
expand current Mineral Resources through ongoing exploration diamond drilling, both down dips,
along on-strike and on other occurrences.
A National Instrument ("NI") 43-101 Technical Report summarizing the PEA will be filed on SEDAR+.
Amounts stated are in Q4
2023 Canadian dollars
(C$).
Revel Ridge 2023 PEA Highlights Include:
High-grade underground mine with mineralized material
1
averaging
C$361
/t NSR value (diluted)
comprising Main Zone with 11.43 Mt averaging 3.80 g/t Au, 37.37 g/t Ag, 2.34 % Zn, 1.30 %
Pb (diluted) and Yellowjacket Zone 0.34 Mt averaging 8.61% Zn, 2.66% Pb, 65.0 g/t Ag and
0.07 g/t Au (diluted).
After-tax NPV5.0% of
C$454M
and 21.1% IRR at
US$1,850
/oz Au,
US$23.00
/oz Ag,
US$1.26
/lb Zn, and
US$0.90
/lb Pb.
After-tax payback period of 3.2 years discounted at 5.0%.
Pre-production capital expenditures ("CAPEX") of
C$588M
(
US$436M
2
) including contingency
of
C$84M
(
US$62M
2
).
After-tax NPV
5.0%
: CAPEX Ratio of 0.77:1.
Life of mine ("LOM") average annual payable production of 158 koz AuEq per year (114 koz Au
per year, 940 koz Ag, 32.6 mlbs Zn, 19.6 mlbs Pb) over a production lifespan of 11.4 years.
LOM cash costs
3
of
US$540
/oz payable Au on a by-product basis, LOM all-in sustaining costs
("AISC"
4
) of
US$836
/oz payable Au on a by-product basis.
2,920 tonne per day ("t/d") crush and particle sort-mill-flotation-POX & gold plant producing
gold/silver doré and saleable zinc and lead concentrates.
1. Underground mineralized material contains Measured, Indicated and Inferred Resources.
2. Exchange Rate (C$/US$) of 0.74
3. Cash costs are inclusive of mining costs, processing costs, site G&A, treatment, and refining costs, and transportation costs.
4. AISC includes cash costs plus estimated sustaining capital, royalties, and closure costs and less salvage value.
5. Payable Gold Equivalent (AuEq) calculated by dividing gross sales revenue by $1,850.
PEA Overview
The 2023 Revel Ridge PEA considers an underground mine with on-site treatment of the mined
material by particle sorting followed by conventional milling, and flotation to produce separate lead
and zinc concentrates for sale to third-party smelters, in combination with on-site treatment of
refractory gold concentrates to produce gold-silver doré. The mine will comprise an owner-operated,
ramp developed, long hole stope underground mine.
The processing capacity of 2,920 tonnes per day will result in a production lifespan of 11.4 years.
An additional 18 months of mine ramp access and development, and construction of the process
plant and filtered waste management facility (filtered tailings and filtered residues) is planned prior to
the project becoming fully operational in Year 1. The PEA leverages Revel Ridge's existing
infrastructure, including all-weather access roads, 3 km of underground development, permitted
waste rock storage facility, full camp facility and approximately 15 km from the BC Hydro electrical
system and the
City of Revelstoke
with its skilled labor pool.
The PEA is derived using the Company's NI 43-101 Mineral Resource Estimate (
June 06, 2023
).
The effective date of the PEA is
December 29, 2023
, and a Technical Report will be filed on the
Company's website and SEDAR+ within 45 days of this disclosure.
Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability. The
PEA is preliminary in nature and includes Inferred Mineral Resources that are too speculative to
have economic considerations applied to them that would enable them to be categorized as Mineral
Reserves. There is no certainty that PEA results will be realized.
Economic Analysis
The economic analysis was performed assuming a 5% discount rate. Cash flows have been
discounted to the start of construction, assuming that the project execution decision will be taken,
and major project financing will be carried out at this time.
On a post-tax basis, the NPV discounted at 5% is
C$ 454 M
; the IRR is 21.1%; and payback period
is 3.2 years. A summary of the project economics is shown in Table 1.
