Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

PRU.TO ·

MARCH 2023 QUARTER REPORT Perseus Mining’s strong operating performance continues with 130,275oz gold produced at AISC of US$971/oz

Production Results

19 APRIL 202 3

NEWS RELEASE

PERSEUS MINING LIMITED

Level 2, 437 Roberts Road, Subiaco WA 6008

ABN: 27 106 808 986

1

MARCH 2023 QUARTER REPORT

Perseus Mining’s strong operating performance continues with

130,275oz gold produced at AISC of US$971/oz

PERTH, Western Australia/ April 19, 2023/Perseus Mining Limited (“Perseus” or the “Company”) (TSX & ASX: PRU) reports

on its activities for the three months’ period ended March 31, 2023 (the “Quarter”).

• Key Operating highlights for the March 2023 quarter and the nine months ending 31 March 2023 include:

PERFORMANCE

INDICATOR UNIT SEPTEMBER 2022

QUARTER

DECEMBER 2022

QUARTER

MARCH 2023 QUARTER FY 2023 TO DATE

Gold recovered Ounces 137,460 130,911 130,275 398,645

Gold poured Ounces 139,553 130,992 130,512 401,057

Production Cost US$/ounce 762 881 830 823

All-In Site Cost (AISC) US$/ounce 879 983 971 943

Gold sales Ounces 58,767 203,154 135,111 397,031

Average sales price US$/ounce 1,645 1,748 1,821 1,757

Cash margin US$/ounce 766 765 850 814

Notional Cashflow US$ million 112 101 111 324

– Gold production of 130,275 ounces was within 0.5% of December 2022 quarter production.

– US$971 per ounce weighted average AISC was 1.2% lower than the December 2022 quarter.

– Average sale price of gold sold (135,111 ounces) was US$1,821 per ounce, up 4% or US$73 per ounce compared

to December 2022 quarter.

– Average cash margin of US$850 per ounce of gold sold was 11% greater than in the prior quarter, reflecting both

an improved realised gold price and the AISC decrease.

– Notional cashflow from operations of US$111 million during the quarter, 10% more than last quarter (US$101

million).

– Perseus’s strong operating performance is forecast to continue in the June 2023 quarter with both gold

production and cost guidance for the 2023 June Half Year and Financial Year, expected to be achieved.

• Strong quarterly cashflows further strengthened Perseus’s financial position with available cash and bullion of

US$471 million, zero debt, net cash and bullion balance increased by US$66 million at quarter end.

• Perseus’s revolving corporate credit facility upsized to US$300 million during the quarter provides additional capacity

to fund its growth strategy while continuing to pay dividends to shareholders.

• Development activities continued at Meyas Sand Gold Project (MSGP) in Sudan, with confirmatory and sterilisation

drilling, Front-End Engineering and Design and site preparation, ahead of a possible FID during December 2023 Half

Year.

NEWS RELEASE | MARCH 2023 QUARTER REPORT

PERSEUSMINING.COM

• Organic growth activities including Mineral Resource drill outs and feasibility studies for MSGP and Yaouré’s CMA

Underground Project progressed on schedule. Results due in the September 2023 quarter.

• Perseus’s total economic contribution to its host countries of Ghana, Côte d’Ivoire and Sudan was ~US$156 million

(approximately 63% of revenue) during the quarter.

OPERATIONS

PRODUCTION, COSTS AND NOTIONAL CASHFLOW

Perseus’s three operating gold mines, Yaouré and Sissingué in Côte d’Ivoire, and Edikan in Ghana combined to produce

130,275 ounces of gold in the March 2023 quarter. The weighted average production cost across all three operations was

US$830 per ounce, while the weighted average AISC incurred during the quarter was US$971 per ounce of gold.

In the March 2023 quarter, combined gold sales totalled 135,111 ounces. The weighted average gold price realised was

US$1,821 per ounce, US$73 per ounce more than the December 2022 quarter price of US$1,748 per ounce.

Perseus’s average cash margin for the March 2023 quarter was US$850 per ounce, 11% better than the cash margin

achieved during the December 2022 quarter. Notional operating cashflow from operations was US$111 million,

US$10 million more than the December quarter, driven by the improved gold price achieved and reduced AISC.

These strong results summarised below in Tables 1, 2 and 3 below, confirm Perseus’s position as one of the world’s better

performing mid-tier gold producers thus far in 2023.

