Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

PRU.TO ·

SEPTEMBER 2025 QUARTER REPORT Perseus Mining’s sustained operational performance grows cash & bullion balance to US$837 million

Financials

1

27 OCTOBER 2025

NEWS RELEASE

PERSEUSMINING.COM

SEPTEMBER 2025 QUARTER REPORT

Perseus Mining’s sustained operational performance grows

cash & bullion balance to US$837 million

PERTH, Western Australia/October 27, 2025/Perseus Mining Limited (“Perseus” or the “Company”) (TSX & ASX: PRU)

reports on its activities for the three months’ period ended September 30, 2025 (the “Quarter”).

Operating performance

• 12-month rolling average TRIFR of 0.60 well below industry average.

• Gold produced totalled 99,953 ounces at an AISC of US$1,463 per ounce.

• Average cash margin of US$1,612 per ounce of gold produced, giving notional operating cashflow of US$161 million.

• Cash and bullion of US$837 million, plus liquid listed securities of US$134 million.

• CMA Underground development commenced at Yaouré.

• Nyanzaga project development progressing to plan with first production planned for March Quarter 2027.

FY26 Outlook

• Production and AISC market guidance remains unchanged for the June 2026 Financial Year (FY26) at 400,000 -

440,000 ounces at AISC of US$1,460 – 1,620 per ounce.

• Share buyback programme renewed, with up to A$100 million to be invested over a 12-month period.

Corporate

• Jeff Quartermaine retired as Perseus’s Managing Director and Chief Executive Officer on September 30, 2025 with Craig

Jones assuming the role on October 1, 25.

Key operating indicators and highlights for the September 2025 quarter (Q1 FY26) include:

PERFORMANCE

INDICATOR UNIT MARCH 2025

QUARTER

JUNE 2025

QUARTER

JUNE 2025

HALF YEAR

SEPTEMBER 2025

QUARTER

CALENDAR 2025

YEAR TO DATE

Gold recovered Ounces 121,605 121,237 242,843 99,953 342,795

Gold poured Ounces 122,915 119,868 242,782 103,566 346,349

Production Cost US$/ounce 977 1,038 1,008 1,152 1,050

All-In Site Cost (AISC) US$/ounce 1,209 1,417 1,313 1,463 1,366

Gold sales Ounces 117,585 131,242 248,826 101,589 350,415

Average sales price US$/ounce 2,462 2,977 2,734 3,075 2,832

Notional Cashflow US$ million 152 189 345 161 503

2

NEWS RELEASE | SEPTEMBER 2025 QUARTER REPORT

PERSEUSMINING.COM

OPERATIONS

PRODUCTION, COSTS AND NOTIONAL CASHFLOW

Perseus’s three operating gold mines, Yaouré and Sissingué in Côte d’Ivoire, and Edikan in Ghana, produced a combined

total of 99,953 ounces of gold in Q 1 FY26. The weighted average production cost was US$1, 152 per ounce, while the

weighted average All-in-Site Cost (AISC) was US$1,463 per ounce. 

In Q1 FY26, combined gold sales from all three operations totalled 101,589 ounces or 29,653 ounces less than in Q4 FY25

due to lower production in line with FY26 guidance and the timing of shipments. The weighted average realised gold price

was US$3,075 per ounce, US$98 per ounce more than the Q4 FY25 price of US$2,977 per ounce.

Perseus’s average cash margin for the quarter was US$1, 612 per ounce resulting in notional operating cashflow from all

operations of US$161 million, US$28 million lower than in Q4 FY25.  

Group and mine operating results summarised in Tables 1 to 3 below.

