Rock Tech Conducting Trade-off Study of Electricity Supply Options for Georgia Lake

Corporate Updates

Rock Tech Lithium Inc.

600-777 Hornby Street | Vancouver | British Columbia | Canada | V6Z 1S4

P. +1.778.358.5200 | F. +1.604.670.0033

www.rocktechlithium.com | [email protected]

TSXV: RCK | Frankfurt: RJIB

Rock Tech Conducting Trade-off Study of Electricity Supply Options for Georgia Lake

Vancouver, BC, Canada – August 19, 2019 – Rock Tech Lithium Inc. (the "Company" or

“Rock Tech”) (TSX-V: RCK; Frankfurt: RJIB) announces that it is conducting a trade-off study

of the electricity supply options at its 100%-owned Georgia Lake lithium project in Ontario,

Canada.

The Province of Ontario is home to a robust and reliable electricity system that is powered by

very clean energy. In 2018, Ontario’s electricity system was over 93% carbon-free with 61% of

electricity coming from nuclear power plants. In addition, hydro power contributed 25% of

Ontario’s electricity needs with the remainder coming from wind, gas, solar and biomass.

“The location of our Georgia Lake lithium project provides us with many options for electricity

supply,” said Dirk Harbecke, Rock Tech’s chairman. “This lithium project has best-in-class

infrastructure with an existing 115 kilovolt transmission line less than 5 kilometres from the

preliminary site of spodumene concentration. Furthermore, the project is endowed with access

roads and in very close proximity to professional services and exploration personnel, railyards,

lines and the Port of Thunder Bay. The outlines of a transmission corridor established in the late

1950’s, when a production decision was made, remains. Both the transportation and transmission

corridors have already been secured and are part of our land package at Georgia Lake.”

Figure 1 – Transportation and Transmission Corridors

The trade-off study will include a comparison of capital and operating expenses of connecting to

the existing grid, managed by the Independent Electricity Supply Operator (“IESO”) and Hydro

One Networks Inc. (“Hydro One”), or purchasing from an Independent Power Producer (“IPP) in

conjunction with on-site power generation.

Rock Tech Lithium Inc.

600-777 Hornby Street | Vancouver | British Columbia | Canada | V6Z 1S4

P. +1.778.358.5200 | F. +1.604.670.0033

www.rocktechlithium.com | [email protected]

TSXV: RCK | Frankfurt: RJIB

All scientific and technical information in this news release concerning the Georgia Lake lithium

property was reviewed and approved by Karl-Stephan Peters, EurGeol 787, a qualified person

(QP) as defined under National Instrument 43-101.

Georgia Lake Lithium Project Infrastructure

The Georgia Lake lithium project has best-in-class infrastructure. The main resource zone is just

5 kilometres from the Trans Canada Highway with a series of logging roads providing year-

round access to all areas of the property. Furthermore, just 5 kilometres to the east is an existing

115 kV transmission line providing a grid connection. The neighbouring towns of Beardmore

and Nipigon provide ample housing, personnel and supplies. The world-class mining hub of

Thunder Bay, less than two hours by car, provides access to the Port of Thunder Bay, the

Figure 2 - Transmission corridor extending from main

resource zone to existing Hydro One powerline.

Rock Tech Lithium Inc.

600-777 Hornby Street | Vancouver | British Columbia | Canada | V6Z 1S4

P. +1.778.358.5200 | F. +1.604.670.0033

www.rocktechlithium.com | [email protected]

TSXV: RCK | Frankfurt: RJIB

Thunder Bay International Airport and all needed exploration, engineering and mining

professionals.

About the Georgia Lake Lithium Project

The Georgia Lake lithium project is a lithium-rich pegmatite vein deposit with measured and

indicated resources of 6.57 million tonnes grading 1.01% Li2O in addition to inferred resources

of 6.72 million tonnes grading 1.16% Li2O. The first PEA for the project, focused exclusively on

the main resource area which hosts less than 80% of total defined resources to date, was

published in October 2018. Highlights from the PEA included an NPV of $312 million and an

IRR of 62.2%. While the Georgia Lake lithium project has received extensive exploration and

development investment over the years, there remains extensive areas for future exploration and

discovery located both within and adjacent to the main resource area.

On behalf of the Board of Directors,

"Martin Stephan"

Martin Stephan

Director, Chief Executive Officer

For further information, please contact:

Brad Barnett

Chief Financial Officer

Rock Tech Lithium Inc.

777 Hornby Street, Suite 600

Vancouver, B.C., V6Z 1S4

Telephone: (778) 358-5200

Facsimile: (604) 670-0033

Email: [email protected]

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture

Exchange) accepts responsibility for the adequacy or accuracy of this release.

Statements included in this announcement, including statements concerning our plans, intentions and expectations, which are not

historical in nature a re intended to be, and are hereby identified as, "forward ‐looking statements". Forward‐looking statements

may be identified by words including "anticipates", "believes", "i ntends", "estimates", "expects" and similar e xpressions. The

Company cautions readers that forward‐looking statements, including without limitation those relating to the Company' s future

operations and business prospects, are subject to certain risks and uncertainties that could cause actual results to differ materially

from those indicated in the forward‐looking statements.