Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

PTM.TO ·

Platinum Group Metals Ltd. Announces Positive Independent Definitive Feasibility Study for the Waterberg Palladium Mine IRR Post Tax of 20.7% at Spot Metal Prices Including an

Economic Studies

838 – 1100 Melville Street

Vancouver, BC V6E 4A6

P: 604-899-5450

F: 604-484-4710

News Release No. 19-400

September 24, 2019

Platinum Group Metals Ltd. Announces Positive Independent

Definitive Feasibility Study for the Waterberg Palladium Mine

IRR Post Tax of 20.7% at Spot Metal Prices Including an

Estimated Smelter Discount (September 4, 2019)

Proven and Probable Mineral Reserves Estimated at

19.5 Million Ounces of Palladium, Platinum, Gold and Rhodium

for a Life of Mine Plan of 45 years

Annual Steady State Production of 420,000 Ounces of

Palladium, Platinum Gold and Rhodium plus 16.7 million Pounds

of Nickel and Copper

Fully Mechanised, Shallow, Decline-Accessed Mine would be

One of the Largest and Lowest

Cash Cost Underground PGM Mines Globally

(Vancouver/Johannesburg) Platinum Group Metals Ltd. (PTM-TSX; PLG-NYSE American)

(“Platinum Group” or the “Company”) announces positive results from an Independent

Definitive Feasibility Study (“DFS”) on the Waterberg Project (the “Project”) completed by

international and South African engineering firms Stantec Consulting International LLC

(“Stantec”) and DRA Projects SA (Pty) Ltd. (“DRA”) along with a large team of specialists.

The DFS was managed by Waterberg JV Resources (Pty) Ltd. (“Waterberg JV”) representing

the owners of Platinum Group, Impala Platinum Holdings Ltd. (“Implats”), Japan Oil, Gas and

Metals National Corporation (“JOGMEC”), Ha nwa Co. Ltd. (“Hanwa”) and Mnombo Wethu

Consultants (Pty) Ltd. (“Mnombo”). All of the partners contributed actively to the Project

through the technical committee and the Board of Waterberg JV.

Highlights of the DFS include:

 A significant increase in Mineral Reserves from the Project’s 2016 Pre-Feasibility Study

(“PFS”) for a large-scale, shallow, decline-accessible, mechanised, palladium, platinum,

gold and rhodium (“4E”) mine. Use of backfill in the DFS design lowers risk and increases

mined ore extraction rates.

 Annual Steady State production rate of 420, 000 4E ounces, which is a lower production

rate than in the PFS. This result is by careful design in order to reduce capital costs and

simplify construction and ramp-up.

 After-tax Net Present Value (“NPV”) of US$ 982 million, at an 8% real discount rate, using

spot metal prices as at September 4, 2019 (Incl. US$ 1,546 Pd/oz) (“Spot Prices”).

2

 After-tax NPV of US$ 333 million, at an 8% real discount rate, using three-year trailing

average metal prices up until September 4, 2019 (Incl. US$ 1,055 Pd/oz) (“Three Year

Trailing Prices”).

 After-tax Internal Rate of Return (“IRR”) of 20.7% at Spot Prices and 13.3% at Three

Year Trailing Prices.

 Estimated project capital of approximately US$ 874 million, includin g US$ 87 million in

contingencies. Peak project funding estimated at US$ 617 million.

 On site Life of Mine (LOM) average cash cost (inclusive of by-product credits and smelter

discounts) for the Spot Metal Price scenario equates to US$ 640 per 4E ounce.

 Updated Measured and Indicated Mineral Resources of 242 million tonnes at 3.38g/t 4E

for 26.4 million 4E ounces (using 2.5 g/t 4E cut-off) and the deposit remains open on

strike to the north and below an arbitrary depth cut-off of 1,250-meters.

 Proven and Probable Mineral Reserves of 187 million tonnes at 3.24 g/t 4E for 19.5 million

4E ounces (using 2.5 g/t 4E cut-off).

R. Michael Jones, CEO and co-founder of Platinum Group said, “The DFS provides a clear

outline of the world-class nature of the Wate rberg Palladium deposit and concludes that it

can be one of the largest fully mechanised, lo w cost platinum group metals mines in the

world. A large global team of approximatel y 100 independent professionals and specialists

as well as excellent participation from our partner Implats, have contributed to an optimized

mining plan that reduced capital from the earlier plan and significantly increased the Mineral

Reserves for a 45 year life, 420,000 4E ounce per year steady state mine plan”.

