Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

RK.V ·

Rockhaven Announces Robust PEA with Post-Tax $378M NPV(5%) and 37% IRR for its Klaza Gold-Silver Project, Southern Yukon

Economic Studies

1016 – 510 West Hastings Street

Vancouver, BC V6B 1L8

604-687-2522

[email protected]

www.rockhavenresources.com

*Gold equivalent values for mining purposes assume base case metal prices and recoveries used in the PEA and are calculated using the following

formula: AuEQ=1*Au+Ag/107.82+Pb/4.14+Zn/4.68

Rockhaven Announces Robust PEA with Post-Tax $378M NPV(5%) and 37% IRR

for its Klaza Gold-Silver Project, Southern Yukon

July 13, 2020 - Rockhaven Resources Ltd. (TSX-V:RK) (“Rockhaven”) is pleased to

announce the results of an updated Preliminary Econom ic Assessment (“PEA”) for its

100%-owned and road-accessible Klaza Deposit, located in the Dawson Range Gold Belt

of southern Yukon.

PEA Highlights:

Highlights from the PEA, with a base case gold price of US$1 ,450/oz and an exchange

rate of C$1.00 equa l to US$0.7 2 are as follows (all figures in Canadian Dollars unless

otherwise stated):

 Pre-Tax NPV(5%) of $529 million and an IRR of 45%, and a Post-Tax NPV(5%) of

$378 million and an IRR of 37%;

 Using a +/- 20% sensitivity analysis for gold price, Post-Tax NPV(5%) of $540

million and 49% IRR at US$1,740/oz gold and a Post-Tax NPV(5%) of $211

million and 24% IRR at US$1,160/oz gold;

 12-year mine life producing total payable metals of approximately 750,000

ounces gold and 13.8 million ounces silver;

 Initial capital costs of $ 244 million, which includes $ 32 million in contingency

costs. Life-of-mine (“LOM”) sustaining capital costs total $114 million;

 Average LOM operating cash cost of US$613/oz AuEQ* and total all -in

sustaining cost of US$875/oz AuEQ*;

 Annual payable metal production exceeds 100,000 ounces AuEQ in years three

through seven; and,

 Only the upper portions of three out of eleven known mineralized zones are

included in Mineral Resources evaluated by this PEA, and there is excellent

potential for value enhancement through additional exploration.

“This study demonstrates that Rockhaven’s Klaza Deposit could support a mine with a

long life and robust economics ,” stated Matt Turner, President and CEO of Rockhaven .

“Since the last economic study was completed in 2016, closer spaced drilling has better

defined the upper portions of the deposit, resulting in higher average grades in a superior

resource category. We are very pleased with the results of this PEA and look forward to

continuing to add val ue through additional discoveries whi le advancing the deposit

through Pre-Feasibility. At its current ~C$3 5 million market capitalization, Rockhaven

offers investors one of the most compelling valuations in the sector.”

AMC Mining Consultants (Canada) Lt d. (mineral resource, mining, infrastructure and

financial analysis) was contracted to conduct the PEA in cooperation with Blue Coast

Metallurgy Ltd. (metallurgy and processing), Knight Piesold Ltd (tailings and waste

2

management). The PEA is based on the updated Mineral Resource estimate from the

Klaza Deposit (see Klaza Property Technical Report dated June 5, 2018).

The reader should be cautioned that the PEA is preliminary in nature. It includes Inferred

Mineral Resources that are considered too specul ative geologically to have the economic

considerations applied to them that would enable them to be categorized as Mineral

Reserves. There is no certainty that the results of the PEA will be realized.

Economic Results and Sensitivities

Tables I and II sh ow economic results with varying metal prices and assumptions, and

summarize projected production.