Table 1: Gold Production Summary by Mine

MINE

TOTAL GOLD RECOVERED (OUNCES) TOTAL GOLD POURED (OUNCES)

SEPTEMBER

2022 QUARTER

DECEMBER

2022 QUARTER

MARCH 2023

QUARTER

FISCAL YEAR

2023 TO DATE

SEPTEMBER

2022 QUARTER

DECEMBER

2022 QUARTER

MARCH 2023

QUARTER

FISCAL YEAR

2023 TO DATE

Yaouré 71,469 65,352 64,753 201,573 72,887 65,456 64,512 202,855

Edikan 52,127 53,850 53,720 159,696 53,342 53,615 54,096 161,053

Sissingué 13,864 11,709 11,803 37,376 13,325 11,919 11,904 37,148

Group 137,460 130,911 130,275 398,645 139,554 130,990 130,512 401,056

Table 2: Gold Sales by Mine

MINE

TOTAL GOLD SOLD (OUNCES) REALISED GOLD PRICE (US$ PER OUNCE)

SEPTEMBER

2022 QUARTER

DECEMBER

2022 QUARTER

MARCH 2023

QUARTER

FISCAL YEAR

2023 TO DATE

SEPTEMBER

2022 QUARTER

DECEMBER

2022 QUARTER

MARCH 2023

QUARTER

FISCAL YEAR

2023 TO DATE

Yaouré 9,000 126,174 67,578 202,751 1,748 1,726 1,800 1,751

Edikan 49,767 52,601 54,705 157,073 1,626 1,754 1,834 1,741

Sissingué - 24,379 12,828 37,207 - 1,847 1,877 1,857

Group 58,767 203,154 135,111 397,031 1,645 1,748 1,821 1,757

Table 3: All-In Site Costs (AISC) and Notional Cash Flow by Mine

MINE

ALL-IN SITE COST (US$/OUNCE) NOTIONAL CASHFLOW FROM OPERATIONS (US$ MILLION)

SEPTEMBER

2022 QUARTER

DECEMBER

2022 QUARTER

MARCH 2023

QUARTER

FISCAL YEAR

2023 TO DATE

SEPTEMBER

2022 QUARTER

DECEMBER

2022 QUARTER

MARCH 2023

QUARTER

FISCAL YEAR

2023 TO DATE

Yaouré 658 798 803 750 78 61 65 202

Edikan 1,060 1,058 1,067 1,062 30 38 41 108

Sissingué 1,336 1,672 1,458 1,480 7 2 5 14

Group 879 983 971 943 112 101 111 324

YAOURÉ GOLD MINE, CÔTE D’IVOIRE

Refer to Table 4 below for details of operating and financial parameters recorded at the Yaouré gold mine during the

March 2023 quarter and relevant prior periods.

During the quarter, Yaouré produced 64,753 ounces of gold at a production cost of US$677 per ounce and an AISC of

US$803 per ounce. The weighted average sales price of the 67,578 ounces of gold sold during the quarter was US$1,800

NEWS RELEASE | MARCH 2023 QUARTER REPORT

PERSEUSMINING.COM

per ounce, giving rise to a cash margin of US$998 per ounce. Notional operating cashflow generated during the quarter by

Yaouré was US$64.6 million, or US$3.9 million more than in the December 2022 quarter.

This performance places Yaouré in a strong position to achieve market guidance for the June 2023 Half Year of 117,500 to

130,000 ounces of gold production at an AISC of US$900 to US$1,000 per ounce.

The strong operating performance at Yaouré resulted from sound operating fundamentals that compared favourably with

the prior quarter, including head grade of processed ore (2.26 g/t compared to 2.17 g/t) and throughput rates (491 tph

compared to 481 tph). The mill runtime (91% compared to 94%), and gold recovery rates (92.4% compared to 93.6%) both

marginally lagged the prior period’s metrics but such variances are well within normal fluctuating operating ranges taking

into account scheduled maintenance shut downs and ore type variations.