The Waterberg Project will create approximately 1,100 new highly skilled jobs and a

significant investment in local training and busi ness opportunities is part of the benefits to

stakeholders including local communities, shareholders, provincial and national

governments. The Project includes an upgrad e to the local water infrastructure under a

current co-operation agreement with the municipality and a connection to the Eskom power

grid.

3

Total Ounces Produced – Life of Mine

MINERAL RESOURCES AND RESERVE UPDATES

The Mineral Resources for the Waterberg Proj ect have been updated and have increased

slightly based on recent in-fill drilling. The Mineral Resources have been estimated based on

441 diamond drill holes and 583 deflections and has been stated at a 2.5 g/t 4E cut-off (the

base-case). In the DFS, a 2.5 g/t 4E cut-off grade has been applied to the Mineral Resource

model as an input into the mine design. At th e 2.5 g/t 4E cut-off grade, the total Measured

and Indicated Mineral Resources are estimated at 242 million tonnes grading 3.38 g/t 4E for

an estimated 26.4 million ounces 4E. Total Mineral Reserves at a 2.5 g/t 4E grade cut-off are

estimated at 187 million tonnes for 19.5 million ounces 4E. Waterberg is effectively estimated

in four zones and three complexes, each with twin declines from surface. The South Complex

has T Zone and F Zone Mineral Resources and Reserves. The Central Complex currently has

just F Zone Mineral Resources and Reserves, is the largest part of early production and also

has potential for expansion on the T Zone Mineral Resources. The North Complex just has F

Zone Mineral Resources and Reserves and is planned for the later part of the mine life from

2044 out to 2066. Future drilling from surface and underground is expected to result in the

delineation of additional Mineral Reserves, thereby extending the Project mine life. The

Mineral Resources are estimated in the two zones with the T Zone approximately 350 meters

above the F Zone with both zones striking northeast and dipping at approximately 38 degrees

to the west. An arbitrary depth cut-off of 1,250-meters has been applied in all zones.

The Mineral Reserves are a subset of the Mineral Resource envelope at a 2.5 g/t 4E cut-off

and they include only Measured and Indicat ed Mineral Resources with dilution and stope

shapes considered. A minimum mining thickness of 2.4 meters and sublevel planning of 20

meters to 40 meters was considered in the mine plan for Mineral Reserves.

4

The Mineral Resources for the Waterberg Project are categorised and reported in terms of

the National Instrument for the Standards of Di sclosure for Mineral Projects within Canada,

2011 (“NI 43-101”) and are tabulated below.