Table I: Klaza Combined Open Pit and Underground Mining – Key Economic

Assumptions and Results

Klaza Unit Value

Total Mineralized Rock Mined kt 7,464

Gold Grade1 g/t 3.4

Silver Grade1 g/t 79

Lead Grade1 % 0.6%

Zinc Grade1 % 0.7%

AuEQ Grade2 g/t 4.43

Gold Recovery1 % 95%

Silver Recovery1 % 90%

Lead Recovery1 % 80%

Zinc Recovery1 % 80%

Gold Price US$/oz 1,450

Silver Price US$/oz 17.00

Lead Price US$/lb 0.95

Zinc Price US$/lb 1.00

Payable Gold Metal3 oz 751,472

Payable Silver Metal3 Moz 13.8

Payable Lead Metal3 Mlbs 50.0

Payable Zinc Metal3 Mlbs 50.1

Payable Gold Equivalent Oz 980,561

Total Net Revenue $M 1,975

Initial Capital Costs $M 244

Sustaining Capital Costs $M 114

Operating Costs (Total)4 $/t 111.8

Operating Cash Cost (AuEQ2) US$/oz AuEQ 612.6

Total All In Sustaining Cost (AuEQ2) US$/oz AuEQ 875.3

3

Mine Life Yrs 12

Payback Period (Pre-tax) Yrs 3.9

Payback Period (Post-tax) Yrs 4.2

Cumulative Net Cash Flow (pre-tax) $M 783

Pre-tax NPV(5%) $M 529

Pre-tax IRR % 45

Post-tax NPV(5%) $M 378

Post-tax IRR % 37

1. LOM average

2. Gold equivalent values for mining purposes assume base case metal prices and recoveries used in the PEA a nd are calculated

using the following formula: AuEQ=1*Au+Ag/107.82+Pb/4.14+Zn/4.68

3. Overall payable % includes treatment, transport, refining costs and selling costs

4. Includes mine operating costs, milling, and mine G&A

Table II: Klaza Economic Sensitivity Analysis (Post-tax)

-20% BASE CASE +20%

Variable Unit Value NPV IRR Value NPV IRR Value NPV IRR

Gold US$/oz $1,160 $211 24% $1,450

$378 37%

$1,740 $540 49%

Silver US$/oz $13.60 $343 35% $17.00 $20.40 $407 39%

Mining Cost $/t $44.1 $417 39% $55.14 $66.2 $334 34%

Processing Cost $/t $33.3 $406 39% $41.30 $50.0 $344 35%

LOM Capital $M $286 $456 60% $380 $429 $280 23%

Capital and Operating Costs

The Klaza project has been envisioned as a combined open-pit and underground mining

operation. Open-pit mining is anticipated to be completed by a contract mining company

while the underground operation will be owner -operator with the equipment owned and

personnel employed by Rockhaven.

Grid electrical power will provide the majority of the e lectrical power to the project over

the life of the mine. An on-site camp is envisioned to house mine and mill personnel.

Table III: Total Capital Cost Estimate

Description Cost ($M)

Underground development 115

Flotation tailings storage & residue tailings storage 17

Underground mine infrastructure 21

Mobile equipment 32

Processing plant 103

Surface infrastructure 16

Capital indirects 10

Contingency 32

Additional 5% sustaining for equipment rebuilds 12

Total capital cost 358

4

Initial capital 244

Sustaining capital 114

Table IV: Total Operating Cost Estimate

Description Cost ($/t)

Mining cost 55.14

Processing cost 41.64

General and Administration cost 15.00

Total operating cost 111.78

Mining

Open-pit mining is anticipated to commence in Year 1 and produce a total of 1,181 kt of

mineralized rock over three years. Peak open-pit production will be 598 kt in Year 2. A

total of 6,283 kt of mineralized rock is anticipated to be produced from underground

operations over the 12-year mine life, beginning in Year 1. Peak underground production

will be 688 kt in Years 5 through 7.

Underground mining will be accomplished using mechanized longhole open stoping on

25 m sub-levels. A minimum stope width of 3.0 m was used in this study with dilution of

0.25 m in the hanging wall and 0.1 m in the footwall. Underground access will be

achieved via four separate declines for the each of the four main zones. The Central

Klaza decline will start from the base of the open-pit.

Waste rock will be used to backfill underground stopes as they are mined and to construct

the tailings dams. The remainder will be disposed of in waste dumps on surface.