General
LOM Total / Avg
Lead Price (US$/lb)
0.90
Zinc Price (US$/lb)
1.26
Gold Price (US$/oz)
1,850
Silver Price (US$/oz)
23.00
Mine Life (Years)
11.4
Total Processed Feed Tonnes (kt)
11,772
Total Waste Tonnes (kt)
4,113
Production
LOM Total / Avg
Head Grade – Pb (%)
1.34
Head Grade – Zn (%)
2.52
Head Grade – Au (g/t)
3.69
Head Grade – Ag (g/t)
38.18
Recovery Rate – Pb (%) to saleable Pb Concentrate
68.4
Recovery Rate – Zn (%) to saleable Zn Concentrate
66.8
Recovery Rate – Au (%) to saleable Pb Concentrate
13.8
Recovery Rate – Ag (%) to saleable Pb Concentrate
36.5
Recovery Rate – Au (%) to saleable Zn Concentrate
0.4
Recovery Rate – Ag (%) to saleable Zn Concentrate
5.8
Recovery Rate – Au (%) to doré
80.4
Recovery Rate – Ag (%) to doré
41.7
Total Metal Payable – Pb (m lbs)
224
Total Metal Payable – Zn (m lbs)
372
Total Metal Payable – Au (koz)
1,300
Total Metal Payable – Ag (koz)
10,716
Average Annual Payable Production – Pb (m lbs)
20
Average Annual Payable Production – Zn (m lbs)
33
Average Annual Payable Production – Au (koz)
114
Average Annual Payable Production – Ag (koz)
940
Operating Costs
LOM Total / Avg
Mining Cost (C$/t Processed)
82.67
Processing Cost (C$/t Processed)
70.76
G&A Cost (C$/t Processed)
3.53
Total Operating Costs (C$/t Processed)
156.97
Table 1: Revel Ridge 2023 PEA Detailed
Parameters and Outputs
Cash Costs (By-Product Basis) (C$/oz Au)*
540.2
AISC (By-Product Basis) ($/oz Au)**
836.1
Capital Costs
LOM Total / Avg
Initial Capital (C$M)
588
Sustaining Capital (C$M)
486
Closure Capital (C$M)
76
Salvage Value (C$M)
42
Financials
Pre-Tax
NPV (5%) (C$M)
751
IRR (%)
29.0
Payback (Years)
2.6
Financials
Post-Tax
NPV (5%) (C$M)
454
IRR (%)
21.1
Payback (Years)
3.2
*Cash Costs includes mining costs, processing costs, site G&A, treatment and refining costs, and transportation costs.
**AISC includes cash costs cash costs plus sustaining capital, royalties, and closure costs and less salvage value.
Sensitivities
NPV
5.0
remains positive for changes of 25% in revenue drivers (commodity prices, grade, and
recovery), capital expenditure or operating costs. After-tax economic sensitivities to commodity
prices are presented in Table 2 illustrating the effects of varying gold price as compared to the
base-case. Additional Project sensitivities will be presented in the Technical Report.
Lower Case
Base Case
Higher Case
Gold Price (US$/oz)
1,700
1,850
2,000
After-Tax NPV (5.0%)
(C$M)
334
454
574
After-Tax NPV (8.0%) (C$M)
218
319
419
After-Tax NPV (10.0%) (C$M)
157
247
336
After-Tax IRR (%)
17.3
21.1
24.7
After-Tax Payback (Years)
3.7
3.2
2.9
Table 2: After-Tax NPV and IRR Sensitivities
to Commodity Prices
Revel Ridge Mineral Resource Estimate
The Company's current Mineral Resource Estimate (MRE; effective date of June 6, 2023)
completed by P&E Mining Consultants Inc. forms the basis for this PEA. The MRE includes drilling
results from the Company's 2020-2022 exploration diamond drill programs.