Mineral Resource Estimate at 2.5 g/t 4E cut-off,

effective September 4, 2019 on 100% Project basis

T Zone at 2.5 g/t (4E) Cut-off

Mineral

Resource

Category

Cut-off

Tonnage

Grade Metal

4E Pt Pd Rh Au 4E Cu Ni 4E

g/t Tonnes g/t g/t g/t g/t g/t % % kg Moz

Measured 2.5 4,443,483 1.17 2.12 0.05 0.87 4.20 0.150 0.080 18,663 0.600

Indicated 2.5 17,026,142 1.37 2.34 0.03 0.88 4.61 0.200 0.094 78,491 2.524

M+I 2.5 21,469,625 1.34 2.29 0.03 0.88 4.53 0.189 0.091 97,154 3.124

Inferred 2.5 21,829,698 1.15 1.92 0.03 0.76 3.86 0.198 0.098 84,263 2.709

F Zone at 2.5 g/t (4E) Cut-off

Mineral

Resource

Category

Cut-off

Tonnage

Grade Metal

4E Pt Pd Rh Au 4E Cu Ni 4E

g/t Tonnes g/t g/t g/t g/t g/t % % kg Moz

Measured 2.5 54,072,600 0.95 2.20 0.05 0.16 3.36 0.087 0.202 181,704 5.842

Indicated 2.5 166,895,635 0.95 2.09 0.05 0.15 3.24 0.090 0.186 540,691 17.384

M+I 2.5 220,968,235 0.95 2.12 0.05 0.15 3.27 0.089 0.190 722,395 23.226

Inferred 2.5 44,836,851 0.87 1.92 0.05 0.14 2.98 0.064 0.169 133,705 4.299

Waterberg Aggregate Total 2.5 g/t (4E) Cut-off

Mineral

Resource

Category

Cut-off

Tonnage

Grade Metal

4E Pt Pd Rh Au 4E Cu Ni 4E

g/t Tonnes g/t g/t g/t g/t g/t % % kg Moz

Measured 2.5 58,516,083 0.97 2.19 0.05 0.21 3.42 0.092 0.193 200,367 6.442

Indicated 2.5 183,921,777 0.99 2.11 0.05 0.22 3.37 0.100 0.177 619,182 19.908

M+I 2.5 242,437,860 0.98 2.13 0.05 0.22 3.38 0.098 0.181 819,549 26.350

Inferred 2.5 66,666,549 0.96 1.92 0.04 0.34 3.27 0.108 0.146 217,968 7.008

5

Mineral Resource

Category

Prill Split Waterberg Project Aggregate

Pt Pd Rh Au

% % % %

Measured 28.2 64.4 1.5 5.9

Indicated 29.4 62.6 1.5 6.5

M+I 29.1 63.0 1.5 6.4

Inferred 29.5 58.9 1.2 10.4

Notes:

1. 4E elements are platinum, palladium, rhodium and gold.

2. Cut-offs for Mineral Resources were established by a QP after a review of potential operating costs

and other factors.

3. Conversion factor used for kilograms (“kg”) to ounces (“oz”) is 32.15076

4. A 5% and 7% geological loss was applied to the Measured/Indicated and Inferred Mineral

Resources categories, respectively.

5. The Mineral Resources are classified in accordance with the National Instrument for the Standards

of Disclosure for Mineral projects within Canada, 2011 (“NI 43-101”). Mineral Resources that are

not Mineral Reserves do not have demonstrated economic viability and Inferred Mineral Resources

have a high degree of uncertainty.

6. The Mineral Resources are provided on a 100% Proj ect basis, Inferred and Indicated categories

are separate and the estimates have an effective date of 4 September 2019.

7. Mineral Resources were completed by Mr. CJ Muller of CJM Consulting.

8. Mineral Resources were estimated using kriging methods for geological domains created in

Datamine from 441 mother holes and 583 deflecti ons. A process of geological modelling and

creation of grade shells using indicating kriging was completed in the estimation process.

9. The Mineral Resources may be materially affected by metal prices, exchange rates, labour costs,

electricity supply issues or many other factors detailed in the Company's 2018 Annual Information

Form.

10. The data that formed the basis of the Mineral Re sources estimate are the drill holes drilled by

Platinum Group as project operator, which consist of geological logs, drill hole collars surveys,

downhole surveys and assay data. The area where each layer was present was delineated after

examination of the intersections in the various drill holes.

11. Numbers may not add due to rounding.

Proven Mineral Reserve Estimate at 2.5 g/t 4E cut-off,

effective September 4, 2019 on 100% Project basis.