Processing & Metallurgy

The Klaza process consists of comminution by crushing followed by semi -autogenous

grinding and ball milling, with the ground product feeding a conventional sequential

flotation circuit producing lead, zinc and arsenopyrite concentrates. The arsenopyrite

concentrate is treated by pressure oxidation (POX), followed by cyanide leaching of the

POX residue to recover the gold. Precious metals are also leached from the lead

concentrate to increase the overall gold recovery to doré and enhance saleability of the

concentrate. Final products from this process are precious -metal-rich lead and zin c

concentrates as well as gold and silver as doré.

The processing plant will operate year -round at a rate of approximately 1, 900 tonnes per

calendar day, and will achieve full throughput by Year 2. The average LOM feed grade is

projected to be 3.40 g/t Au, 79 g/t Ag, 0.6% lead and 0.7% zinc.

Base metal c oncentrates will be dewatered and containerized for shipment to smelters.

Flotation tailings will be thickened and sent to a conventional tailings impoundment, and

5

the leached pressure oxidation residue wi ll flow through cyanide destruction and be sent

to a double-lined hydromet residue storage facility.

Although this study assumes a relatively small 250 tpd onsite POX circuit would be used,

an arsenopyrite concentrate could be produced for shipment to a smelter in Nevada or

China. This was not considered in this study at this time but will be investigated as the

project advances.

Process water will primarily be sourced from underground dewatering and surface run -

off, with make-up from the nearby Klaza River as necessary.

Metallurgical testwork to support the PEA has been conducted on several composites

from the Western Klaza, Central Klaza and Western BRX zones, as well as a Project -

Wide Composite comprising a blend of material from these zones. Testwor k included

grinding, flotation and pressure oxidation work.

Opportunities to Enhance Value

This updated PEA reaffirms Rockhaven’s commitment to enhancing value at the Klaza

project through engineering studies and resource expansion and definition . It h as

highlighted several key areas that can provide significant opportunities to further enhance

the value of the Klaza project. These opportunities include:

 Infill drilling to better define areas of high-grade mineralization within the current

inferred resource area;

 Additional drilling to better define and expand the Central BRX Zone which has

seen limited work to date relative to the other zones;

 Additional drilling of potential near surface bulk tonnage target s within the

Eastern BRX Zone, which has yielded high gold recoveries through cyanidation;

 Additional drilling beneath current Mineral Resources, where the deposit remains

open at depth;

 Detailed drilling of other known mineralized structures in order to model and

include these into future mineral resource estimations; and,

 Further metallurgical studies and investigation of potential smelter contracts for

an arsenopyrite concentrate as an alternative to the on-site POX circuit that is

currently envisioned.

Mineral Resources

The basis for the PEA is the Mineral Resource estimate completed by AMC Mining

Consultants (Canada) Ltd. in the NI 43 -101 report with an effective date of June 5, 2018

entitled "Technical Report Describing Updated Diamond Drilling , Metallurgical Testing

and Mineral Resources on th e Klaza Property, Yukon, Canada” which is filed on

SEDAR.

A summary of this resource estimate is shown in Table V:

Table V: Mineral Resource Estimate Summary, June 5, 20181,5

6

Tonnes

Grade Contained Metal

Au Ag Pb Zn AuEQ4 Au Ag Pb Zn AuEQ4

(kt) (g/t) (g/t) (%) (%) (g/t) (koz) (koz) (klb) (klb) (koz)

Indicated3 4,457 4.8 98 0.7 0.9 6.3 686 14,071 73,268 92,107 907

Inferred3 5,714 2.8 76 0.6 0.7 3.9 507 13,901 77,544 89,176 725

1 CIM Definition Standards (2014) were used for reporting the Mineral Resources. Using drilling results to December 31, 2017. The

Qualified Persons are Adrienne Ross, P.Geo. of AMC Mining Consultants (Canada) Ltd, and Nicholas Ingvar Kirchner, FAusIMM,

MAIG. of AMC Mining Consultants Pty Ltd.

2 Near surface Mineral Resources are constrained by an optimized pit shell at a metal prices of US$1,400/oz Au, US$19/oz Ag,

US$1.10/lb Pb, and US$1.25/lb Zn at an exchange rate of $0.80 US to $1.00 Canadian.

3

Cut-off grades applied to the pit-constrained and underground resource are 1.0 g/t and 2.3 g/t AuEQ respectively.

