Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

RDS.V ·

Radisson Announces Positive Preliminary Economic Assessment for O'Brien Gold Project C$532M After-Tax NPV5%, C$175M Initial Capital, Adjacent to Multiple Mills, Still Growing

Economic Studies

Radisson Announces Positive Preliminary

Economic Assessment for O'Brien Gold

Project

C$532M After-Tax NPV5%, C$175M Initial Capital, Adjacent to

Multiple Mills, Still Growing

Rouyn-Noranda, Quebec--(Newsfile Corp. - July 9, 2025) -

Radisson Mining Resources Inc. (TSXV:

RDS) (OTCQB: RMRDF)

("

Radisson

" or the "

Company

") is pleased to announce a positive

Preliminary Economic Assessment (the "

PEA

") for the O'Brien Gold Project ("

O'Brien

" or the "

Project

")

located in the Abitibi region of Québec. Highlights are as follows (all figures are in Canadian dollars and

troy ounces unless noted):

Basis of Study:

Assumes off-site toll milling based on the results of a recent milling assessment and metallurgical

study that demonstrated the potential compatibility of the nearby Doyon gold mill, part of IAMGOLD

Corporation's ("

IAMGOLD

") Westwood Mine Complex

1

. Off-site milling reduces capital costs,

development risk, and project footprint.

Utilizes existing Mineral Resource Estimate ("

MRE

"), re-blocked with an updated cut-off yielding

more ounces in more tonnes with good continuity at a lower average grade.

Presents a base case "snap-shot" study that excludes recent drilling successes outside the

existing MRE and below historic mine workings, with a 50-60,000 metre (m) fully funded drill

program ongoing.

Value:

After-tax Net Present Value at a 5% discount rate ("NPV

5%

") of

$532 million ("M")

, Internal Rate

of Return ("IRR") of

48%

, and payback of

2.0 years

at US$2,550/oz gold ("Au").

After-tax NPV

5%

of

$871M

, IRR of

74%

, and payback of

1.1 years

at US$3,300/oz Au.

Cost:

Initial Capital Cost ("Capex") of

$175M

and Life-of-Mine Sustaining Capital of

$173M

Cash Cost

2

of

US$861/oz

and All-In Sustaining Cost

1

("AISC") of

US$1,059/oz

including

conceptual 30% toll milling margin on processing and G&A costs.

Extremely capital efficient with after-tax NPV

5%

to Initial Capital Cost ratio of

3.0

at US$2,550/oz

Au and

5.0

at a spot gold price of US$3,300/oz Au.

Production Profile:

11-Year Mine Life with

740 koz

mined and

647 koz

recovered at

87%

average recovery with a

gravity-flotation-regrind-leach flowsheet.

70 koz/annum

average steady-state gold production (Years 2-8) at an average annual after-tax

Free Cash Flow ("FCF") of

$97M

.

Underground mining with long-hole stoping and minimal surface facilities.

Radisson will host a technical webinar on the O'Brien PEA on Wednesday July 9, 2025 at 11am ET

(8am PT). Participants may register

here

. A recording will be available following the webinar.

Matt Manson, President & CEO, commented:

"We are pleased to be reporting today the first modern

mining study for the O'Brien Gold Project. This PEA builds upon the milling assessment completed

earlier this year that demonstrated the potential viability of processing O'Brien mined material at a

neighbouring mill. The result is a low cost and high value project should a beneficial milling

arrangement be secured. By taking advantage of existing infrastructure in the region, the study

surfaces considerable value for O'Brien while minimizing its environmental impact. The extremely

high NPV

5%

to cost ratio demonstrates the efficient allocation of capital that this approach offers.

"Rather than high-grading the deposit, as was the case with the historic O'Brien Mine, the PEA is

developed from the existing MRE with a lower cut-off, yielding more ounces, more tonnes and better

mining continuity at lower average grades. From that starting point, we are presenting a fully

underground mine plan, right sized at 1,200 tonnes per day ("tpd") and optimized at a cautious

US$2,000/oz gold price assumption, delivering 740,000 ounces of gold to the mill at high margins

over an 11-year life. The O'Brien Gold Project's legacy of high grades and visible gold continues to be

an attribute of the current mine design and the ongoing exploration."

Pierre Beaudoin, Chairman of the Board of Directors, commented:

"The PEA announced today is a

significant step forward for Radisson. The study outlines a credible mine plan and development

strategy for O'Brien, offering shareholders significant value even on the existing mineral resources.