Proven Mineral Reserve Estimate at 2.5 g/t 4E cut-off

Pt Pd Rh Au 4E Cu Ni 4E Metal

Zone Tonnes (g/t) (g/t) (g/t) (g/t) (g/t) (%) (%) Kg Moz

T Zone 3,963,694 1.02 1.84 0.04 0. 73 3.63 0.13 0.07 14,404 0.463

F Central 17,411,606 0.94 2.18 0.05 0.14 3.31 0.07 0.18 57,738 1.856

F South - - - - - - - - - -

F North 16,637,670 0.85 2.03 0.05 0.16 3.09 0.10 0.20 51,378 1.652

F Boundary North 4,975,853 0.97 2.00 0.05 0.16 3.18 0.10 0.22 15,847 0.509

F Boundary South 5,294,116 1.04 2.32 0.05 0.18 3.59 0.08 0.19 19,020 0.611

F Zone Total 44,319,244 0.92 2.12 0.05 0.16 3.25 0.09 0.20 143,982 4.629

Waterberg

Project Total 48,282,938 0.93 2.10 0.05 0.20 3.28 0.09 0.19 158,387 5.092

6

Probable Mineral Reserve Estimate at 2.5 g/t 4E cut-off,

effective September 4, 2019 on 100% Project basis

Probable Mineral Reserve Estimate at 2.5 g/t 4E cut-off

Pt Pd Rh Au 4E Cu Ni 4E Metal

Zone Tonnes (g/t) (g/t) (g/t) (g/t) (g/t) (%) (%) Kg Moz

T Zone 12,936,870 1.23 2.10 0.02 0.82 4.17 0.19 0.09 53,987 1.736

F Central 52,719,731 0.86 1.97 0.05 0.14 3.02 0.07 0.18 158,611 5.099

F South 15,653 ,961 1.06 2.03 0.05 0.15 3.29 0.04 0.13 51,411 1.653

F North 36,984,230 0.90 2.12 0.05 0.16 3.23 0.09 0.20 119,450 3.840

F Boundary North 13,312,581 0.98 1.91 0.05 0.17 3.11 0.10 0.23 41,369 1.330

F Boundary South 7,616,744 0.92 1.89 0.04 0.13 2.98 0.06 0.18 22,737 0.731

F Zone Total 126,287,248 0.91 2.01 0.05 0.15 3.12 0.08 0.18 393,578 12.654

Waterberg Project

Total 139,224,118 0.94 2.02 0.05 0.21 3.22 0.09 0.18 447,564 14.390

Proven & Probable Mineral Reserve Estimate at 2.5 g/t 4E cut-off,

effective September 4, 2019 on 100% Project basis

Total Estimated Mineral Reserve at 2.5 g/t 4E cut-off

Pt Pd Rh Au 4E Cu Ni 4E Metal

Zone Tonnes (g/t) (g/t) (g/t) (g/t) (g/t) (%) (%) Kg Moz

T Zone 16,900,564 1.18 2.04 0.03 0.80 4.05 0.18 0.09 68,391 2.199

F Central 70,131,337 0.88 2.02 0.05 0.14 3.09 0.07 0.18 216,349 6.956

F South 15,653,961 1.06 2.03 0.05 0.15 3.29 0.04 0.13 51,411 1.653

F North 53,621,900 0.88 2.09 0.05 0.16 3.18 0.10 0.20 170,828 5.492

F Boundary North 18,288,434 0.98 1.93 0.05 0.17 3.13 0.10 0.23 57,216 1.840

F Boundary South 12,910,859 0.97 2.06 0.05 0.15 3.23 0.07 0.19 41,756 1.342

F Zone Total 170,606,492 0.91 2.04 0.05 0.15 3.15 0.08 0.19 537,560 17.283

Waterberg Project

Total 187,507,056 0.94 2.04 0.05 0.21 3.24 0.09 0.18 605,951 19.482

Notes:

1. The estimated Mineral Reserves have an effective date of September 4, 2019.

2. A 2.5 g/t 4E stope cut-off grade was used for mine planning for the T Zone and the F Zone Mineral

Reserves estimate. The cut-off grade considered April 2018 metal spot prices.

3. Tonnes and grade estimates incl ude planned dilution, geological losses, external overbreak

dilution, and mining losses.

4. 4E elements are platinum, palladium, rhodium and gold.

5. Numbers may not add due to rounding.

MINING PLAN OUTPUTS

The DFS mine plan models production at 4.8 million tonnes of ore per annum and 420,000

4E ounces per year in concentrate. The mine initially accesses the orebody using two sets of

twin decline tunnels with mining by fully mech anised long hole stoping methods with paste

7

backfill. Paste backfill allows for a high mining extraction ratio as mining can be completed

next to backfilled stopes without leaving internal pillars. Maintaining safety and reliability

were key mine design criteria. As a result of th e scale of the orebody, bulk mining on 20 to

40 meter sublevels with large underground equipment and conveyors for ore and waste

transport provides high efficiency. Many of the larger successful underground mines in the

world use the same method of mining with backfill and estimated costs were benchmarked

against many of these operations.

METALLURGICAL RECOVERY AND SMELTER ASSUMPTIONS

Following extensive test work at the PFS and DFS level, DRA, an experienced South African

engineering and EPCM firm, based the plant designs, metallurgical recoveries and costing on

a standard South African flotation MF-2 (Mill – Float – Mill – Float) circuit. Additional

metallurgical checks on mineral types and potential recoveries were completed at XPS Labs

in Sudbury, Ontario. The detailed design is ba sed on this metallurgical test work. Modelled

recoveries were completed for the different recovered elements and zones within the

Waterberg mining complex over the 45-year LOM and an average 4E recovery of 78.9% is

estimated. Copper recoveries are forecast at 83% and nickel recovery is modelled at 48%.

Net payability after smelter discount is estimated to be 85% on the 4E metal, 73% for copper

and 68% for nickel, based on an 80 g/t 4E target concentrate grade sold to a South African

smelter. The discounts on metal values have b een calculated and included as a cost per 4E

ounce for an estimate of financial returns.