4 Gold equivalent values for the Mineral Resources assume US$1,400/oz Au, US$19/oz Ag, US$1.10/lb Pb, and US$1.25/lb Zn, and

variable recoveries for the different metals.

5 Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

The Klaza Gold-Silver-Lead-Zinc Project

The Klaza property is 100% owned by Rockhaven Resources Ltd . and covers an area of

287 km 2. It is favourably located within the southern part of Yukon’s Dawson Range

Gold Belt, in an area that hosts a n historical gold mine, rich placer gold deposits and key

infrastructure such as road access.

The Klaza property is located 50 km west of the village of Carmacks and is road

accessible by a two -wheel drive road from the K londike Highway. Rockhaven’s

exploration since it acquired the project in late 2009 has included over 100,000 m of

diamond drilling and 24,000 m excavator trenching.

Drilling at the Klaza property has identified eleven main mineralized zones and numerous

subsidiary structures which have a cumulativ e mineralized strike length greater than 10

km. The zones are hosted within a 1.8 km -wide structural corridor consisting of Mid -

Cretaceous granitic country rocks. Low to intermediate sulphidation veins host go ld,

silver, lead and zinc mineralization.

Qualified Persons

A Technical Report supporting the PEA in accordance with National Instrument 43 -101

will be filed on SEDAR (www.sedar.com) within 45 days.

The PEA was prepared under the direction of AMC Mining Consultants (Canada) Ltd. by

independent industry consultants, all of whom are Qualified Persons (QP) under terms of

NI 43-101 and have reviewed the technical content of this press release and approved its

dissemination. QPs contributing to the PEA are listed in the following table.

Qualified Person Position Company Sections of Report

7

Dr A Ross, P.Geo.(BC),

P.Geol.(AB) Principal Geologist AMC Mining Consultants

(Canada) Ltd.

1 (part), 11 ,12, 14 (part) 25

(part), 26 (part), 27 (part)

Mr I Kirchner, FAusIMM,

MAIG Principal Geologist AMC Mining Consultants

Pty Ltd. 1 (part) and 14 (part)

Mr C Martin, C.Eng. Principal Metallurgist Blue Coast Metallurgy Ltd. 1 (part), 13, 17 (part), 19, 25

(part), 26 (part), 27 (part)

Mr M Dumala, P.Eng. (BC) Senior Engineer and

Partner

Archer, Cathro & Associates

(1981) Limited.

1 (part), 3 (part), 4-10, 23, 24,

25 (part), 26 (part), 27 (part)

Mr G Methven, P.Eng. (BC) Principal Mining

Engineer

AMC Mining Consultants

(Canada) Ltd.

1 (part), 2, 3 (part), 15, 16

(part), 20, 21 (part), 22, 25

(part), 26 (part), 27 (part)

Mr M Molavi, P.Eng. (BC) Principal Mining

Engineer

AMC Mining Consultants

(Canada) Ltd.

1 (part), 18, 25 (part), 26

(part)

Mr D Warren, P.Eng. (BC) Principal Mining

Engineer

AMC Mining Consultants

(Canada) Ltd.

1 (part), 16 (part), 21 (part),

25 (part) 26 (part), 27 (part)

Mr B Borntraeger, P.Eng.

(BC)

Specialist

Geotechnical Engineer

/ Associate

Knight Piésold Ltd. 1 (part), 17 (part), 26 (part)

All other technical information, not pertaining to the PEA, in t his news release has been

reviewed and approved by Matthew R. Dumala , P.Eng., of Archer, Cathro & Associates

(1981) Limited and Rockhaven’s designated QP.

The Qualified Persons under the terms of N ational Instrument 43-101 have reviewed the

technical content of this press release for the Klaza property and h ave approved its

dissemination.

About Rockhaven

Rockhaven Resources Ltd. is a mineral exploration company focused on growth through the

advancement of its K laza project. For additional information concerning Rockhaven or its

Klaza project please visit Rockhaven’s website at www.rockhavenresources.com.

Matthew Turner

President, CEO and Director

Rockhaven Resources Ltd.

T:604-687-2522

[email protected]

NEITHER THE TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER (AS

THAT TERM IS DEFINED IN THE POLICIES OF THE TSX VENTURE EXCHANGE) ACCEPTS

RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THIS RELEASE.