RIO2 Provides Eia Plan Update

Permits & Approvals

RIO2 PROVIDES EIA PLAN UPDATE

For Immediate Release July 11, 2022

Vancouver, BC - Rio2 Limited (“Rio2” or “the Company”) (TSXV: RIO; OTCQX: RIOFF; BVL: RIO) is

providing an update of its activities following the announcement made on July 5, 2022 in respect to

the Atacama Regional Evaluation Commission ’s (“the Commission”) decision to not approve the

Environmental Impact Assessment (“EIA”) for its Fenix Gold Project (“the Project”) in Chile.

The Company , along with its Chilean environmental and legal advisors, are currently evaluating

options to continue to advance the P roject. A key document the Company is waiting for is the

Environmental Qualification Resolution (“RCA”) which is the administrative document with which the

Environmental Assessment Service (“SEA”) , outlines th e rationale for their decision. Th e RCA is

expected within the next three weeks and the Company is finalizing its action plan thereafter.

Once the EIA action plan is completed, the Company anticipates announcing a revised timeline of its

proposed activities and how it intends to execute and finance the plan forward.

Key considerations for developing a plan forward is to use all the well-established options within the

permitting process and working with all relevant government authorities to ensure we secure a

successful path forward for the development of the Fenix Gold project.

The Company is thankful for the support it has received following the EIA decision from various

government authorities and community organizations that participated in the Participación Ciudadana

(Citizen Participation) and Consulta Indígena (Indigenous Consultation) as part of the EIA process. The

Company is also encouraged that the SEA decision states that the EIA fulfills all the applicable

regulations and meets the environmental requirements for the granting of applicable sectorial

permits.

The Fenix Gold project is one of the largest undeveloped gold oxide, heap leach project s in the

Americas, hosting a Measured and Indicated mineral resource (as such term is defined in National

Instrument 43-101 -Standards of Disclosure for Mineral Projects, “ NI 43-101”) of 5 Million ounces of

gold which the Company believes will make a positive contribution to the Atacama Region and Chile.

The Project is an example of modern gold mining where a full complement of technical,

environmental, and social considerations have been consulted on and designed in from the outset.

The Project represents a significant investment in the gold mining business in Chile by a junior mining

company of approximately US$210M of initial and sustaining capital and will generate employment

for at least 1,200 people during the construction phase and 550 people during the 17 years operations

phase. The mine being contemplated at the Project will be a run -of-mine heap leach operation, no

crushing or tailings storage facilities are required thereby minimizing the overall impact and footprint

of the Project.

As at March 31, 2022, the Company had cash of approximately US$ 33M and working capital of

approximately US$25M which had been allocated to pre -development activities for the Project. A

significant amount of money has been invested so far in the pre-development of the Project including

the construction of the camp facilities at its infrastructure subsidiary, Lince S.A. , pre-fabrication of

elements of the processing plant and water loading facilities in Copiapo.

TECHNICAL INFORMATION

The scientific and technical content of this news release has been reviewed, approved and verified by

Enrique Garay, MSc. P. Geo (AIG Member), Senior Vice President Geology of Rio2 Limited, who is a QP

under NI 43-101 has also reviewed, approved and verified the scientific and technical content of this

news release. For additional information regarding the Project, including ke y parameters,

assumptions and risks associated with its development, see the independent technical report entitled

“Updated Pre-Feasibility Study for the Fenix Gold Project, Atacama, III Region, Chile” dated August 3,

2021, with an effective date of August 15, 2019, a copy of which document is available under Rio2’s

SEDAR profile at www.sedar.com

ABOUT RIO2 LIMITED

Rio2 is a mining company with a focus on development and mining operations with a team that has

proven technical skills as well as a successful capital markets track record. Rio2 is focused on taking its

Fenix Gold Project in Chile to production in the sho rtest possible timeframe based on a staged

development strategy. In addition to the Fenix Gold Project in development in Chile, Rio2 Limited

continues to pursue additional strategic acquisitions where it can deploy its operational excellence

and responsible mining practices to build a multi-asset, multi-jurisdiction, precious metals company.

Forward-Looking Statements

This news release contains forward-looking statements and forward-looking information (collectively

“forward-looking information”) within the meaning of applicable securities laws relating to Rio2’s

planned development of its Project and other aspects of Rio2’s anticipated future operations and plans.

In addition, without limiting the generality of the foregoing, this news release contains forward-looking

information pertaining to the following: Rio2’s intentions to prepare and undertake an action plan to

address the concerns raised in the RCA, anticipated timing for an announcement on revised timeline

and financial plan; the potential development of a mine at the Project; the impact of the Project for

Chile; development and operating plans; and other matters ancillary or incidental to the foregoing.

All statements included herein, other than statements of historical fact, may be forward -looking

information and such information involves various risks and uncertainties. Forward- looking

information is often, but not always, identified by the use of words such as “seek”, “anticipate”, “plan”,

“continue”, “estimate”, “expect”, “may”, “will”, “project”, “predict”, “potential”, “targeting”, “intend”,

“could”, “might”, “should”, “believe”, and similar expressions. The forward- looking information is

based on certain key expectations and assumptions made by Rio2’s management which may prove to

be incorrect, including but not limited to: expectations concerning the ongoing environmental impact

assessment process with the SEA; expectations relating to timing of receipt of the RCA; expectations

concerning prevailing commodity prices, exchange rates, interest rates, applicable royalty rates and

tax laws; capital efficiencies; legislative and regulatory environment of Chile; future production rates

and estimates of capital and operating costs; estimates of reserves and resources; anticipated timing

and results of capital expenditures; the sufficiency of capital expenditures in carrying out planned

activities; performance; the availability and cost of financing, labor and services; and Rio2’s ability to

access capital on satisfactory terms.

Rio2 believes the expectations reflected in these forward- looking statements are reasonable, but no

assurance can be given that these expectations will prove to be correct and such forward- looking

statements in this news release should not be unduly relied upon. A description of assumptions used

to develop such forward- looking information and a description of risk factors that may cause actual

results to differ materially from forward -looking information can be found in Rio2's disclosure

documents on the SEDAR websi te at www.sedar.com. These risks and uncertainties include, but are

not limited to: risks and uncertainties relating to the completion of the financings as described herein,

and management’s ability to anticipate and manage the factors and risks referred to herein. Forward-

looking statements included in this news release are made as of the date of this news release and such

information should not be relied upon as representing its views as of any date after the date of this

news release. Rio2 has attempted to identify important factors that could cause actual results,

performance or achievements to vary from those current expectations or estimates expressed or

implied by the forward-looking information. However, there may be other factors that cause results,

performance or achievements not to be as expected or estimated and that could cause actual results,

performance or achievements to differ materially from current expectations. Rio2 disclaims any

intention or obligation to update or revise any forward-looking statements, whether as a result of new

information, future events or otherwise, except as expressly required by applicable securities

legislation.

To learn more about Rio2 Limited, please visit: www.rio2.com or Rio2's SEDAR profile at

www.sedar.com.

ON BEHALF OF THE BOARD OF RIO2 LIMITED

Alex Black

President, CEO & Director

Email: [email protected]

Tel: 604 260-2696

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the

policies of the TSX Venture Exchange) accepts the responsibility for the adequacy or accuracy of this

release.