Classification
Tonnes
(kt)
AuEq
(g/t)
AuEq
(koz)
AgEq
(g/t)
AgEq
(koz)
Au
(g/t)
Ag
(g/t)
Pb
(%)
Zn
(%)
Measured & Indicated
7,156.2
6.63
1,526.0
691.9
159,198.9
4.14
51.2
1.96
4.19
Inferred
7,563.9
6.11
1,486.0
621.7
151,188.8
4.42
48.9
1.48
2.62
Table 3: Mineral Resources Reported at CAD $110/t NSR
Cut-Off (effective date June 6, 2023)
Notes:
1)
Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability. The estimate of Mineral Resources may be materially affected by
environmental, permitting, legal, title, taxation, socio-political, marketing, or other relevant issues
2)
The Inferred Mineral Resource in this estimate has a lower level of confidence than that applied to an Indicated Mineral Resource and must not be converted to a Mineral
Reserve. It is reasonably expected that the majority of the Inferred Mineral Resource could be upgraded to an Indicated Mineral Resource with continued exploration,
however there is no certainty an upgrade to the Inferred Mineral Resource would occur or what proportion would be upgraded to an Indicated Mineral Resource
3)
The Mineral Resources in this estimate were calculated using the Canadian Institute of Mining, Metallurgy and Petroleum ("CIM") Standards on Mineral Resources and
Reserves, Definitions and Guidelines (2014) prepared by the CIM Standing Committee on Reserve Definitions and adopted by CIM Council and CIM Best Practices
Guidelines (2019)
4)
The following parameters were used to derive the NSR block model C$/tonne cut-off values used to define the Mineral Resource:
• March 2023 Consensus Economics long term forecast metal prices of Au US$1,750/oz, Ag US$22/oz,
Pb US$0.95/lb, Zn US$1.26/lb
• Exchange rate of US$0.74 = C$1.00
• Main Zone process recoveries of Au 96%, Ag 85%, Pb 71%, Zn 70%
• Yellowjacket Zone process recoveries of Au 86%, Ag 94%, Pb 88%, Zn 93%
• Main Deformation Zones (MDZ) AuEq = Au g/t + (Ag g/t x 0.010) + (Pb% x 0.265) + (Zn% x 0.314); MDZ AgEq = Ag g/t + (Au g/t x 101.478) + (Pb% x 26.933) + (Zn% x
31.847); Revel Ridge Yellowjacket Zone (RRYZ) AuEq = Au g/t + (Ag g/t x 0.008) + (Pb% x 0.310) + (Zn% x 0.457); RRYZ AgEq = Ag g/t + (Pb% x 40.588) + (Zn% x
59.737)
• Mineral Resources have been reported using a NSR cut-off of C$110/t. The NSR cut-off was derived from $75/t mining, $25/t processing and $10/t G&A
5)
Totals may not sum due to rounding
Table 4: The Mineral Resource Estimates for each of the five mineralized zones at
Revel Ridge
Classification
Cut-off
NSR
(C$/t)
Tonnes
(kt)
Ag
(g/t)
Ag
(koz)
Au
(g/t)
Au
(koz)
Pb
(%)
Zn
(%)
NSR
(C$/t)
AuEq
(g/t)
AuEq
(koz)
AgEq
(g/t)
AgEq
(koz)
Totals for All Mineralized Zones
Measured
110
1,916.5
58.6
3,611.6
5.49
338.5
2.05
4.01
544
7.88
485.6
799.0
49,231.4
Indicated
110
5,239.7
48.5
8,168.8
3.64
613.9
1.93
4.25
409
6.18
1,040.3
652.8
109,967.5
Meas & Ind
110
7,156.2
51.2
11,780.4
4.14
952.4
1.96
4.18
445
6.63
1,526.0
691.9
159,198.9
Inferred
110
7,563.9
46.9
11,414.3
4.42
1,075.1
1.48
2.62
417
6.11
1,486.7
621.7
151,188.8
Totals For Revel Ridge Main Zone
Measured
110
1,550.1
63.6
3,171.4
5.89
293.6
2.25
4.25
585
8.46
421.5
857.4
42,730.1
Indicated
110
2,922.4
49.6
4,662.5
4.97
466.6
2.02
3.60
491
7.13
669.8
722.7
67,902.9
Meas & Ind
110
4,472.6
54.5
7,833.8
5.29
760.3
2.10
3.83
523
7.59
1,091.3
769.4
110,663.0
Inferred
110
5,689.1
49.1
8,975.5
4.94
903.3
1.66
2.93
466
6.79
1,241.6
688.1
125,859.5
Totals For Revel Ridge Footwall Zone
Measured
110
196.1
33.8
212.8
5.08
32.0
0.95
1.78
427
6.23
39.3