This is also just a snap-shot of a project that is continuing to grow. The ongoing drill program is

demonstrating impressive new gold mineralization outside the scope of this initial mine design. On

the basis upon which the PEA is developed, we believe a significantly larger mineral inventory exists

to our exploration horizon of 2,000 m depth. Recent drill results are supporting this thesis."

Matt Manson continued

: "We see in O'Brien a broad system of mineralization with significant scale

potential. Our current focus at Radisson is to maximize this potential through the recently expanded

drill program and our strong treasury. Today's PEA, however, establishes a project development path

that is practical and highly rewarding. We intend to further pursue this path with environmental

baseline studies, additional engineering and mine plan optimization, community consultation, and

dialog with potential processing partners."

VIDEO: President & CEO Matt Manson comments on today's news

O'Brien Gold Project Preliminary Economic Assessment

The PEA was completed by Ausenco Engineering Canada ULC ("Ausenco") as lead consultant with

specific responsibility for metallurgy, processing design, infrastructure and financial modelling.

InnovExplo (a member of Norda Stelo Inc.; "Norda Stelo") completed the mine design and mine

scheduling, BBA Inc. were responsible for water management, surface facilities, and a review of the

Project's environmental assessment procedure and permitting requirements, and SLR Consulting

(Canada) Ltd. ("SLR") were responsible for the MRE.

The PEA is a companion study to a recently completed milling assessment for the Project in which a

metallurgical program was conducted with representative samples of mineralized core from O'Brien. The

samples were tested based on a series of flow sheet options which would conceptually be compatible

with the nearby Doyon gold mill, part of IAMGOLD's Westwood Mine Complex, with minimal adjustment

to the existing Doyon mill configuration. The milling assessment was conducted under a Memorandum of

Understanding ("

MOU

") with IAMGOLD (

Radisson news release dated September 9, 2024

).

The MOU

is non-binding and non-exclusive and contains no specific terms around potential commercial

arrangements between the parties. The PEA has been completed independently by Radisson and

establishes criteria for the development of O'Brien based on processing and tailings management at an

existing off-site facility under a toll milling arrangement.

Cautionary statement

: Readers are cautioned that the PEA is preliminary in nature, it includes inferred

mineral resources that are considered too speculative geologically to have economic considerations

applied to them that would enable them to be categorized as mineral reserves, and there is no certainty

that the PEA will be realized.

Table 1

: Summary of Key Results and Assumptions in the PEA

Production Data

note 1

Values

Units

Life-of-Mine

11

Years

Total Resource Mined

4,575

kt

Total Waste Mined

3,314

kt

Average Head Grade

5.0

g/t Au

Contained Gold

740

koz

Recovered Gold

647

koz

Average Gold Recovery

87%

Years 2-8: Steady State Run-Rate

note2

Average Production Mining Rate

1,160

tpd

Average Annual Gold Production

70

koz

Average Head Grade

4.9

g/t Au

Annual Average After-Tax Free Cash Flow

$97

C$M

Capital Costs

note 1

Values

Units

Initial Capital

$175

C$M

Sustaining Capital (Excluding Closure)

$173

C$M

Capital Intensity (Initial Capital/oz milled)

$172

US$/oz

Life-of-Mine Operating Costs

notes 1

,3

Values

Units

Mining

note 3

$76

C$/t milled

Processing

$38

C$/t milled

G&A

$31

C$/t milled

30% Processing Toll

note 4

$19

C$/t milled

Total Operating Cost

$163

C$/t milled

Refining & Transport

$6

US$/oz

Royalties

$10

C$M

Total Cash Cost

$861

US$/oz

All-In Sustaining Cost

note 5

$1,059

US$/oz

Financial Analysis

note 1

Values

Units

Gold Price for Financial Analysis

$2,550

US$/oz

US$:C$ Exchange

$0.73

Pre-Tax NPV

5%

$782

C$M

Pre-Tax IRR

65%

Pre-Tax Payback

1.4

years

After-Tax NPV

5%

$532

C$M

After-Tax IRR

48%

After-Tax Payback

2.0

years

Mine Revenue

$2,258

C$M

EBITDA

$1,496

C$M

EBITDA Margin

66%

Pre-Tax Unlevered Free Cash Flow

$1,146

C$M

After-Tax Unlevered Free Cash Flow

$803

C$M

Note

s:

1

.