Table 1: Gold Production by Mine

MINE

TOTAL GOLD RECOVERED (OUNCES) TOTAL GOLD POURED (OUNCES)

MARCH 2025

QUARTER

JUNE 2025

QUARTER

SEPTEMBER

2025 QUARTER

CALENDAR

2025 TO DATE

MARCH 2025

QUARTER

JUNE 2025

QUARTER

SEPTEMBER

2025 QUARTER

CALENDAR

2025 TO DATE

Yaouré 68,822 70,259 55,405 194,486 69,697 69,059 57,672 196,428

Edikan 41,668 38,865 32,856 113,389 42,632 38,655 33,583 114,871

Sissingué 11,115 12,113 11,692 34,920 10,586 12,153 12,311 35,050

Group 121,605 121,237 99,953 342,795 122,915 119,868 103,566 346,349

Table 2: Gold Sales by Mine

MINE

TOTAL GOLD SOLD (OUNCES) REALISED GOLD PRICE (US$ PER OUNCE)

MARCH 2025

QUARTER

JUNE 2025

QUARTER

SEPTEMBER

2025 QUARTER

CALENDAR

2025 TO DATE

MARCH 2025

QUARTER

JUNE 2025

QUARTER

SEPTEMBER

2025 QUARTER

CALENDAR 2025

TO DATE

Yaouré 64,859 77,750 57,441 200,050 2,415 3,004 2,959 2,800

Edikan 40,562 42,033 31,274 113,869 2,551 2,932 3,337 2,907

Sissingué 12,164 11,459 12,874 36,497 2,418 2,964 2,953 2,778

Group 117,585 131,242 101,589 350,416 2,462 2,977 3,075 2,832

Table 3: All-In Site Costs and Notional Cash Flow by Mine

MINE

ALL-IN SITE COST (US$/OUNCE) NOTIONAL CASHFLOW FROM OPERATIONS (US$ MILLION)

MARCH 2025

QUARTER

JUNE 2025

QUARTER

SEPTEMBER

2025 QUARTER

CALENDAR

2025 TO DATE

MARCH 2025

QUARTER

JUNE 2025

QUARTER

SEPTEMBER

2025 QUARTER

CALENDAR

2025 TO DATE

Yaouré 981 1,180 1,110 1,106 99 128 102 329

Edikan 1,177 1,482 1,603 1,405 57 56 57 170

Sissingué 2,736 2,584 2,745 2,686 -4 5 2 3

Group 1,209 1,417 1,463 1,366 152 189 161 503

Note: Numbers reported in Tables 1 to 3 are rounded to zero decimal places

3

NEWS RELEASE | SEPTEMBER 2025 QUARTER REPORT

PERSEUSMINING.COM

YAOURÉ GOLD MINE, CÔTE D’IVOIRE

Refer to Table 4 below for details of Yaouré Gold Mine’s operating and financial parameters during Q 1 FY26.

During the quarter, ore tonnes mined at Yaouré were lower by 20% and 55,405 ounces of were produced, 21% lower

than the prior quarter , in line with expected production. This reflects constrained mining at the base of CMA pit and a

change in ore source from the CMA open pit to the Yaouré open pit as per the mine plan . A final “good -bye” cut was

taken in the CMA open pit during the quarter. Gold grade for the remainder of the year is expected to be lower than Q1

due to the completion of the CMA pit and the Yaouré pit being the primary ore source.

CMA underground development commenced during the quarter with the firing of the Pauline portal. The Blika, Sika and

Assanou portals will commence early in Q2. CMA Underground will be the first mechanised underground mine in Côte

d’Ivoire.

The production cost in the quarter was US$829 per ounce with an AISC of US$1,110 per ounce. In total, 57,441 ounces of

gold from Yaouré were sold at a weighted average sale price of US$ 2,959 per ounce. This resulted in an average cash

margin of US$1,849 per ounce for the quarter. Notional operating cashflow generated by Yaouré during the quarter was

US$102 million, compared with US$128 million in Q4 FY25.

Ore milled tonnes were lower mainly due to maintenance shutdown for the Apron feeder reline and management of

crushed ore stockpile levels. Mill throughput averaged 450 tph, which was below the prior quarter’s 506 tph. Throughput

was reduced to manage the crushed stockpile levels ahead of crusher maintenance shutdown in the quarter . Mill run -

time was 94.2%, compared to 93.8% for the June quarter. Gold recovery remained comparable to the previous quarter .