Table 4: Yaouré Quarterly Performance

PARAMETER UNIT SEPTEMBER 2022

QUARTER

DECEMBER 2022

QUARTER

DECEMBER 2022

HALF YEAR

MARCH 2023

QUARTER

FY 2023 TO DATE

Gold Production & Sales

Total material mined Tonnes 6,991,354 9,369,467 16,360,821 8,716,713 25,077,534

Total ore mined Tonnes 1,326,508 1,280,881 2,607,389 1,280,134 3,887,523

Average ore grade g/t gold 1.92 1.80 1.86 1.92 1.88

Strip ratio t:t 4.3 6.3 5.3 5.8 5.5

Ore milled Tonnes 980,624 1,001,560 1,982,184 962,200 2,944,383

Milled head grade g/t gold 2.43 2.17 2.30 2.26 2.29

Gold recovery % 93.1 93.6 93.2 92.4 92.9

Gold produced ounces 71,469 65,352 136,821 64,753 201,573

Gold sales1 ounces 9,000 126,174 135,174 67,578 202,751

Average sales price US$/ounce 1,748 1,726 1,727 1,800 1,751

Unit Production Costs

Mining cost US$/t mined 2.87 2.97 2.92 2.88 2.91

Processing cost US$/t milled 12.18 12.00 12.09 12.67 12.28

G & A cost US$M/month 2.24 2.14 2.19 2.18 2.18

All-In Site Cost

Production cost US$/ounce 541 707 620 677 638

Royalties US$/ounce 93 78 86 104 92

Sub-total US$/ounce 635 785 706 781 730

Sustaining capital US$/ounce 23 13 18 22 19

Total All-In Site Cost2 US$/ounce 658 798 724 803 750

Notional Cashflow from Operations

Cash Margin US$/ounce 1,090 928 1,003 998 1,002

Notional Cash Flow US$M 77.9 60.7 137.2 64.6 201.9

Notes:

1. Gold sales are recognised in Perseus’s accounts when gold is delivered to the customer from Perseus’s metal account

2. Included in the AISC for the quarter is US$ 5 million of costs relating to excess waste stripping. When reporting cost of sales, in line with accepted

practice under IFRS, this cost will be capitalised and the costs amortised over the remainder of the relevant pit life.

MINERAL RESOURCE TO MILL RECONCILIATION

The reconciliation of processed ore tonnes, grade and contained gold relative to the Yaouré Mineral Resource block model

are shown in Table 5. During the March 2023 quarter, 9% more ore tonnes were processed at 4% lower grade for an overall

increase of 5% in ounces compared to the Mineral Resource model. In the previous six and twelve months, Yaouré has

produced 8% more metal than the Mineral Resource model predicted. The performance of the Yaouré Mineral Resource

model to date is considered satisfactory.

NEWS RELEASE | MARCH 2023 QUARTER REPORT

PERSEUSMINING.COM

Table 5: Yaouré Block Model to Mill Reconciliation

PARAMETER BLOCK MODEL TO MILL CORRELATION FACTOR

3 MONTHS 6 MONTHS 1 YEAR

Tonnes of Ore 1.09 1.13 1.18

Head Grade 0.96 0.91 0.91

Contained Gold 1.05 1.03 1.08

EDIKAN GOLD MINE, GHANA

Table 6 below summarises the key operating and financial parameters recorded at Edikan during the March 2023 quarter

and relevant prior periods.

Edikan produced 53,720 ounces of gold at a production cost of US$916 per ounce and an AISC of US$1,067 per ounce in

the March quarter, in line with last quarter’s performance when 53,850 ounces were produced at an AISC of $1,058 per

ounce. Gold sales of 54,705 ounces were 4% more than the prior quarter, at a weighted average realised gold price of

US$1,834 per ounce, generating an average cash margin of US$767 per ounce. In addition, notional cashflow of US$41.2

million was US$3.7 million better than in the prior period.

Following a challenging FY2022, Edikan has significantly improved the level and consistency of its performance and this is

expected to continue in the future. This is likely to result in the June 2023 Half Year guidance of 87,500 to 100,000 ounces

at an AISC of US$1,100 to US$1,200 per ounce being comfortably achieved.

Operating performance at Edikan was based on sound operating fundamentals generally in line with the prior quarter.

Quarter on quarter, head grade of processed ore increased by 9% (1.09 g/t compared to 1.02 g/t), gold recovery rates

were steady at 91.8% (compared to 91.4%), while mill run time (94% compared to 96%), throughput rates (824 tph

compared to 846 tph) were down slightly on the prior quarter but remaining within acceptable tolerance ranges.