Denotes a "specified financial measure" within the meaning of NI 52-112. See note on "Non-IFRS Financial Measures".

2

.

Represents full calendar years

3

.

LOM operating costs includes cash operating costs during the initial capital period. Mining operating costs exclude waste development

costs and mobile equipment costs which are captured as sustaining capital items

4

.

Processing toll milling charges are conceptual and have been estimated by Ausenco based on recent industry precedent

5

.

AISC inclu

des Royalties, Total Cash Costs and Sustaining Capital, including closure costs. Excludes corporate G&A.

Mineral Resources

The MRE for the Project was originally disclosed in March 2023 (

Radisson news release dated March

2, 2023

) based on 325,509 m of drilling completed to the end of 2022 and authored by SLR. Indicated

Mineral Resources were estimated at 0.50 million ounces (1.52 million tonnes at 10.26 g/t Au) with

additional Inferred Mineral Resources of 0.45 million ounces (1.60 million tonnes at 8.66 g/t Au). The

2023 study utilized a 4.5 g/t Au cut-off at US$1,600/oz Au with certain assumptions for minimum mining

width, mining costs, C$:US$ exchange and metallurgical recovery. Mineral Resources that are not

Mineral Reserves do not have demonstrated economic viability.

For the purposes of the PEA, the 2023 block model was re-blocked by SLR in the Z-direction to 5 m to

allow for more flexible underground mine design, and an updated cut-off and set of economic criteria

were applied consistent with Deswick Stope Optimizer ("DSO") parameters used for the optimization of

the underground mine schedule and the Project's recent milling assessment. The MRE now utilizes a cut-

off of 2.2 g/t Au at US$2,000/oz Au. No other changes were made. This has the effect of increasing

tonnage and ounces and decreasing average grade compared to the previous estimate (Table 2).

Table 2

: Mineral Resource Estimate Using a 2.2 g/t Au Cut-Off and US$2,000/oz Gold Price

(

Numbers in Italics Represent Changes from the MRE based on a 4.5 g/t Au Cut-Off and

US$1,600/oz Gold Price.)

Category

Tonnes (kt)

Grade (g/t Au)

Oz (koz Au)

Indicated

2,204

+45%

8.2

-20%

582

+16%

Inferred

6,671

+317%

4.4

-50%

932

+109%

N

ot

es:

1

.

Prepared in accordance with the Canadian Institute of Mining, Metallurgy and Petroleum (CIM) Definition Standards (2014) and Best

Practice Guidelines of Mineral Resources and Reserves (2019).

2

.

Mineral Resources are reported above a cut-off grade of 2.2 g/t Au based on a C$172.5/t operating cost.

3

.

Mineral Resources are estimated using a long-term gold price of US$2,000/oz Au, a US$:C$ exchange rate of 1:1.33, and a metallurgical

recovery of 90%.

4

.

Wireframes were modelled at a minimum width of 1.2 m.

5

.

Bulk density varies by deposit and lithology and ranges from 2.00 t/m³ to 2.82 t/m³.

6

.

Full length composites were capped 40 g/t Au.

7

.

Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

8

.

Numbers may not a

dd

due to rounding.

Between the end of 2022 and the present, Radisson completed approximately 50,000 m of additional

drilling at the Project. Drilling that was completed within the volume of the MRE is assessed to have no

material impact on the overall contained mineral resource, such that the MRE is appropriate in SLR's

opinion for mine planning. Drilling that was completed outside the volume of the MRE, including below

the level of the historic mine workings at O'Brien, has indicated the presence of significant additional

gold mineralization that is not incorporated in the current conceptual mine plan. Radisson expects to

complete a further 50,000-60,000 m of drilling in 2025 and 2026, at which time the Company expects to

complete an updated MRE.

Mining

The PEA describes an 11-year mine life based on the mining of 4.57 Mt of mineralized material and

3.31 Mt of waste rock (Table 3). Mining will be fully underground with long-hole stoping and a cemented

rock backfill. Stope design is benefitted by good spatial continuity of reported resource blocks at the

lower cut-off grade. Minimum and average stope widths are 2.2 m and 2.7 m respectively, including 0.7

m of planned dilution. The mine will be accessed by way of twin 4.5 m by 4.5 m ramps from surface to a

depth of 950 m with 86 kilometres (km) of development. Mining equipment includes 20 tonne trucks with

rock haulage assisted by vertical conveyors delivering mined material from the 300 m level to a surface

run-of-mine pad. The underground mine design does not incorporate any infrastructure from the historic

O'Brien Mine. A shaft at the historic Kewagama Mine site east of O'Brien will be reused for ventilation.

