RIO2 Announces GOLD Pour at Fenix GOLD MINE

Production Results Mine Development & Operations

RIO2 ANNOUNCES GOLD POUR AT FENIX GOLD MINE

For Immediate Release January 26, 2026

VANCOUVER, BC - Rio2 Limited (“Rio2” or “the Company”) (TSX: RIO; OTCQX: RIOFF; BVL: RIO)

announces that the first official gold pour at Rio2’s 100% owned Fenix Gold Mine (“Fenix Gold”) in

Chile occurred on Friday, January 23, 2026.

Construction of critical path items at Fenix Gold has been completed on time and on budget, as

previously guided. This gold pour yielded approximately 897 ounces of gold which are in addition to

approximately 358 ounces of gold that were produced in December as part of the plant commissioning

process. As well, the two pours combined produced approximately 131 ounces of silver. With this

significant milestone, the Fenix Gold Mine has become the newest gold mine in Chile.

Rio2 is now focused on ramping up operations at Fenix Gold to 20,000 tonnes per day of ore to pad

over the remainder of the year. Based on the current ramp-up plan, Rio2 is targeting gold production

of 60,000 to 70,000 ounces for 2026.

L to R: João Canêdo, Operations Manager - Fenix Gold; Alex Black, Executive Chairman - Rio2; Andrew Cox,

President & CEO - Rio2

Gold pour at the Fenix Gold Project

The Rio2 and Fenix Gold team celebrating the first official gold pour

Alex Black, Executive Chairman of Rio2, commented: “This milestone moment is the culmination of a

long and somewhat challenging eight-year journey since our 2018 merger with Atacama Pacific Gold

Corporation. It speaks to the discipline, execution capability and determination of our team. On behalf

of the board of directors of Rio2, I want to congratulate Andrew Cox and the combined Rio2 and Fenix

Gold team for delivering the Fenix Gold Mine on budget, in record time. Despite all that we have dealt

with, the team has always maintained its “never give up” attitude to get the job done. Fenix Gold is

the cornerstone asset for creating value for all our stakeholders and I look forward to what the future

holds as we expand the mine and bed -down the Condestable Copper Mine acquisition that we

announced in December.”

Andrew Cox, President and Chief Executive Officer of Rio2, commented: “I am very proud that our

team at Fenix Gold has been able to achieve this exceptional accomplishment, after a short 14-month

construction period. I would like to offer my sincere thanks to all our employees and contractors in

achieving this result with a strong safety record. We are now fully focused on the safe and efficient

ramp-up of operations over the remainder of the year and achieving our 2026 production targets.”

A brief video of Fenix Gold gold pour is available at the following link:

https://youtu.be/UyYpHw62ivU

Rio2 intends to provide further project updates and guidance as mining and gold production

progresses in 2026. The Company also intends to provide updates related to the Phase 2 expansion of

Fenix Gold, which will drive the next significant leg of growth for Rio2.

The scientific and technical content of this news release has been reviewed, approved and verified by

Enrique Garay, MSc P.Geo/FAIG, who is a QP under NI 43-101. For additional information regarding the

Project, including key parameters, assumptions and risks associated with its development, see the

independent technical report entitled “NI 43-101 Technical Report on the Feasibility Study for the Fenix

Gold Project” (the “Feasibility Study”) pursuant to National Instrument 43-101 Standards of Disclosure

for Mineral Projects (“NI 43-101”). The Feasibility Study is dated October 16, 2023, with an effective

date of October 16, 2023, a copy of which document is available under Rio2’s SEDAR+ profile at

www.sedarplus.ca.

ABOUT RIO2 LIMITED

Rio2 is a mining company with a focus on development and mining operations with a team that has

proven technical skills as well as successful capital markets track record. Rio2 is focused on ramping

up its Fenix Gold Mine in Chile to 20,000 tonnes per day of ore to pad by the end of 2026. Rio2 and its

wholly owned subsidiary, Fenix Gold Limitada, are companies with the highest environmental

standards and responsibility with the firm conviction that it is possible to develop mining projects that

respect the three pillars (Social, Environment, Economics) of responsible development. As related

companies, we reaffirm our commitment to apply environmental standards beyond those that are

mandated by regulators, seeking to protect and preserve the environment of the territories that we

operate in.

Forward-Looking Statements

This news release contains forward-looking statements and forward-looking information (collectively

“forward-looking information”) within the meaning of applicable securities laws relating to Rio2’s

development of the Fenix Gold Mine and other aspects of Rio2’s future operations and plans. In

addition, without limiting the generality of the foregoing, this news release contains forward-looking

information pertaining to the following: the anticipated mining rate for the remainder of 2026, the

anticipated gold production for 2026, and other matters ancillary or incidental to the foregoing.

All statements included herein, other than statements of historical fact, may be forward -looking

information and such information involves various risks and uncertainties. Forward -looking

information is often, but not always, identified by the use of words such as “seek”, “anticipate”, “plan”,

“continue”, “estimate”, “expect”, “may”, “will”, “project”, “predict”, “potential”, “targeting”, “intend”,

“could”, “might”, “should”, “believe” and similar expressions. The forward -looking information is

based on certain key expectations and assumptions made by Rio2’s management, including but not

limited to: expectations concerning prevailing commodity prices , exchange rates, interest rates,

applicable royalty rates and tax laws; capital efficiencies; legislative and regulatory environment of

Chile; future mining and production rates and estimates of capital and operating costs; expectations

regarding the availability of debt financing; estimates of reserves and resources; anticipated timing

and results of capital expenditures; the sufficiency of capital expenditures in carrying out planned

activities; results of operations; performance; the anticipated timing and results of expansion studies

and related approvals; the availability and cost of financing, labor and services; and Rio2’s ability to

access capital on satisfactory terms.

Rio2 believes the expectations reflected in these forward-looking statements are reasonable, but no

assurance can be given that these expectations will prove to be correct and such forward -looking

statements in this news release should not be unduly relied upon. A description of assumptions used

to develop such forward-looking information and a description of risk factors that may cause actual

results to differ materially from forward -looking information can be found in Rio2's disclosure

documents on the SEDAR+ website at www.sedarplus.ca. These risks and uncertainties include, but are

not limited to: risks and uncertainties relating to the completion of debt and equity financing for the

construction phase of the mine, market conditions and management’s abil ity to anticipate and

manage the factors and risks referred to herein.

Forward-looking statements included in this news release are made as of the date of this news release

and such information should not be relied upon as representing its views as of any date subsequent to

the date of this news release. Rio2 has attempted to identify important factors that could cause actual

results, performance or achievements to vary from those current expectations or estimates expressed

or implied by the forward-looking information. However, there may be other factors that cause results,

performance or achievements not to be as expected or estimated and that could cause actual results,

performance or achievements to differ materially from current expectations. Rio2 disclaims any

intention or obligation to update or revise any forward-looking statements, whether as a result of new

information, future events or otherwise, except as expressly required by applicable securities

legislation.

To learn more about Rio2 Limited, please visit: www.rio2.com or Rio2's SEDAR+ profile at

www.sedarplus.ca.

ON BEHALF OF THE BOARD OF RIO2 LIMITED

Alex Black

Executive Chairman of the Board

Email: [email protected]

Tel: +51 99279 4655

Kathryn Johnson

Executive Vice President, CFO & Corporate Secretary

Email: [email protected]

Tel: +1 604 762 4720