Table 6: Edikan Quarterly Performance

PARAMETER UNIT SEPTEMBER 2022

QUARTER

DECEMBER 2022

QUARTER

DECEMBER 2022

HALF YEAR

MARCH 2023

QUARTER

FY 2023 TO DATE

Gold Production & Sales

Total material mined Tonnes 6,585,431 7,432,736 14,018,167 6,693,065 20,711,232

Total ore mined Tonnes 1,523,694 1,824,015 3,347,709 1,888,576 5,236,285

Average ore grade g/t gold 1.07 1.03 1.05 1.07 1.05

Strip ratio t:t 3.32 3.07 3.19 2.54 2.96

Ore milled Tonnes 1,736,623 1,791,242 3,527,865 1,671,960 5,199,824

Milled head grade g/t gold 1.04 1.02 1.03 1.09 1.05

Gold recovery % 89.7 91.4 90.5 91.8 91.0

Gold produced ounces 52,127 53,850 105,977 53,720 159,696

Gold sales1 ounces 49,767 52,601 102,368 54,705 157,073

Average sales price US$/ounce 1,626 1,754 1,692 1,834 1,741

Unit Production Costs

Mining cost US$/t mined 4.38 3.94 4.14 4.20 4.16

Processing cost US$/t milled 9.19 9.11 9.15 9.87 9.38

G & A cost US$M/month 1.49 1.61 1.55 1.51 1.54

All-In Site Cost2

Production cost US$/ounce 945 935 940 916 932

Royalties US$/ounce 97 117 107 127 114

Sub-total US$/ounce 1,042 1,052 1,047 1,043 1,046

Sustaining capital US$/ounce 18 6 12 24 16

Total All-In Site Cost2 US$/ounce 1,060 1,058 1,059 1,067 1,062

Notional Cashflow from Operations1

Cash Margin US$/ounce 566 696 633 767 680

Notional Cash Flow US$M 29.5 37.5 67.1 41.2 108.6

NEWS RELEASE | MARCH 2023 QUARTER REPORT

PERSEUSMINING.COM

Notes:

1. Gold sales are recognised in Perseus’s accounts when gold is delivered to the customer from Perseus’s metal account.

2. Included in the AISC for the December 2023 quarter is US$ 5 million of costs relating to excess waste stripping. When reporting cost of sales, in line

with accepted practice under IFRS, this cost will be capitalised and the costs amortised over the remainder of the relevant pit life.

MINERAL RESOURCE TO MILL RECONCILIATION

Reconciliation of processed ore tonnes, grade and contained ounces relative to the Edikan Mineral Resource block model

is in Table 7 below. During the March quarter, grade control has predicted additional tonnes (+9%), exact grade and more

ounces (+8%) when compared to the Mineral Resource Estimate (MRE). Over the past six months, Edikan has also

recorded more contained metal than predicted by the MRE, however, over a 12-month period, contained gold was slightly

under that predicted by the MRE (5%). Therefore, Perseus regards the overall outperformance as being within normal

industry standards.

Table 7: Edikan Block Model to Mill Reconciliation

PARAMETER BLOCK MODEL TO MILL CORRELATION FACTOR

3 MONTHS 6 MONTHS 1 YEAR

Tonnes of Ore 1.09 1.09 1.04

Head Grade 1.00 1.01 0.91

Contained Gold 1.08 1.10 0.95

SISSINGUÉ GOLD MINE, CÔTE D’IVOIRE

Table 8 below summarises the key operating and financial parameters recorded at the Sissingué gold mine during the

March 2023 quarter and relevant prior periods.