Mined material will be trucked by road for processing.

Table 3

: Mined Material

Material

Tonnes

(kt)

Oz

(koz Au)

Head Grade

(g/t Au)

Production Stopes

3,146

588

5.8

Marginal Stopes

169

16

2.9

Development

469

91

6.0

Low-Grade Development

790

45

1.8

Total Mineralized Mined Material

4,575

740

5.0

Waste

3,314

n/a

n/a

Figure 1:

Annual Average Production Schedule

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/10977/258183_1e2a85bb743ed9d7_002full.jpg

The underground mine was designed and production scheduled on the basis of a DSO optimization at

US$2,000 Au and production cut-off grades of 3.05 g/t Au and 3.11 g/t Au depending on the royalty to be

considered. "Mined Material" is categorized as Production Stope Material, Marginal Stope Material,

Development Material, Low-Grade Development Material and Waste. In Years 2-8 during which the

Project maintains steady-state operation, production from stopes averages 1,160 tpd. However, the

PEA contemplates up to 2,000 tpd of mill capacity. Consequently, all mineralized mined material is

scheduled for processing (Figure 1), resulting in an average head grade of 5.0 g/t Au, delivering an

average of 1,410 tonnes of mined material daily to the mill, and eliminating the requirement for a low-

grade stockpile.

Mineral Resources not included in the mine plan are those considered too isolated or too marginal at a

US$2,000/oz DSO optimization. The mine design also excludes Mineral Resources located in the

former Thompson Cadillac mine area or in areas considered too close to the historic workings. The

quantity of mineralized mined material in the mine design is highly sensitive to the gold price

assumption, with the DSO optimization delivering significantly more mined material in both existing

production stopes and development areas, as well new stopes and development areas, at higher gold

prices.

Infrastructure and Site Facilities

The Project is located adjacent to the Trans-Canada Highway 117 and has existing road access to the

historic O'Brien mine site. The PEA contemplates twin underground mine portals located 2 km to the

east of the historic site, with new haul roads, a waste rock pad, a run-of-mine pad, laydown areas, the

surface installation of a vertical conveyor, trenches and sumps for water management, and a waste-

water treatment plant. The PEA does not contemplate a mill, tailings deposition, accommodation camp,

or major maintenance facilities. Small vehicle maintenance and site offices/mine dry will be provided

from existing facilities or temporary modules. A new substation will derive power from the adjacent 112

kV high voltage transmission line operated by Hydro-Québec.

Processing

(See footnote 1)

The PEA contemplates processing and tailings deposition at an off-site facility. To assess the viability of

this scenario, Radisson conducted a metallurgical study and milling assessment under the auspices of

an MOU with IAMGOLD to assess the design criteria for processing O'Brien mined material at the

nearby Doyon gold mill, the processing facility for IAMGOLD's Westwood Mine Complex. The Doyon mill

is located 21 km west of O'Brien and directly accessible along Trans-Canada Highway 117.

The metallurgical results of this milling assessment were previously reported (

see Radisson news

release dated February 3, 2025

) and are incorporated into the PEA. Gold recoveries of between 86%

and 96% were obtained based on a series of flow sheet options, all of which are compatible with the

Doyon mill with minimal or modest additional capital. The metallurgical program was undertaken at the

Lakefield, Ontario facilities of SGS Canada Inc. under the supervision of Ausenco.

The Doyon mill currently operates at approximately 3,000 tpd with a conventional cyanidation process.

Mined material is processed with a primary crusher and a two-stage semi-autogenous SAG mill/Ball mill

grinding at 75 µm (P80). Leaching is by way of two stage Carbon-in-Leach and Carbon-in-Pulp circuits.

The PEA contemplates a Gravity-Flotation-Regrind-Leach flow sheet and assumes Radisson deploying

$21M of capital to upgrade the gravity and flotation circuits at Doyon that have been used previously but

are currently inactive.