The Waterberg Project is planned to produce a sulphide concentrate at a grade that is

attractive to the current operating smelters in South Africa, with no significant penalty

elements. Implats holds a first right of refusal for smelter offtake and Hanwa of Japan holds

the rights to market the final refined metal at market prices.

PROJECT TIMELINE

The DFS project timeline includes a formal construction decision to be taken following the

granting of the Mining Right, expected in Q1 2020 with first production 3.5 years later. The

planned decline access provides for rapid and low-cost access to the shallow orebody. Under

the DFS mine plan, first production is estimated in late 2023 with ramp-up to steady state

by 2027. The LOM on current Mineral Reserves extends to 2066 and the deposit remains

open at depth and on strike.

CAPITAL COSTS AND INFRASTRUCTURE, INCLUDING POWER AND WATER

Capital costs to full production and peak funding of the Project are estimated predominantly

in South African Rand (ZAR), with all cost estimates expressed in ZAR real July 2019 terms.

Peak funding is estimated at US$ 617 million (ZAR 9.26 billion). Modelled costs are converted

to US Dollars at a long-term real exchange rate of 15.00 (ZAR/US$). The real escalation of

costs (in Rand terms) is estimated to be offset, over time, by the future devaluation of the

Rand against the US Dollar.

Regional infrastructure in the DFS capital cost estimate includes road upgrades to access the

mine area, a 74km power line to connect to the Eskom power utility grid and water pipelines

to drilled water resources with associated servitudes. Waterberg JV has executed a water co-

operation agreement with the Capricorn Municipa lity that surrounds the mine and has drill

tested, studied and assessed available water resources together with community needs in

detail. Improvement in service delivery of water to the region is included in the DFS capital

cost estimate and plans. Eskom has agreed to both a ‘self-build’ plan for the electrical

8

infrastructure to an existing substation and the power allocation for the Project. Servitude

work for the power lines is well advanced.

Estimated Project Capital expenditure and anticipated Peak Funding are shown below.

Project Capital Breakdown

Cost Area ZAR Total

(ZAR million Real)

USD Total

(US$ million Real)

Underground Mining 6,097 406

Concentrator 2,580 172

Shared Services and Infrastructure 682 45

Regional Infrastructure 1,229 82

Site Support Services 234 16

Project Delivery Management 654 44

Other Capitalised Costs 331 22

Provisions 1,298 87

Total Project Capital (excl. Capitalised OpEx) 13,105 874

Capitalised Operating Costs 3,453 230

Total Project Capital (incl. Capitalised OpEx) 16,559 1,104

Peak Funding (Spot Prices) 9,255 617

Notes:

1. Project Capital is defined as all required capital expenditure until the Project achieves 70% of

planned steady-state production. This is projected to occur from January 2020 to December 2025.

2. A US$/ZAR exchange rate of 15.00 is used in all cost conversions

3. Post December 2025, the DFS estimates stay-in-business or sustaining capital for the LOM at US$

1.44 billion (ZAR 21.6 billion).

4. The DFS estimates peak funding at US$ 617 million (ZAR 9.26 billion) at Spot Prices, and US$ 667

million (ZAR 10.26 billion) at Three Year Trailing Prices. This includes all spend offset by revenue.

ENVIRONMENTAL, PERMITTING AND COMMUNITIES

A program of public consultati on as part of the formal Mining Right and Environmental

Authorisation applications for the Project wa s completed in August 2019. The process was

undertaken in a climate of mutual respect with good community interaction and comment.

The Environmental Impact Assessment and Environmental Management Programme was

filed on August 15, 2019 and government feedba ck is expected before the end of 2019. A

formal Mining Right Application, including a Social and Labour Plan, was accepted by the

South African Department of Mineral Resources and Energy (“DMR”) on September 14, 2018.

The Company held local public meetings on numerous occasions in advance of the Mining

Right Application and these meetings also had a good spirit of co-operation and mutual

respect. All of this work forms part of the Mining Right Application and a decision by the DMR

is expected in early 2020. The Project plan in the DFS assumes a positive decision during

calendar Q1 2020. Training for a new mechanised mining workforce is an important part of

the DFS and planning has been undertaken with the assistance of global mine training leader,

Norcat, of Sudbury, Ontario. The DFS modelled a significant investment in training, focussed

on the immediate area of the Project, working in co-operation with local colleges and

facilities.