631.4
3,980.8
Indicated
110
846.5
28.8
785.0
4.01
109.1
0.74
1.11
328
4.84
131.8
491.0
13,362.9
Meas & Ind
110
1,042.5
29.8
997.9
4.21
141.1
0.78
1.24
347
5.10
171.0
517.4
17,343.7
Inferred
110
704.7
21.5
488.2
3.96
89.7
0.53
1.00
313
4.63
104.9
469.5
10,637.3
Totals For Revel Ridge Yellowjacket Zones
Measured
110
0.5
48.0
0.8
0.11
0
1.89
3.99
122
2.79
0
363.1
5.8
Indicated
110
887.4
62.9
1794.1
0.10
2.9
2.65
9.08
289
5.47
156.2
712.8
20,336.6
Meas & Ind
110
887.9
62.9
1795.0
0.10
2.9
2.65
9.07
289
5.47
156.2
712.6
20,342.4
Inferred
110
132.6
126.3
538.8
0.04
0.2
2.43
4.96
198
4.03
17.2
521.5
2,223.3
Totals For Revel Ridge Hanging Wall Zone
Measured
110
169.7
41.5
226.6
2.35
12.8
1.53
4.37
307
4.55
24.8
460.9
2,514.7
Indicated
110
583.5
49.4
927.1
1.88
35.3
2.09
4.69
296
4.40
82.6
445.9
8,365.1
Meas & Ind
110
753.2
47.6
1,153.7
1.99
48.1
1.96
4.62
299
4.43
107.4
449.3
10,879.8
Inferred
110
575.1
44.8
827.6
1.67
30.9
1.51
3.10
232
3.49
64.6
353.7
6,539.9
Totals For Revel Ridge Main Zone Extension
Inferred
110
462.4
39.3
584.1
3.44
51.1
0.36
0.04
263
3.94
58.5
398.8
5,928.8
1
See notes to Table 3.
Mining Overview
An underground mining scenario is the basis for this PEA. The owner-operated and leased mining
fleet will utilize conventional trackless haulage and long-hole stoping with backfill using cemented
process tailings (paste), cemented rockfill and waste rock.
The mine designs and scheduling were engineered to provide 1,066 kt per year of mineralization to
the 2,920 t/d process plant. A total of 11.77 Mt of diluted mill feed, including Inferred material, and
comprising of Main Zone mineralisation with 11.43 Mt averaging 3.80 g/t Au, 37.37 g/t Ag, 2.34 %
Zn, 1.30 % Pb (diluted) and Yellowjacket Zone mineralisation of 0.34 MT averaging 8.61% Zn,
2.66% Pb, 65.04 g/t Ag and 0.07 g/t Au (diluted) is expected to be processed over the life of mine.
Mill feed will be trucked to the process facility located proximal to the main portal. Waste rock that
cannot be accommodated within the mine as backfill will be stored together with dry-stack tailings or
in a separated facility constructed adjacent to the process plant. Underground mining dilution has
been accounted for in the minimum
2.0 m
width of stope shapes, with an additional allowance for
overbreak. Total dilution in the delivered mill feed is estimated at 35.4% (4.17 Mt).
Metallurgical Optimizations
To support this PEA, metallurgical test work was supervised by Canenco Consulting Corp. and
flowsheet development test work was undertaken at Base Metallurgical Laboratories Ltd. using
samples from the Main Deformation Zone (MDZ). The recent metallurgical programs have focused
on sensor based sorting, optimizing sulphide flotation, impurity depression, assessment of onsite
limestone as a reagent, maximizing pressure oxidation and leaching recovery resulting in a process
flowsheet that has improved overall extraction.
Based on the envisioned circuit and corresponding laboratory test response, the overall process
recoveries based on the samples tested for the Main Zone mineralization were expected to be in the
range of 94-96% Au, 84-85% Ag,
71-73% Pb and 70-74% Zn. The Yellowjacket mineralization is less complex metallurgically than the
Main Zone mineralization and responds to standard sequential flotation. Based on the metallurgical
studies undertaken in 2014, the overall process recoveries for the Yellowjacket zone were expected
to be 86% Au, 94% Ag, 88% Pb, and 93% Zn.