The Doyon mill currently processes approximately 1,000 tpd from the underground Westwood mine and

approximately 2,000 tpd from the nearby Grand Duc open pit. Processing of Grand Duc material is

estimated to be completed in early 2027, as outlined in the Westwood Mine Complex technical report

dated September 30, 2024. Hence, the PEA envisions up to 2,000 tpd of mill capacity available for

O'Brien at Doyon, allowing for the direct shipment of both production material

and

lower grade

development material at an average of 1,400 tpd. The PEA does not anticipate the stockpiling of low-

grade mined material at the O'Brien site, resulting in a significant cost saving.

Life-of-mine average gold recovery with the Gravity-Flotation-Regrind-Leach flowsheet is estimated at

87%. This is based on 90% recovery for the O'Brien metallurgical sample at an average grade of 6.3 g/t

Au and the application of a grade-recovery model to the average head-grade expected in the PEA of 5.0

g/t Au after the processing of low-grade development materials.

O'Brien gold mineralization is associated with pyrite and arsenopyrite. The metallurgical program

determined average arsenic values of 0.4% to 0.5% in whole rock, relevant if material is being sent to

tailings deposition on-site, and 4.6% in flotation concentrate, relevant if a concentrate is being sold to an

off-take agent. These values are consistent with precedent projects in Québec's Abitibi and offtake

threshold limits for concentrates of high-grade gold projects. The PEA contemplates tailings deposition

after leach without a segregated tailings impoundment. If one is required, additional capital expenses

would be incurred.

The PEA contains estimates of operating and capital costs for trucking, processing, tailings

management and G&A developed by Ausenco from first principles based on the metallurgical results

and precedent projects. These costs correspond well to recently reported operating results from the

Doyon facility. The PEA's financial results reflect an additional 30% charge on processing and G&A

costs, corresponding to approximately $19/t, to reflect the impact of a potential toll milling charge. The

MOU between Radisson and IAMGOLD contains no specific terms around potential commercial

arrangements between the Parties, including the use of the Doyon mill or the terms of potential toll-

milling. There is no certainty that any arrangement between the Parties will result from their dealings

pursuant to the MOU, which is non-binding and non-exclusive.

Capital and Operating Costs

(See footnote 1)

Initial Capital costs (Table 4) are estimated at $175M and reflect costs incurred during a 21-month

period of early works, mill modification and principal mine construction to the end of the first quarter of

Year 2 and the attainment of commercial production. The Initial Capital cost estimate excludes both pre-

production mine operating costs and revenue, which are reflected in the Life-of-mine operating cost and

revenue estimates, and excludes development costs incurred prior to the commencement of early works.

Contingencies on individual capital line items in the underground mine design are at 15%, developed

within the material, productivity and cost estimates. Contingencies on non-underground mine items, and

on mill modifications and surface facilities, are at 25%.

Life-of-mine Sustaining Capital costs are estimated at $173M and reflect capital costs incurred after the

first quarter of Year 2, including underground mine development costs in waste rock and underground

mine infrastructure, but excluding mine closure and salvage. Mobile mining equipment is scheduled to be

purchased in installments, and is represented as Initial Capital, to the extent that a payment or deposit

occurs within the project construction period, and as Sustaining Capital to the extent it occurs during the

operating phase.

Table 4:

LOM Capital Costs

Item

note 1,2

Cost (C$M)

Mining Capex

$93

Mobile Equipment

$25.7

Mine Development

$47.4

Buildings

$0.4

Mine Services

$19.7

Process Plant

$21

Flotation

$4.5

Regrind

$14.1

Reagents

$2.0

Onsite Infrastructure

$16

Offsite Infrastructure

$8

Indirects

$14

Owners Costs

$4

Cash Contingency

$20

Total Initial Capital

$175

Sustaining Capital

$173

Closure

$5

Salvage

$(3)

Total

$ 350

Notes:

1

.

Denotes a "specified financial measure" within the meaning of NI 52-112. See note on "Non-IFRS Financial Measures".

2

.

Columns may not sum exactly due to rounding.

Mining, haulage and water management operating costs (Table 5) are estimated at $75.66/t milled

(LOM). These are developed by Norda Stelo from first principles based on recent precedent projects

with similar mining methodologies and location. Total life-of-mine mining costs, including mining related

Initial Capital, Sustaining Capital and Operating costs are $581M, or $127/t milled. Processing and

G&A cost estimates are developed by Ausenco from first principles based on the results of the milling

assessment conducted at the Doyon mill and based on recent precedent projects. Toll Milling Charges

are conceptual and have been estimated by Ausenco based on recent industry precedent.