AISC for Yaouré decreased by 6% compared to the previous quarter, most notably due to sustaining capital and royalties.

The decrease in sustaining capital primarily relates to timing of ongoing works on the tailings storage facility expansion

which was higher in Q4 FY25 and a decrease in royalties due to a slightly lower average gold price achieved during the

quarter. Mining unit cost was also higher due to reduction in mined tonnes and mining of fresh ore at bottom of CMA

open pit and longer haul distances. Higher processing unit costs were driven by the impact of lower milled tonnes on the

unit fixed costs offset by slight improvement in recovery. Although the unit costs improved, the gold sales were lower by

26% and the average realised sales price slightly reduced by 1% to US$2,959 per ounce compared to the previous quarter.

First ore from underground is expected later in the year.

4

NEWS RELEASE | SEPTEMBER 2025 QUARTER REPORT

PERSEUSMINING.COM

Table 4: Yaouré Quarterly Performance

PARAMETER UNIT MARCH 2025

QUARTER

JUNE 2025

QUARTER

JUNE 2025

HALF YEAR

SEPTEMBER 2025

QUARTER

CALENDAR 2025

YEAR TO DATE

Gold Production & Sales

Total material mined Tonnes 8,184,423 7,799,852 15,984,275 5,197,676 21,181,951

Total ore mined Tonnes 2,803,764 1,603,623 4,407,386 1,276,492 5,683,878

Average ore grade g/t gold 1.24 1.47 1.32 1.77 1.42

Strip ratio t:t 1.9 3.9 2.6 3.1 2.7

Ore milled Tonnes 1,060,202 1,042,307 2,102,509 935,745 3,038,254

Milled head grade g/t gold 2.16 2.24 2.20 1.96 2.12

Gold recovery % 93.6 93.8 93.7 94.0 93.8

Gold produced ounces 68,822 70,259 139,081 55,405 194,486

Gold sales1 ounces 64,859 77,750 142,609 57,441 200,050

Average sales price US$/ounce 2,415 3,004 2,736 2,959 2,800

Unit Production Costs

Mining cost US$/t mined 3.65 3.96 3.80 4.35 3.94

Processing cost US$/t milled 13.82 15.67 14.74 16.06 15.15

G & A cost US$M/month 2.59 3.21 2.90 2.76 2.85

All-In Site Cost

Production cost US$/ounce 760 809 785 829 798

Royalties US$/ounce 172 232 202 228 209

Sub-total US$/ounce 932 1,041 987 1,057 1,007

Sustaining capital US$/ounce 50 138 95 53 99

Total All-In Site Cost2 US$/ounce 981 1,180 1,082 1,110 1,106

Notional Cashflow from Operations

Cash Margin US$/ounce 1,434 1,824 1,655 1,849 1,694

Notional Cash Flow US$M 99 128 230 102 329

Notes:

1. Gold sales are recognised in Perseus’s accounts when gold is delivered to the customer from Perseus’s metal account

2. Included in the AISC for the quarter is US$ 3.2 million of costs relating to excess waste stripping. When reporting cost of sales, in line with accepted

practice under IFRS, this cost will be capitalised, and the costs amortised over the remainder of the relevant pit life

MINERAL RESOURCE TO MILL RECONCILIATION

Table 5 shows the reconciliation of processed ore tonnes, grade and contained gold relative to the Yaouré Mineral

Resource Estimate (MRE).

In Q1 FY26, ore tonnes processed were 17% higher than predicted, while the head grade was 10% lower, resulting in a

5% positive variance in contained gold compared with the block model estimate.