Table 8: Sissingué Quarterly Performance

PARAMETER UNIT SEPTEMBER 2022

QUARTER

DECEMBER 2022

QUARTER

DECEMBER 2022

HALF YEAR

MARCH 2023

QUARTER

FY 2023 TO DATE

Gold Production & Sales

Total material mined Tonnes 1,639,628 2,039,033 3,678,661 2,317,850 5,996,511

Total ore mined Tonnes 205,949 310,892 516,841 354,784 871,625

Average ore grade g/t gold 0.71 0.74 0.73 0.88 0.79

Strip ratio t:t 7.0 5.6 6.1 5.53 5.88

Ore milled Tonnes 389,357 410,365 799,722 468,679 1,268,401

Milled head grade g/t gold 1.21 0.97 1.09 0.85 1.00

Gold recovery % 91.2 91.9 91.5 91.6 91.6

Gold produced ounces 13,864 11,709 25,573 11,803 37,376

Gold sales1 ounces 0 24,379 24,379 12,828 37,207

Average sales price US$/ounce 0 1,847 1,847 1,877 1,857

Unit Production Costs

Mining cost US$/t mined 3.72 3.96 3.85 3.71 3.79

Processing cost US$/t milled 16.71 16.46 16.58 12.69 15.14

G & A cost US$M/month 1.39 1.31 1.35 1.46 1.43

All-In Site Cost 2,3

Production cost US$/ounce 1,209 1,602 1,389 1,276 1,354

Royalties US$/ounce 122 63 95 121 103

Sub-total US$/ounce 1,331 1,665 1,484 1,397 1,457

Sustaining capital US$/ounce 5 7 6 61 23

Total All-In Site Cost US$/ounce 1,336 1,672 1,490 1,458 1,480

Notional Cashflow from Operations 3

Cash Margin US$/ounce 309 174 357 419 377

Notional Cash Flow US$M 7.1 2.0 9.1 4.9 14.0

Notes:

1. Gold sales are recognised in Perseus’s accounts when gold is delivered to the customer from Perseus’s metal account.

NEWS RELEASE | MARCH 2023 QUARTER REPORT

PERSEUSMINING.COM

2. Included in the AISC for the December 2023 quarter is US$1 million of costs relating to excess waste stripping. When reporting cost of sales, in line

with accepted practice under IFRS, this cost will be capitalised and the costs amortised over the remainder of the relevant pit life.

3. For the March 2023 Quarter, US$4.2m (FY2023 to date, US$4.6m), relating to pre-commercial-production operating costs at Fimbiasso, have been

capitalised out of All-In-Site-Costs. Furthermore, for these periods, the number of oz produced used for the AISC, cash margin and notional cash flow

calculations has been reduced by 269oz, also relating to Fimbiasso production.

During the quarter, Sissingué produced 11,534 ounces of gold at a production cost of US$1,276 per ounce and an AISC of

US$1,458 per ounce. A further 269 ounces of gold were produced from ore mined from the Fimbiasso deposit, as these

satellite pits ramp up into commercial production, for a total of 11,803 ounces for the Sissingué Gold Complex.

Most of the ore processed at Sissingué was drawn from low-grade stockpiles as well as from the remnants of West Arm,

Binkadi and Bagoé pits adjacent to the Sissingué plant.

Mining of higher-grade ore commenced during the quarter in the satellite pits at Fimbiasso East and West, however,

mobilisation delays experienced by our haulage contractor limited the amount of material that was transported back from

Fimbiasso to the Sissingué plant for processing.

Notwithstanding this, overall production performance by Sissingué during the quarter was very solid in most areas with

only head grade (0.85g/t) down relative to the prior quarter and below targets as a result of the mobilisation issues

referred to above. This situation has been resolved subsequent to the end of the quarter and material improvements in

the grade of processed ore is expected in coming periods with the inclusion of higher grade Fimbiasso ore in the mill feed.

Other key operating parameters during the quarter including runtime (97%), and throughput rate (224 tph) were both

better than the prior quarter while the recovery rate (91.6%) was fractionally lower than the prior quarter largely due to

the fall in head grade of ore processed.

The AISC of US$1,458 per ounce was slightly improved on the previous quarter despite the delay in declaring commercial

production at Fimbiasso. Not included in this AISC is pre-commercial-production operating costs incurred on Fimbiasso of

$4.2m, which has been capitalised as (non-sustaining) development expenditure.

The weighted average sales price of the 12,828 ounces of gold sold during the quarter was US$1,877 per ounce, giving rise

to an average cash margin of US$419 per ounce. Notional cashflow generated by the mine during the quarter totalled

US$4.9 million.

BAGOÉ MINING LEASE

Perseus’s environmental and social impact assessment (“ESIA”) for its proposed Bagoé mining operation was approved by

the environmental regulator (ANDE) and has been lodged with the Department of Mines, Petroleum and Energy together

with the Definitive Feasibility Study of an operation located on the Bagoé exploration permit. Required community

consultation processes are being conducted and approval is expected during the next few months. The Exploitation Permit

should be granted thereafter and a Mining Convention covering the operation negotiated in due course. Construction of

infrastructure required to support a mining operation on the Bagoé lease will commence as soon as possible following

receipt of the Mining Lease.