Processing Overview
Run-of-mine ("ROM") material is crushed and screened before particle sorting to remove gangue.
The beneficiated material reports to the milling and flotation circuits where lead and zinc sulphide
concentrates are produced and dewatered for sale while the refractory sulphides are collected and
treated by pressure oxidation ("POX") to facilitate extraction and recovery of gold and silver by
cyanide leach - Merrill Crowe process and refining to doré bars.
Concentrate Marketing Studies
Multiple marketing assessments have been completed to support this PEA which indicate that Revel
Ridge zinc and lead-silver-gold concentrates are saleable.
Capital and Operating Costs
The capital cost estimate conforms to Class 5 guidelines for a PEA-level estimate accuracy set out
by the Association for the Advancement of Cost Engineering International ("AACE") with an
estimated accuracy of +50%/-30%. The operating cost estimates were developed from first
principles and benchmarking and applied to the mine production schedule.
The capital and operating cost estimate was developed in Q4
2023 Canadian dollars
(C$). The
capital cost summary is presented in Table 5 and the operating cost summary is presented in Table
6.
WBS
WBS Description
Initial Capital Cost
(C$M)
Sustaining Capital
Cost (C$M)
Total Cost (C$M)
1000
Mining
89.4
372.1
461.4
2000
Process Plant
280.1
0.0
280.1
3000
Additional Facilities
10.4
66.9
77.3
4000
On-Site Infrastructure
19.5
0.0
19.5
5000
Off-Site Infrastructure
10.0
0.0
10.0
Total Directs
409.5
439.0
848.4
6000
Project Indirects
13.2
2.1
15.3
7000
Project Delivery
61.2
7.3
68.5
8000
Owner's Cost
20.5
0.0
20.5
Total Indirects
94.9
9.5
104.3
9000
Provisions (Contingency)
84.0
37.2
121.1
Closure (Incl. Contingency)
Project Totals
588.3
485.6
1,149.6
Table 6: Project Operating Cost Estimates (C$M) (totals may differ due to rounding):
Cost Area
Average Annual Costs (C$M)
C$/t Processed
Mining
85.4
82.67
Process
73.1
70.76
G&A
3.65
3.53
Total
162.1
156.97
Environmental and Permitting Considerations
Revel Ridge represents an existing exploration site with existing permits for mine discharge and
waste disposal. The site has been maintained in good standing and environmental monitoring has
been ongoing during operations and since the site was last active in 2012. There is a database of
environmental information for the site and region spanning almost 30 years. To accommodate the
mine design contemplated by the PEA, updated baseline data and an environmental assessment and
mine permits will be required. The Company is currently performing an analysis of existing
environmental data to identify additional data needs with the intent of carrying out environmental
baseline studies to advance the environmental assessment and permitting processes.
Conclusion and Recommendations
The 2023 PEA demonstrates that Revel Ridge has the potential to become a commercially robust
project. Additional opportunities and next steps include:
Continued exploration and infill drilling for conversion of Inferred Mineral Resources to the
Measured and Indicated categories.
Mine scheduling investigations allowing for the further optimization of blending scenarios.
Supplementary metallurgical optimizations including deposit-wide variability testing and host rock
limestone quality.
Optimization of the particle sorting process, flotation recovery and concentrate quality as well
as the leach-Merrill Crowe process.
Analyses and environmental baseline studies to support expedited permitting.
Further optimization of waste and water management infrastructure, including surface
geotechnical site investigations, laboratory testing, physical waste characterization, water
balance modelling, and engineering studies.
Qualified Persons
A team of independent Qualified Persons ("QP") (as such term is defined under NI 43-101) at
Ausenco, P&E Mining Consultants Inc., Mining Plus, Canenco and KP have led the PEA and have
reviewed and verified the technical disclosure in this press release, including:
Kevin Murray
, P.Eng., of Ausenco is an independent QP for process and infrastructure capital
and operating cost estimation and project financials.
Scott Weston
, P.Geo., of Ausenco is an independent QP for the environmental and permitting
studies.