Increased proportion of Yaouré Ore continued where geological complexity is greater. Despite the lower grades, the six

and 12-month correlations show contained gold tracking within 5 –6% of the model, indicating that long -term

reconciliation remains stable

The ongoing implementation of the refined grade control and reconciliation workflows, introduced in late FY25,

continued to result in improved mill reconciliation in the quarter with September result being within normal ranges.

5

NEWS RELEASE | SEPTEMBER 2025 QUARTER REPORT

PERSEUSMINING.COM

Table 5: Yaouré Block Model to Mill Reconciliation

PARAMETER BLOCK MODEL TO MILL CORRELATION FACTOR

3 MONTHS 6 MONTHS 1 YEAR

Tonnes of Ore 1.17 1.22 1.29

Head Grade 0.90 0.87 0.82

Contained Gold 1.05 1.06 1.05

EDIKAN GOLD MINE, GHANA

Table 6 below summarises the key operating and financial parameters recorded at the Edikan Gold Mine during Q1 FY26

and in relevant prior periods.

Edikan produced 32,856 ounces of gold at a production cost of US$ 1,232 per ounce and an AISC of US$1, 603 per ounce

during the quarter. Edikan’s production was down by 15% and weighted average AISC was up 8% when compared to the

previous quarter. Gold sales of 31,274 ounces were 26% lower than in the prior quarter at a weighted average realised

gold price of US$3,337 per ounce. This was US$405 more than in the prior quarter, generating an average cash margin of

US$1,734 per ounce. Notional cashflow generated was up 2% to US$57 million for the quarter compared to Q4 FY25.  

Operating performance at Edikan during the quarter was in line with production expectations, with access issues to the

Nkosuo pit mostly resolved, enabling access for mining operations. Ore tonnes mined were lower due to fewer mining

areas following the completion of mining at the AG and Fetish pits over the last two quarters. Throughput averaged 831

tph, higher than prior quarter’s 794 tph; the head grade of processed ore was 0.67 g/t, down from 0.86 g/t due to heavier

reliance on low grade stockpiles to offset changes to mining sequences at Nkosuo; gold recovery was 87.7%, down from

87.9%; and mill run-time was 94%, compared to 93% for the previous quarter.

AISC for the quarter was US$1,603 per ounce, US$121 per ounce higher than the previous quarter due to higher

production cost and royalties. Production costs increased due to higher mining costs driven by additional waste stripping

at Nkosuo following pit face position changes to access new areas , increased explosives usage from changes in blast

patterns designs, higher unit fixed cost resulting from lower mined volume and additional rehandle cost from hauling

lower grade ore from stockpiles. Mining at Nkosuo was also impacted by wet weather resulting in the processing of lower

grade stockpiles, further impacting head grade and gold production for the quarter. Royalties per ounce increased due

to higher gold prices achieved quarter on quarter.

The current phase of AG Pit was completed during this quarter. Plans are progressing for further cutback of the Fetish pit

and the Esuajah North Pit in future periods.