MINERAL RESOURCE TO MILL RECONCILIATION

The reconciliation of processed ore tonnes, grade and contained ounces relative to the Sissingué Mineral Resource block

model is in Table 9 below. During the last three months, grade control has predicted additional tonnes (+18%) at a

reduced grade (-10%) resulting in an increase in overall ounces (+6%) when compared to the Mineral Resource Estimate

(MRE). This trend has continued over the past six- and 12-month periods, with Sissingué producing overall more metal

than the Mineral Resource model predicted. Perseus regards the overall outperformance as being within normal industry

standards.

Table 9: Sissingué Block Model to Mill Reconciliation

PARAMETER BLOCK MODEL TO MILL CORRELATION FACTOR

3 MONTHS 6 MONTHS 1 YEAR

Tonnes of Ore 1.18 1.15 1.20

Head Grade 0.90 0.97 0.98

Contained Gold 1.06 1.11 1.19

NEWS RELEASE | MARCH 2023 QUARTER REPORT

PERSEUSMINING.COM

NEWS RELEASE | MARCH 2023 QUARTER REPORT

PERSEUSMINING.COM

GROUP GOLD PRODUCTION AND COST MARKET GUIDANCE

Group gold production and AISC’s for the June 2023 Half Year and the full 2023 Financial Year are as shown below in Table

10. This guidance data remains unchanged from that previously provided to the market.

Table 10: Production and Cost Guidance

PARAMETER UNITS FISCAL YEAR 2023 TO DATE

(ACTUAL)

JUNE 2023 HALF YEAR

(FORECAST)

2023 FINANCIAL YEAR

(FORECAST)

Yaouré Gold Mine

Production Ounces 201,573 117,500 to 130,000 254,300 to 266,800

All-in Site Cost USD per ounce 750 900 to 1,000 850 to 900

Sissingué Gold Mine

Production Ounces 37,376 25,000 to 30,000 50,600 to 55,600

All-in Site Cost USD per ounce 1,480 1,750 to 1,850 1,625 to 1,675

Edikan Gold Mine

Production Ounces 159,696 87,500 to 100,000 193,500 to 206,000

All-in Site Cost USD per ounce 1,062 1,100 to 1,200 1,075 to 1,125

PERSEUS GROUP

Production Ounces 398,645 230,000 to 260,000 498,370 to 528,370

All-in Site Cost USD per ounce 943 1,000 to 1,200 1,000 to 1,100

SUSTAINABILITY

SUSTAINABILITY GOVERNANCE

During the quarter, Perseus continued to strengthen its sustainability governance through the following:

• Continued to work to improve our Group safety performance by holding several training seminars and workshops. This

included “Safely Home Ev ery Day” (SHED) Leadership Workshops at each of our operations, , skills training for

supervisors, and ongoing field coaching for our employees and contractors.

• Conducted regular environmental workplace inspections across all sites, including daily inspections for Sudan with the

intention of educating the workforce.

• Finalised the Environmental Impact Statement (EIS) for the Bagoé project near Sissingué, with the EIS report validated

and recommendations addressed.

• Received approval for an occasional explosive use arrangement and a temporary fuel farm permit for the Fimbiasso

project near Sissingué. Application for permanent permits has been lodged and approval is currently awaited.

• Conducted road safety sessions with the communities which will be impacted by ore haulage from Fimbiasso.

SUSTAINABILITY PERFORMANCE

This quarter, Perseus continued its strong sustainability performance relative to objectives and targets, as shown below in

Table 11 and summarised as follows:

• Safety:

– Safety performance across the portfolio has improved this quarter, with the Group Total Recordable Injury

Frequency Rates (TRIFR) decreasing from 1.43 at the end of the December quarter to 1.23 at the end of March

2023. However, this remains higher than the FY23 threshold of 1.10 and target of 0.8. There were only two

recordable injuries for the quarter across all sites, with one Restricted Work Injury recorded for Sudan in March

2023, and one Lost Time Injury recorded for Yaouré in February 2023, where an EPSA worker fell and broke a

wrist.

– Lost Time Injury Frequency (LTIFR) across the Group remained stagnant at 0.25. Most sites are maintaining their

safety milestones of no Lost Time Incidents, except for Yaouré.