Total Cash Costs are US$861/oz with AISC of US$1,059/oz (LOM). AISC³ during the steady-state

operations of Years 2-8 is estimated at US$1,106/oz.

Table 5

: Life-of-Mine Operating Costs and AISC

Item

note1,2

Value

Units

Mining, Haulage and Water Management

$346

C$M

$75.66

C$/t milled

Processing & Tailings Treatment

$173

C$M

$37.71

C$/t milled

Process Toll

note3

$87

C$M

$18.94

C$/t milled

G&A

$142

C$M

$31.06

C$/t milled

Total

$747

C$M

$163.38

C$/t milled

Off-Site Costs, Refining and Transport

$6

C$M

Royalties

$10

C$M

Total Cash Costs

$861

US$/oz Au

Sustaining, Closure, Salvage Capital

$197

US$/oz Au

Total AISC

note4

$1,059

US$/oz Au

Notes:

1

.

Denotes a "specified financial measure" within the meaning of NI 52-112. See note on "Non-IFRS Financial Measures".

2

.

Columns may not sum exactly due to rounding.

3

.

Conceptual and estimated based on recent industry precedent.

4

.

AISC includes Royalties, Total Cash Costs and Sustaining Capital, including closure costs and corporate G&A.

Financial Analysis

At a long-term consensus gold price of US$2,550 and an exchange rate of 0.73 (US$/C$) the Project

generates an after-tax NPV

5%

of $532M and IRR of 48% (unlevered; Table 6). Payback on initial capital

is 2.0 years. The Project's valuation is discounted to Year -0.5 when early works would be scheduled to

commence.

Table 6:

Valuation Sensitivities to the Gold Price (after-tax, unlevered)

Gold Price (US$/oz)

Price Case

$1,800

Downside

$2,200

$2,550

Base Case

$3,000

Upside

$3,300

Spot

$4,000

After Tax NPV (C$M)

0%

$340

$587

$803

$1,081

$1,266

$1,698

3%

$244

$448

$626

$856

$1,009

$1,366

5%

$193

$374

$532

$736

$871

$1,188

8%

$134

$286

$419

$591

$705

$971

10%

$102

$239

$358

$512

$614

$853

IRR

21%

35%

48%

64%

74%

100%

NPV

5%

/Capex

1.1

2.1

3.0

4.2

5.0

6.8

Payback

note 2

Years

4.3

2.7

2.0

1.4

1.1

0.7

Total After Tax FCF

note1, 3

C$M

$340

$587

$803

$1,081

$1,266

$1,698

Average Annual FCF

note1, 4

C$M

$48

$74

$97

$127

$147

$194

Notes:

1

.

Denotes a "specified financial measure" within the meaning of NI 52-112. See note on "Non-IFRS Financial Measures".

2

.

Payback is defined as achieving cumulative positive free cashflow after all cash costs and capital costs, including sustaining.

3

.

Calculated LOM, unlevered.

4

.

Calculated for Years 2-8 of steady state production, unlevered.

LOM EBITDA is estimated at $1.5 billion ("B"), with an effective EBITDA margin of 66%. LOM after-tax

FCF is estimated at $0.8B on an unlevered basis. Annual average after-tax FCF during the steady-state

operations of Years 2-8 is estimated at $97M. The Project is forecast to generate federal and provincial

income taxes and mining duties of $343M.

At spot gold of US$3,300/oz gold, the Project generates an after-tax NPV

5%

of $871M, IRR of 74%, and

payback on initial capital of 1.1 years. The Project is cash positive after-tax at gold prices above

US$1,260/oz.

The Project is most sensitive to revenue attributes such as gold price, head grade and exchange rate,

followed by operating cost and capital cost (unlevered; Table 7). Valuation sensitivities on conceptual

toll-milling charges expressed as margins on processing and G&A costs of between 0% and 60%. At

0% toll, the Project has an after-tax NPV

5%

of $578M and IRR of 52% (unlevered; Table 8).

A 2% Net Smelter Royalty ("NSR") is applied on gold production on certain claims on the easternmost

portion of the property in the favour of Globex Mining Enterprises Inc., covering approximately 22% of the

scheduled gold production.