Eugene Puritch
, P.Eng., FEC, CET., of P&E Mining Consultants Inc. is an independent QP for
the geology and Mineral Resource Estimate.
Evan Verkade
, P.Eng., of Mining Plus is an independent QP for the mine planning and cost
estimation.
Stacy Freudigmann
, P.Eng., F.Aus.IMM., of Canenco is an independent QP for metallurgical
test work and recovery model.
Wilson Muir
, P.Eng. of Knight Piesold is an independent QP for the tailings and waste rock
management facility.
About the Company and Project
Rokmaster's flagship Revel Ridge Project is host to a high-grade gold and polymetallic orogenic
sulphide deposit which has been the subject of the PEA with an effective date of
December 29,
2023
, and an Updated Mineral Resource Estimate
1
on the Revel Ridge Property with an effective
date of
June 6, 2023
. The 2023 Mineral Resource Estimate remains open in all directions and
occupies approximately 2.0 km of the total 5.7 km strike length of the Main Deformation Zone (MDZ)
as defined by geological mapping, drilling, and geochemistry.
Measured & Indicated (M&I):
1.53 million
gold equivalent ("AuEq") Measured & Indicated (M&I)
ounces contained within 7.16 million tonnes with an average grade of 6.63 g/t AuEq.
Inferred (Inf):
1.49 million
AuEq ounces contained within 7.56 million tonnes at an average
grade of 6.11 g/t AuEq.
Footnote 1. Stone et al. 2023. Technical Report and Updated Mineral Resource Estimate of the Revel Ridge Polymetallic Property. NI 43-101 Technical Report dated July 28, 2023.
Ausenco is a global diversified engineering, environmental, construction and project management
company providing consulting, project delivery and asset management solutions to the resources,
energy, and infrastructure sectors. Ausenco's experience in poly-metallic projects ranges from
conceptual, pre-feasibility and feasibility studies for new project developments to project execution
with EPCM and EPC delivery. Ausenco is currently engaged on a number of global projects with
similar characteristics and opportunities to the Revel Ridge project.
On Behalf of the Board of Directors of
Rokmaster Resources Corp.
John Mirko
President & Chief Executive Officer.
Neither TSX Venture Exchange nor its Regulation Services Provider (as that term in defined in the
policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this
press release.
CAUTIONARY NOTE REGARDING FORWARD LOOKING STATEMENTS: This news release may
contain forward-looking information within the meaning of applicable securities laws ("forward-
looking statements"). Forward-looking statements are statements that are not historical facts and
are generally, but not always, identified by the words "expects," "plans," "anticipates," "believes,"
"intends," "estimates," 'projects," "potential" and similar expressions, or that events or conditions
"will," "would," "may," "could" or "should" occur. These forward-looking statements are subject to a
variety of risks and uncertainties which could cause actual events or results to differ materially from
those reflected in the forward-looking statements, including, without limitation: risks related to
fluctuations in metal prices; uncertainties related to raising sufficient financing to fund the planned
work in a timely manner and on acceptable terms; changes in planned work resulting from weather,
logistical, technical or other factors; the possibility that results of work will not fulfill expectations and
realize the perceived potential of the Company's properties; risk of accidents, equipment
breakdowns and labour disputes or other unanticipated difficulties or interruptions; the possibility of
cost overruns or unanticipated expenses in the work program; the risk of environmental
contamination or damage resulting from Rokmaster's operations and other risks and uncertainties.
Any forward-looking statement speaks only as of the date it is made and, except as may be
required by applicable securities laws, the Company disclaims any intent or obligation to update any
forward-looking statement, whether as a result of new information, future events or results or
otherwise.
SOURCE
Rokmaster Resources Corp.
View original content to download multimedia:
http://www.newswire.ca/en/releases/archive/December2023/29/c9100.html
%SEDAR: 00031923E
For further information:
please contact Mr. John Mirko, CEO of Rokmaster,
[email protected], Ph. 1-604-290-4647 or visit the Company's website at:
www.rokmaster.com; For Shareholder information please contact: Mike Kordysz,
[email protected], Ph. +1 (604) 319-3171
CO: Rokmaster Resources Corp.
CNW 04:00e 29-DEC-23