6

NEWS RELEASE | SEPTEMBER 2025 QUARTER REPORT

PERSEUSMINING.COM

Table 6: Edikan Quarterly Performance

PARAMETER UNIT MARCH 2025

QUARTER

JUNE 2025

QUARTER

JUNE 2025

HALF YEAR

SEPTEMBER 2025

QUARTER

CALENDAR 2025

YEAR TO DATE

Gold Production & Sales

Total material mined Tonnes 2,942,218 3,323,268 6,265,486 3,232,048 9,497,534

Total ore mined Tonnes 1,815,604 829,623 2,645,227 733,998 3,379,225

Average ore grade g/t gold 0.86 0.79 0.84 0.85 0.84

Strip ratio t:t 0.6 3.0 1.4 3.4 1.8

Ore milled Tonnes 1,551,978 1,607,055 3,159,032 1,732,158 4,891,190

Milled head grade g/t gold 0.95 0.86 0.90 0.67 0.82

Gold recovery % 88.3 87.9 88.1 87.7 88.0

Gold produced ounces 41,668 38,865 80,534 32,856 113,389

Gold sales1 ounces 40,562 42,033 82,595 31,274 113,869

Average sales price US$/ounce 2,551 2,932 2,745 3,337 2,907

Unit Production Costs

Mining cost US$/t mined 6.09 4.92 5.47 5.39 5.45

Processing cost US$/t milled 10.28 10.60 10.45 9.16 9.99

G & A cost US$M/month 2.00 2.59 2.29 2.39 2.32

All-In Site Cost

Production cost US$/ounce 957 1,060 1,007 1,232 1,072

Royalties US$/ounce 199 299 247 324 269

Sub-total US$/ounce 1,156 1,358 1,254 1,555 1,341

Sustaining capital US$/ounce 21 123 70 48 64

Total All-In Site Cost2 US$/ounce 1,177 1,482 1,324 1,603 1,405

Notional Cashflow from Operations

Cash Margin US$/ounce 1,374 1,451 1,421 1,734 1,503

Notional Cash Flow US$M 57 56 114 57 170

Notes:

1. Gold sales are recognised in Perseus’s accounts when gold is delivered to the customer from Perseus’s metal account

2. Included in the AISC for the quarter is US$ 2.5 million of costs relating to excess waste stripping. When reporting cost of sales, in line with accepted

practice under IFRS, this cost will be capitalised, and the costs amortised over the remainder of the relevant pit life

7

NEWS RELEASE | SEPTEMBER 2025 QUARTER REPORT

PERSEUSMINING.COM

MINERAL RESOURCE TO MILL RECONCILIATION

Table 7 shows the reconciliation of processed ore tonnes, grade and contained gold relative to the Edikan MRE.

In Q1 FY26, ore tonnes processed were 11% below the block model prediction, while the head grade was 6% lower,

resulting in a 16% reduction in contained gold relative to the model estimate. Majority of mining during the quarter was

conducted in the Nkosuo pit, where challenging conditions from sustained rainfall impacted ore handling and increased

dilution, contributing to the lower-than-expected variances.

Despite the short-term variance, the six and 12-month trends show improved alignment, suggesting that the discrepancy

is largely temporary and related to operational factors rather than underlying model performance. Initial results from

recent grade control drilling at Nkosuo show that the reconciliation is likely to return to longer term performance trends.

Table 7: Edikan Block Model to Mill Reconciliation

PARAMETER BLOCK MODEL TO MILL CORRELATION FACTOR

3 MONTHS 6 MONTHS 1 YEAR

Tonnes of Ore 0.89 1.01 0.96

Head Grade 0.94 0.90 0.96

Contained Gold 0.84 0.91 0.92

SISSINGUÉ GOLD COMPLEX, CÔTE D’IVOIRE

Refer to Table 8 below for details of operating and financial performance achieved during Q 1 FY26 and relevant prior

periods, at the Sissingué Gold Complex. The Complex includes mining and processing operations at the Sissingué Gold

Mine, and mining operations at the Fimbiasso East and West pits located on the Fimbiasso Exploitation Permit, some 65

kilometres from the Sissingué processing facilities.

During the Q1 FY26 quarter, the Complex produced 11,692 ounces of gold at a production cost of US$2,458 per ounce

and weighted average AISC of US$2,745 per oun ce. Compared to the previous quarter, gold production was in line with

expectations, decreasing 3% despite higher head grade (Q1 FY26, 1.33g/t against Q4 FY25, 1.12g/t) while weighted

average AISC increased 6%. Total material mined was higher for the quarter primarily reflecting the ramp-up of Airport

West and Fimbiasso Satellite pits. A slight increase in ore tonnes mined was attributed to a higher strip ratio driven by

ongoing low grade waste stripping at Fimbiasso West, Sissingué Stage 4 and Airport West to access higher grade ore.

The increase in the AISC was driven by higher processing costs and royalties. The processing costs were higher due to

scheduled mill reline and surge bin apron feeder maintenance in Q1 FY26 which also resulted in lower ore tonnes milled

and slightly lower gold ounces produced. Royalties per ounce increase resulted from higher gold prices achieved during

the quarter.

Mill runtime at 91% was down from previous quarter’s 96% due to planned maintenance. Throughput averaged 150 tph,

below the 180 tph achieved in Q4 FY25, primarily due to a higher proportion of fresh ore in the blend. Gold recovery

improved marginally to 90.9%, from 88.3% in the previous quarter.

With a weighted average sales price of US$2,953 achieved, which is a slight decrease from the Q4 FY25 price of US$2,964,

the Complex cash margin was US$208 per ounce for the quarter compared to US$380 per ounce in the prior quarter. This

resulted in a notional cashflow of approximately US$2 million for the quarter.

8

NEWS RELEASE | SEPTEMBER 2025 QUARTER REPORT

PERSEUSMINING.COM

Table 8: Sissingué Quarterly Performance

PARAMETER UNIT MARCH 2025

QUARTER

JUNE 2025

QUARTER

JUNE 2025

HALF YEAR

SEPTEMBER 2025

QUARTER

CALENDAR 2025

YEAR TO DATE

Gold Production & Sales

Total material mined Tonnes 2,360,945 2,511,035 4,871,980 3,108,872 7,890,852

Total ore mined Tonnes 222,419 255,917 478,336 258,422 736,758

Average ore grade g/t gold 1.43 1.67 1.56 1.50 1.54

Strip ratio t:t 9.6 8.8 9.2 11.0 9.8

Ore milled Tonnes 382,521 379,238 761,759 301,791 1,063,550

Milled head grade g/t gold 1.03 1.12 1.08 1.33 1.15

Gold recovery % 87.4 88.3 87.9 90.9 88.9

Gold produced ounces 11,115 12,113 23,228 11,692 34,920

Gold sales1 ounces 12,164 11,459 23,622 12,874 36,496

Average sales price US$/ounce 2,418 2,964 2,682 2,953 2,778

Unit Production Costs

Mining cost US$/t mined 6.12 6.17 6.14 4.89 5.66

Processing cost US$/t milled 18.97 18.43 18.70 26.59 20.94

G & A cost US$M/month 1.66 1.78 1.72 1.84 1.76

All-In Site Cost

Production cost US$/ounce 2,401 2,298 2,347 2,458 2,384

Royalties US$/ounce 207 206 206 243 219

Sub-total US$/ounce 2,608 2,504 2,553 2,701 2,603

Sustaining capital US$/ounce 128 80 103 44 83

Total All-In Site Cost2 US$/ounce 2,736 2,584 2,657 2,745 2,686

Notional Cashflow from Operations

Cash Margin US$/ounce (319) 380 26 208 92

Notional Cash Flow US$M (4) 5 1 2 3

Notes:

1. Gold sales are recognised in Perseus’s accounts when gold is delivered to the customer from Perseus’s metal account

2. Included in the AISC for the quarter is US$2.1 million of costs relating to excess waste stripping. When reporting cost of sales, in line with accepted practice

under IFRS, this cost will be capitalised, and the costs amortised over the remainder of the relevant pit life

MINERAL RESOURCE TO MILL RECONCILIATION

Table 9 shows the reconciliation of processed ore tonnes, grade and contained gold relative to the Sissingu é MRE.

In Q1 FY26, ore tonnes processed were slightly below block model predictions ( -4%), while the grade was 14% lower,

resulting in a reduction of 18% in contained gold compared to expectations. The lower grade performance reflects a

continuation of higher dilution than anticipated when mining of narrow, variably mineralised structures at Sissingué

Main, Fimbiasso West and Airport West pits. The six and 12-month data demonstrate a longer trend that shows contained

gold is now tracking within 7% of the block model over the annual period.

Operational controls, including blast design refinement and ore mining initiatives remain in place to minimise dilution

and maintain anticipated operating limits when assessing model to mill reconciliation performance.